ML18153C249

From kanterella
Jump to navigation Jump to search
Insp Rept 50-280/90-18 & 50-281/90-18 on 900416-20. Violations Noted.Major Areas Inspected:Radiation Protection Activities Made to Review Activities Associated W/Airborne Radioactivity Event in Licensee Auxiliary Bldg on 900326
ML18153C249
Person / Time
Site: Surry  Dominion icon.png
Issue date: 05/25/1990
From: Potter J, Wright F
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML18153C247 List:
References
50-280-90-18, 50-281-90-18, NUDOCS 9006140473
Download: ML18153C249 (11)


See also: IR 05000280/1990018

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTA STREET, N.W .

ATLANTA, GEORGIA 30323

Report Nos.: 50-280/90-18 and 50-281/90-18

Licensee:

Virginia Electric and Power Company

Glen Allen, VA 23060

Docket Nos.: 50-280 and 50-281

License Nos.: DPR-32 and DPR-37

Facility Name: Surry 1 and 2

Inspection Conducted: April 16-20, 1990

Jnspector:~~~/:;fi:_ _______________ _

Approved by:

~----------------------

J.

. Potter, Chief

Scope:

Facilities Radiation Protection Section,

Emergency Preparedness and Radiological

Protection Branch*

Division of Radiatfon Safety and Safeguards

SUMMARY

This unann6unced inspection of radiation protection activities was made to

review activities associated with an airborne radioactivity event in the

licensee's Auxiliary Building (AB) on March 26, 1990. A cursory review of

licensee's on-going As Low As Reasonably Achievable (ALARA) activities was also

made.

Results:

One violation was identified for failure to utilize process or other

engineering controls, to the extent practical, to limit* exposures to

concentrations of radioactive materials in air to levels below the allowable

concentrations specified in 10 CFR Part 20. The inspector determined that the

violation resulted from operation and engin~ering deficiencies. The engineering

and operating procedure problems were reported to _resident .inspectors for

review.

-

Management support and increased management and worker involvement in the

licensee's ALARA program activities appeared to be improving worker awareness

of ALARA objectives. Overall, the licensee's radiation protection staff

appeared to be generally effective in protecting the health and safety of the

workers.

7 -

9005:":::0 _

0006140~~~ hsooo2~u

~OR

ADUGK -

PDC

G\\

REPORT DETAILS

1. Persons Contacted

Licensee Employees

  • W. Benthall, Supervisor, Licensing
  • R. Bilyen, Licensing Engineer
  • M. Biron, Supeivisor, Radiological Engineering
  • D. Christian, Assistant Station Manager, Operations and Maintenance
  • W. Cook, Operations Supervisor, Radiation Protection
  • D. Erickson, Superintendent, Radiation Protection
  • E. Grecheck, Assistant Station Manager

~D. Hart, Supervisor, Quality Assurance

  • M. Kansler, Station Manager
  • J. McCarthy, Superintendent, Operations
  • L. Morris, Radwaste Superintendent, Radiation Protection
  • T. Sowers, Superintendent

T. Steed, Station ALARA Coordinator

  • W. Thornton, Directors Corporate Health Physics and Chemistry

Other licensee employees contacted during this inspection included

engineers, craft, technicians, and administrative personnel.

Nuclear Regulatory Commission (NRG)

  • ~. Holland, Senior Resident Inspector

S. Tingen, Resident Inspector

  • J. York, Resident Inspector
  • Attended exit interview held April 20, 1990

2. Onsite Followup of Events at Operating Power Reactofs (93702)

a.

Background

On March 26, 1990, the inspector, as a member of an on-going

maintenance team inspection (MTI), was touring the licensee's

Auxiliary Building

(AB) reviewing radiological postings and

radiological protection activities.

While the inspector was in the

AB the licensee failed to maintain control of radioactive

contaminati6n on the -2 and 13 foot (ft)_ elevations of the AB.

The

event resulted in the contamination of 10,000 square feet (ft2) of

clean Radiological Control Area (RCA) floor space, three personnel

contaminations, and seven personnel having positive whole body counts

in excess of one percent maximum permissible organ burden (MPOB) but

less than three percent MPOB. The inspector reviewed the licensee's

controls and recovery activities following the event and discussed

the activities and findings with the licensee's staff.

The

licensee's radiation protection staff responded quickly to the event

2

limiting additional contaminated area and personnel contaminations.

During the MTI,.the inspector determined that a series of operational

activities apparently had caused the airborne contamination event. At

a MTI pre-ex it briefing, the 1 i censee was informed that there

appeared to be a violation of NRC requirements for controlling

airborne radioactivity resulting from operational activities on

March 26, 1990.

-

b.

Event Chronology (All Times Are Approximate)

March 23, 1990 _

11: 00 AM - The 1 i censee began transferring the contents of a spent

fuel pool ion exchange filter located in the licensee's AB to a High

Integrity Container (HIC) located in the licensee's Decon Building

(DB). The spent filter resin contained 156 curies of radioactivity,

primarily_from the cobalt-60 radioisotope.

03:00 Prt. -

Following the resin transfer, the licensee began

dewat.ering the HIC in accordance with licensee procedures. During the

dewatering process, the licensee's dewatering pump discharged into a

floor drain, in an area the licensee calls Ion Exchange Alley (Ix

Alley), on the -2 ft elevation of the 1icensee's AB.

The Ix Alley

was located along the north wall of the AB and contained the shielded

pl ant ion ext hanger filters for primary systems.

The dewateri ng

continued throu~hout the weekend.

09:00 PM - An entry was.made into the Ix Alley to conduct a survey

and attach a reach rod back onto a valve. A radiological survey made

during the entry showed contamination levels up to 16 million

disintegrations per minute (dpm) per 100 square centimeters (cm 2 ) on

the floor. The measured airborne radioactivity was at a concentration

1.1 times the applicable maximum permissible concentrations (MPCs)

specified in 10 CFR Part 20, Appendix B, for.a weekly exposure of

40 hours4.62963e-4 days <br />0.0111 hours <br />6.613757e-5 weeks <br />1.522e-5 months <br />.

March 26, 1990

10:-00 AM - The licensee was rece1v1ng new fuel into the Fuel Handling

Building (FHB). The activity required the licensee to open an

external roll-up door of the building. The outside temperature was

cool and the fuel handling personnel requested operations provide

building heating.

..

3

10:35 AM - Operations ~tarted a FHB ventilation supply fan (l-VS-F-6)

to provide requested heating. The operator did not start additional

exhaust fans.

~

02:45 PM - Health Physics (HP) Technician and Planner entered the Ix

Alley in the AB for a pre-job inspection for repairing valve reach

- rods.

03:00 PM - A Decon Technician, assigned to maintain the clean area

outside the gate to Ix Alley, during the pre-job *inspection, measured

radioactive *contamination up to 200,000 dpm on a large area swipe

(masslinn cloth) and notified the HP Shift Supervisor. HP_ personnel

were dispatched *to assess the radiological conditions and secure

access to any contaminated areas. Initial surveys found contaminated

clean areas on the -2 and 13 ft elevations of the licensee's AB.

03:20 PM - Affected areas were barricaded and posted.

03:25 PM - HP Technician and Planner left the Ix Alley.

  • 04:30 PM -

FHB ventilation supply fan 1-VS-F-6 stopped as requested

by HP.

04:40 PM - Dewatering of the HIC was stopped.

05:00-06:00 PM - Licensee began preparation for decontamination

efforts for the -2 foot elevation of the AB.

c.

Radiation Protection Activities for Entry into Ix Alley on March 26,

1990

On March 26, 1990, the licensee activated Radiation Work Permit (RWP)

90-1-0014 for entry ,into the Ix Alley.

A Planner required access to

the area for a pre-job walk down, to repair valve reach rods. The

Planner was accompanied by a HP Technician *

The most recent radiation surveys of the Ix.Alley had been made three

days earlier on a March 23, 1990 entry. The licensee's surveys showed

the contamination levels were elevated and the airborne radioactivity

was higher than normally measured. The measured radioactive

contamination was up to 1.6 E7 dpm/100 cm2 and the measured airborne

radioactivity was 1.1 times the MPC.

The contamination levels in the

Ix Alley measured in previous months had varied from 1.5 E5 to 2.0 E6

dpm/100 cm2 * The airborne radioactivity in the area was usually less

than MPC and had only exceeded MPC values twice in recent months. The

highest airborne radioactivity measurement in the area in 1990 was

7.5 times MPC, measured in January. While these activities were

elevated, they were not significantly greater than those found there

occasionally.

4

The RWP required full dress protective clothing with an outer hot

particle suit and tight fitting full face piece respirator for the

task. The respirator chosen provided a protection factor of 50 for

airborne radioactive particulates. The licensee's RWP requirements

appeared to be adequate for radiological conditions and the planned

task. The licensee held a pre-job briefing and the workers were

advised of the radiation levels (50-500 millirem per hour) and

contamination levels (1.6 E7 dpm/100 cm 2 ).

On March 26, 1990, when the HP Technician and the Planner entered the

Ix Alley (approximately 2:45 PM), they entered through Gate 2 where

the licensee had a plastic air lock constructed inside the Ix Alley.

The licensee reported that it was standard practice to assign a

Decon Technician to maintain the clean area outside Gate 2 to prevent

the spread of contamination on the -2 foot elevation of the AB. The

licensee set up a buffer zone at the gate and a Decon Technician was

dressed in paper coveralls, rubber shoe covers, and rubber gloves.

While the Planner and HP Technician performed their work in the Ix

Alley the Decon Technician performed a contamination survey of the

clean area outside the gate using a masslinn mop to take a large area

swipe. The Decon Technician detected radioactive contamination up to

2.0 ES dpm on the masslinn cloth. The Decon Technician notified the

HP Shift Supervisor who sent a HP Technician to evaluate the

situation.

The licensee had secured and posted access to the 13 and -2 foot

elevations of the AB by 3:20 PM and all personnel were evacuated from

the two floors, except for the Planner and HP Technician, who exited

the Ix Alley at approximately 3:25.

d.

Radi~tion Protection Activities Following the Event.

The licensee's initial response to the event was timely and orderly.

The licensee's radiation protection personnel evacuated all persons

on the -2 and 13 ft elevations and barricaded, posted, and restricted

access to affected areas. Personne 1 contaminations were quickly

attended to and internal assessments were made in accordance with

licensee procedures. Access to the Ix Alley was cancelled until

licensee personnel completed initial investigation of the event.

The radiological surveys made by the licensee's staff, during the

entry into the Ix Alley, detected contamination levels up to

4.6 E7 dpm/100 cm2 and air activity 99.3 times the allowable MPC of

10 CFR Part 20, Appendix B for a 40 hour4.62963e-4 days <br />0.0111 hours <br />6.613757e-5 weeks <br />1.522e-5 months <br /> exposure.

The radiological surveys made by the licensee's staff, in clean areas

on the -2 foot elevation of the AB, detected contamination levels up

to 119,000 dpm/100 cm2 and airborne radioactivity 3.3 times the

allowable MPC of 10 CFR 20, Appendix B.

7

higher than most resin processed at the facility .and contained 156

curies, most of which was cobalt 60.

On the evening of March 23, 1990, a licensee represent~tive, who had

made an entry into the Ix Alley to perform a radiological survey,

observed that the floor drain in the Ix Alley had apparently backed

up, puddled, and drained. Licensee representatives reported that the

drain had contained a sock type filter that had apparently restricted

the floor drains ability to drain all of the liquid initially

de 1 i vered to the drain from the dewa teri ng pump in the DB. The

highest level of contamination found during the March 23, 1990

radiological survey was 1.6 E7 dpm/100 cm2 * On March 26, 1990, the*

licensee detected up to 4.6 E7 dpm/100 cm2 *

The licensee concluded, that highly contaminated radioactive liquids

from the spent resin dewatering hose overflowed the AB floor drain

in the Ix A 11 ey and became the source for the airborne materi a 1

detected there on March 26, .1990.

The inspector inquired about an engineering evaluation for the rubb~r

hose that was used as the dewatering *drain. The licensee was unab,le

to find any engineering evaluations or documentation on installation

and. acceptability of using a 300 foot rubber hose used in draining

high radioactivity liquids between the DB and AB. However, the

insp~ctor was told that the hose had been used for at least 15 years.

The inspector determined that the licensee was aware of the

r~diological problems that existed with a hose discharging highly

contamin~t~d fluids from a 300 foot rubber hose into a floor drain

for a period of 15 years. However, at the time of the March 26, 1990

event, the licensee had no planned changes for the dewatering drain.

Following the March 26, 1990 contamination event, the licensee

planned to install a permanent drain line for dewatering activities.

The resident inspector was briefed on the matter for further review.

g.

Building Ventilation Activities

As stated in the previous paragraph, the licensee's Decon, Fuel

Handling, and Auxiliary Buildings are all connected with a pipe

tunnel. The licensee's ventilation systems were designed to maintain

these buildings at a negative _pressure to ensure air leakage was

always into the buildings to prevent unfiltered air from escaping

into the environment. Ventilation airflow was designed to move air

within the buildings from area~ least likely to be contaminated to

areas having a higher probability of contamination to reduce the

probability of spreading radioactive material to cleaner areas.

The inspector determined that the 1 icensee has had contamination

control problems with the -2 ft elevation of the licensee's AB for

years and the Ix Alley also has been a high radiation area. The high

radiation in the area had prevented the licensee from recovering or

decontaminating the Ix Alley floor space on the -2 foot elevation. To

8

contain the radioactive contamination from the Ix Alley and connected

pipe tunnel, the licensee had sealed off some of the ventilation air

flow paths at gates connecting the pipe tunnel to the FHB, DB, and

AB. The licensee sealed or air-dammed HP Gate 22 in the DB and

erected a plexiglas wall across the north end of the AB on* the

-2 foot elevation.

-

The inspector requested a review of the 1 i censee' s engineering

evaluation for the plexiglas wall, to see if it had addressed the

walls effect on the building's ventilation systems. The licensee

reported that there had not been an engineering evaluation on the

wall and that it was constructed in 1985 with a plant work request.

The inspector discussed the findings with the resident inspector for

review.

On morning of March 26, 1990, the licensee Wis receiving new fuel

into the FHB; The ambient temperature was cool and the receiving

operation required a roll up door be opened. The-workers receiving

the new fuel requested operations provide some heat to the FHB.

Operations responded and began operation of l-VS-F-6, a heating

supply of the FHB Ventilation System.

Operating Procedure OP-21.2.5, Placing Fuel Building .Ventilation

System In Service; revision dated October 27, 1983, stated, in part,

not to operate area supply fans unless associated area exhaust fans

are operating. The licensee's investigation of t~e event determined

that when 1-VS-F-6 was started, no additional exhaust fans were

started. That action caused an increased pressure in the FHB which

subsequently increased pressure in the connecting pipe tunnel and its

effluents, which included the Ix Alley. It appeared that the

increased pressure in the Ix Alley provided a motive air stream for

transporting the radioactive contamination in the tunnel and Ix Alley

areas. The inspector did not investigate or assay the adequacy of

operations actions but did discuss the event with the NRC Resident

Inspector for further review.

The licensee was also aware that positive air pressures from the

connecting tunnel caused radioactive material to migrate from

enclosures in the auxiliary and decontamination buildings. The

licensee had processed Engineering Work Request (EWR)89-492 in July

1989, which requested the employment of an outside contractor,

experienced in balancing ventilation systems, to correct AB flow

imbalance. Additionally, Health Physics Staff initiated EWR 89-701 in

August 1989, requesting that an air dam be. installed in the

connecting pipe tunnel to redute contamination migration from the Ix

Alley.

h.

Licensee Investigation, Short Term Corrective Actions, Long Term

Corrective Action Recommendations, and Root Cause Conclusions for the

March 26, 1990 .A.irborne Radioactivity Event

9

The licensee documented the event in Station Deviation Report

Sl-90-477. In the licensee's final report, the licensee reported that

the loss of contamination control resulted from the high levels of

radioactive contamination behind Gate 2 becoming airborne due to the

increased turbulent flow from the FHB ventilation fan 1-VS-F6 and the

opening of Gate 2. The contributing factors to the event were:

0

0

A temporary HIC dewatering flow path backed up causing gross

contamination of surrounding floor area.

A pre-~xisting ventilation system flow imbalance between the AB

and the Spent Fuel Building.

The licensee initiated the following short term corrective actions

following the event:

0

0

Engineering prepared a RCA ventilation matrix for use by

operators to ensure that RCA ventilation flows are always

properly balanced.

RWPs issued for movement of radioactive materials with temporary

hook-ups would require safety reviews.

The licensee developed the following long term corrective actions

following the event:

0

0

Licensee initiation of a Engineering Work Request to correct

ventilation flow imbalances.

Purchase and utilize continuous air monitoring equipment as the

equipment becomes available.

The licensee's radiation protection staff submitted a request for an

EWR requesting the installation 6f an air dam in the FHB pipe tunnel

before the event. The licensee approved a Engineering Work Request to

install an air dam April 19, 1990.

i. Regulatory Evaluation and Conclusion

10 CFR Part 20, Section 103(b)(l) requires that the licensee, as a

precautionary procedure, use process or other engineering controls,

to the extent practicable, to limit concentrations of radioactive

materials in air to levels below those which delimit an airborne

radioactivity area as defined in 10 CFR 20.203(d)(l)(i i).

10

CFR Part 20, Section 203(d)(l)(ii) defines an airborne

radioactivity area as any room, enclosure or operating area in which

airborne radioactive material composed wholly or partly of licensed

material exist in concentrations which, averaged over the number of

hours in any week during which individuals are in the area, exceed

10

25 percent of the amounts specified in Appendix B, Table I, Column 1

of Part 20.

Contrary to the requirements specified a.bove, the licensee failed to

utilize process or other engineering controls to the extent

practicable to limit airborne radioactivity material below 25 percent

of the amounts specified in Appendix B, Table I, Column 1, in that,

on March 26, 1990, the licensee's use of a floor drain for

radioactive waste dewatering activities enabled highly contaminated

fluids to become a source for airborne radioactive material arid the

licensee's building ventilation configurations and inadequate

.ventilation operating procedures provided the motive force for moving

loose surface radioactive material from the Ix Alley throughout the

licensee's -2 and 13 ft elevations of the AB as airborne radioactive

material. The subsequent airborne radioactivity caused licensee

personnel to be exposed to concentrations of airborne radioactivity

two times. the activities specified in Appendix B, Table I, Column 1,

of Part 20, in an airborne radioactivity area of the licensee's AB,

having a concentration 99 times the specified Appendix B limit while

wearing a respirator having a protection factor of 50.

The inspector informed licensee management that failure to use

process or other engineering controls for radioactive waste to limit

exposures to airborne radioactive material was an apparent violation

of 10 CFR Part 20, Section 103(b)(l) (50-280, 281/90-18-01).

The inspector concluded that the licensee's root cause assessment

appeared to be correct and the licensee's proposed corrective actions

could help prevent a similar event. Violations of NRC requirements

for protecting workers from airborne radioactivity were identified;

however, there did not appear to be problems in the licensee's

radiation protection program.

The violations were created from

ventilation problems that the licensee had been experiencing for

several years and operating procedures that were not specific enough

to prevent excessive building ventilation supply without appropriate

exhaust.

One violation was id~ntified.

3.

Surveys, Monitoring, and Control of Radioactive Material

10 CFR 20.201(b) requires each licensee to make or cause to be made such

surveys as (1) may be necessary for the 1 i censee to comply with the

regulations and (2) are reasonable under the circumstances to evaluate the

extent of radioactive hazards that may be present.

The inspector reviewed the plant procedures which established the

licensee's radiological survey and monitoring program and verified that

the procedures were consistent with regulations, Technical Specifications,

and good HP practices.

..

..

11

The inspector reviewed selected records _of radiation_ and contamination

surveys performed in March and April, 1990 and discussed the survey

results with licensee representatives. During tours of the plant the

inspector observed health physics technicians performing radiation and

contamination surveys.

The inspector performed independent radiation surveys in the AB and

verified that the areas were properly posted.

No violations or deviations were identified.

4.

Program for Maintaining Exposures As Low As Reasonably Achievable (ALARA)

10 CFR 20.lc states that persons engaged in activities under licenses

issued by the NRC should make every reasonable effort to maintain

radiation exposures ALARA.

The recommended elements of an ALARA program

are contained in Regulatory Guide 8.8, Information Relevant to Ensuring

that Occupationa 1 Radiation Exposure at Nuclear Power Stations wi 11 be

ALARA, and Regulatory Guide 8.10, Operating Philosophy for Maintaining

Occupational Radiation Exposures ALARA.

5.

The inspector attended a monthly Surry Station ALARA Committee meeting

held Apri 1 16, .1990. In addition to routine activities and reviews. of

ALARA goals, initial Department Exposure Reduction Plans were submitted to

the Committee. The plans were submitted by Maintenance, Radiological

Protection, Operations, and Site Services Departments. The plans were

schedu_l ed for implementation in December, 1990. The Exposure Reduction

Plans appeared to be aggressive and workable. Management support for the

ALARA program was evidence by those plans and commitments.

No violations or deviations were identified.

Exit Interview

The inspection scope and findings were summarized on April 20, 1990, with

those persons indicated in Paragraph 1. The inspector described th~ areas

inspected and discussed in detail the inspection results listed below.

Dissenting comments were- not received from the licensee. Proprietary

information is not contained in this report.

The inspector reported that the Radiation Protection-Staff's response to

the airborne radioactivity event that occurred on March 26, 1990, appeared

to be appropriate and effective in protecting the health and safety of the

workers. The inspector reported that worker awareness of ALARA objectives

appeared to be improving through increased staff participation and

involvement in the ALARA program.

The inspector reported that engineerini controls and records of engineer

reviews for use of a temporary radioactive waste drain and constructing of

plant containments affecting ventilation systems and operating procedures

12

for proper opera ti on of venti 1 at ion systems appeared to be a program*

weaknesses.

Two apparent violations were discussed at the exit meeting. One of the

violations, concerning the selection of respiratory protection equipment.

to meet the requirements of 10 CFR Part 20.103(c) was reviewed and

withdrawn.

During a telephone conversation on May 25, 1990, between

F. Wright of the NRC and D. Erickson of Virginia Electric and Power

Company, the licensee v,*as informed there would not be a violation issued

for failure to select respiratory protection equipment providing a

prot~ction factor greater tha*n the multiple of airborne radioactivity

exceeding the quantities specififed in Appendix B, Table I, Column 1 of

Part 20 because the airborne radioactivity concentrations the licensee

workers were exposed to on March 26, 1990, were not expected by the

licensee.

The second violation is summarized below.

Item Number*

50-280, 281/90-18-01

Description and Referen~~

Violation - Failure to use process and other

engineering .controls to limit exposures to

airborne radioactivity (Paragraph 2) .