ML18153B168

From kanterella
Jump to navigation Jump to search
Insp Repts 50-280/94-32 & 50-281/94-32 on 941027-1114. Violations Noted.Major Areas Inspected:Maint & Surveillance Activities,Performance Trend Analysis & Timeliness/ Effectiveness of Corrective Actions
ML18153B168
Person / Time
Site: Surry  Dominion icon.png
Issue date: 11/23/1994
From: Belisle G, Branch M, David Kern
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML18153B166 List:
References
50-280-94-32, 50-281-94-32, NUDOCS 9412060102
Download: ML18153B168 (8)


See also: IR 05000280/1994032

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETIA STREET, N.W., SUITE 2900

ATLANTA, GEORGIA 30323-0199

50-280/94-32 and 50-281/94-32

Licensee: Virginia Electric and Power Company

Innsbrook Technical Center

5000 Dominion Boulevard

Glen Allen, VA

23060

Docket Nos.:

50-280 and 50-281

License Nos.:

DPR-32 and DPR-37

Facility Name:

Surry 1 and 2

Inspection Conducted: October 27 through November 14, 1994

Inspectors:

W.--Sranc,Senlor Resident Inspector

re w ,xi~ £.,.-

D. M. Kern, Resientlnspector

Approved by~G.v.~l~

Scope:

Reactor Projects Section 2A

Division of Reactor Projects

SUMMARY

//-;u .. 9ti

Date Signe

//-Z1-9y

Date Signed

This special inspection was conducted on site to review the circumstances

whic.h led to the reported October 27-28 inoperability of the Unit 2

2A station battery. Specific emphasis was focussed in the areas of related

maintenance and surveillance activities, performance trend analysis, and the

timeliness/effectiveness ~f corrective actions.

Results:

One violation was identified for ineffective corrective actions that resulted

in operation with a degraded station battery .

9412060102 941123

PDR

ADOCK 05000280

Q

REPORT DETAILS

I.

Persons Contacted

l~l

Licensee Employees

  • L. Baker, Operations
  • W. Benthall, Supervisor, Licensing
  • H. Blake, Jr., Superintendent of Nuclear Site Services
  • R. Blount, Superintendent of Maintenance
  • B. Bryant, Licensing Engineer
  • D. Christian, Station Manager
  • J. Downs, Superintendent of Outage and Planning
  • B. Garber, Licensing Engineer

D. Green, System Engineer

M. Haduck, Electrical Supervisor

  • D. Hayes, Superintendent of Administrative Services
  • R. Johnson, Operations Supervisor

H. Jones, Electrical Supervisor

I. Jones, Electrical .Supervisor

  • R. MacManus, Supervisor, Station Engineering

G. Marshall, Operations Maintenance Advisor

  • J. McCarthy, Assistant Station Manager
  • J. McGinnis, Site Nuclear Safety
  • A. Price, Assistant Station Manager
  • R. Saunders, Vice Pr~sident, Nuclear Operations
  • E. Smith, Site Quality Assurance Manager
  • T. Sowers, Superintendent of Engineering
  • D. Sommers, Supervisor, Corporate Licensing

B. Stanley, Station Procedures

  • J. Swientoniewski, Supervisor, Station Nuclear Safety

Other licensee employees contacted included plant managers and

supervisors, operators, engineers, and technicians.

1.2

NRC Personnel

  • M. Branch, Senior Resident Inspector
  • D. Kern, Resident Inspector
  • S. Tingen, Resident Inspector
  • Attended Exit Interview

Acronyms and initialisms used throughout this.report are listed in .the

last paragraph .

2.

2

2A Station Battery Declared Inoperable

2.1

Event Description

At 11:0'0 am on October 27, the licensee declared the Unit 2,

120 VDC 2A station battery inoperable when cell 52 failed the

monthly TS required surveillance test. Station procedure

O-EPT-0102-01, Monthly Station Battery Cell Voltage Check,

revision 0, specifies the_individual cell voltage acceptance

criteria as~ 2.13 volts. Cells below 2.13 volts are categorized

in the ALERT range which indicates marginal performance.

Cell

voltage~ 2.07 indicates that the cell is inoperable. Procedure

O-EPT-0102-01 directs technicians to notify the shift supervisor

and the system engineer of any ALERT or inoperable test results

for increased monit~ring and performance evaluation. Cell 52

voltage was measured to be 2.067 volts. Technicians promptly

notified the shift supervisor who appropriately entered a 24-hour

LCO shutdown action statement as required by TS 3.16.B.3.

NRC

enforcement discretion, as documented in NRC Inspection Report

Nos. 50-280/94-28 and 50-281/94-28,- was granted to allow an

additional 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> to complete corrective actions.

The licensee

exited TS 3.16.B.3 at 6:15 pm on October 28, thereby terminating

the NRC enforcement discretion.

2.2

Immediate Corrective Action

Immediate corrective action, taken upon the October 27 licensee's

determination that the 2A station battery was inoperable, was

good.

Engineering evaluations, maintenance planning, and

management oversight effectively developed and implemented

corrective actions to jumper around cell 52.

This restored the

2A station battery to an operable condition.

The licensee's

response and corrective maintenance activities are documented in

NRC Inspection Report Nos. 50-280/94-28 and 50-281/94-28.

3.

Activities Which Led to the Event

The inspectors observed licensee activities, conducted interviews, and

reviewed maintenance and engineering records to determine the

circumstances and assess licensee performance which led to the event.

A chronology of the relevant occurrences is listed below.

7/25/94

Observation/Action

Electricians performed the monthly station battery ,voltage'

surveillance (TS 4.6.C.l.b). Cell 52 voltage was 2.08

volts. Cell 52 was placed in ALERT status (<2.13 volts) in

accordance with station surveillance procedures. A priority

three work request for a 2A battery charge was initiated.

8/23

9/02-06

9/11

9/20

3

Observation/Action

Electriciari*s performed the monthly station battery voltage

surveillance. Cell 52 voltage was 2.10 volts {ALERT).

The

system engineer learned that the 7/25 requested battery

charge had not been performed and requested an individual

cell 52 charge be performed promptly.

Electricians performed a cell 52 charge.

- 9/02. As found cell 52 voltage was 2.08 volts (ALERT).

- 9/06 Post charge cell 52 voltage was 2.14 volts

( out of ALERT) .

Electricians performed the quarterly station battery

temperature/specific gravity/water level surveillance

(TS 4.6.C.l.c). The system engineer recommended a

2A battery charge based on divergent specific gravity of

some of the battery cells (not cell 52).

Electricians performed the monthly station battery voltage

surveillance. Cell 52 voltage was 2.09 volts (ALERT).

  • 9/28-10/07 Electricians performed a 2A battery charge based on the 9/11

surveillance results.

- 10/07 Post charge cell 52 voltage was 2.07 volts

(ALERT).

10/07-10

Electricians performed a cell 52 charge due to the low

cell 52 voltage measured following the 2A battery charge.

- 10/07 Began the 30-hour charge of cell 52.

- 10/08 A quick check of cell 52 voltage immediately

following the charge, but prior to the post

charge 72-hour settle period, measured 2.12 volts

{ALERT).

- 10/08 Electricians began a second 30-hour cell 52

charge based on the quick check voltage.

10/13-16

Post charge cell 52 voltage was .not measured or recorded on

10/13 following the 72-hour settle period.

  • 10/17

Electricians measured the post charge cell 52 voltage at

2.07 volts (ALERT).

10/20

Maintenance personnel initiated a work request for a cell 52

charge after discussing the 10/17 voltage reading with the

system engineer.

  • 10/22-26

Electricians performed a cell 52 charge.

- 10/22 As found cell 52 voltage was 2.06 volts {ALERT).

- 10/26 As left cell 52 voltage was 2.07 volts {ALERT) .


10/27

10/28

4

Observation/Action

Electricians performed the monthly station battery voltage

surveillance. Cell 52 voltage was 2.07 volts (ALERT).

Electricians and the-system engineer determined that this

voltage reading made cell 52 inoperable in accordance with

station surveillance procedure O-EPT-0102-01.

Electricians

initiated a DR and informed the SS that the 2A station

battery was inoperable.

11:00 am

The shift supervisor declared the 2A station

battery inoperable and entered a 24-hour LCO

shutdown action statement.

The licensee requested and was granted NRC enforcement

discretion to extend the LCO period an additional 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />

to facilitate on-line corrective maintenance.

Licensee

management was unaware that cell 52 voltage had degraded to

~ 2.07 volts prior to 10/27.

6:15 pm

The licensee completed corrective maintenance and

exited the LCO.

  • Documented test data shows cell 52 voltage~ 2.07 volts. Per

O-EPT-0102-01, cell 52 should have been declared inoperable and a DR

written. Neither station management nor licensed personnel were aware

of this information at- the time of these occurrences and therefore

operability of the 2A station battery was not questioned.

4.

Licensee Actions and Inspector Findings

Maintenance and surveillance data indicated degradation of cell 52 of

the 120 VDC 2A station battery since July 25, 1994. Station procedure

O-EPT-0102-01 requires battery cells with measured cell voltages~ 2.07

volts be declared inoperable. This is consistent with standard TS and

IEEE 450-1987, Recommended Practice for Maintenance, Testing, and

Replacement of Large Lead Storage Batteries for Generating Stations and

Substations. Operation of a battery cell below 2.13 volts can reduce

the life expectancy of the cell.

IEEE 450-1987 further states that cell

voltage of 2.07 volts or below indicates internal cell problems and may

require cell replacement.

Immediate corrective action, usually in the

form of an equalizing charge, is recommended.

Several equalizing

charges were performed on the cell, but the cell failed to adequately

hold the charge.

The inspectors determined that the licensee was slow to take effective

corrective action. Initial corrective action requested in July, an

equalizer charge of the 2A battery (WO 296592), was not performed.

The

requested battery charge had been assigned a routine work order

priority. System engineers were unaware of the low priority assigned

and did not follow-up on the correctiv~ action results until after the

next monthly surveillance. The routine priority assignment combined

5

with absence of follow-up by maintenance or engineering personnel

delayed the start of corrective action by approximately five weeks.

Work priorities are assigned by the OMA or SS in accordance with the

general criteria contained in VPAP-2002, Work Requests and Work Order

Tasks.

The inspectors discussed the priority assignment for WO 296592

with the OMA.

VPAP-2002 does not specifically highlight components in

ALERT status for additional operability review or priority

consideration.

Work priority is assigned based upon information written

on the WR ticket and the personal experience of the SS or OMA.

The OMA

stated that a more in depth priority review is typically conducted when

the DR block on the WR ticket is checked off. Some, but not all,

maintenance procedures direct the submittal of a DR when a component

does not meet procedurally specified.performance criteria. Procedure

O-EPT-0102-01 did not require a DR to be submitted if cell voltage was

measured *in the ALERT range.

The original WR, submitted in response to

the low cell 52 voltage measured on July 25, did not indicate a station

battery operability concern or DR and was therefore assigned a routine

priority three. Following this event the .Station Manager issued a

directive "Problem Reporting" which requires that DRs be submitted when

components are found in the ALERT range, or where trend data indicates

ah approach to an ALERT value.

The inspectors determined this was an

appropriate interim action pending further licensee review of the event.

The inspectors identified that maintenance records documented

information indicating cell 52 voltage had been below station

operability criteria on several occasions between October 7-27. * Neither

station management nor licensed personnel were aware of this information

at time of these occurrences and therefore operability of the 2A station

battery was not questioned.

The inspectors observed that the corrective

maintenanceprocedures used for battery charges do not identify post

maintenance testing requirements to be performed to determine the

success of the corrective maintenance activity. The absence of post

maintenance test requirements contributed to the failure of maintenance

. and engineering personnel to inform management of the unacceptable as

left cell 52 condition.

.

.

The inspectors questioned why post charge voltage was not measured on

October 13 immediately following the 72-hour settling period, as is

normally done.

The measurement delay was inconsistent with the level of

i~portance indicated by charging this cell 3 times in the previous 10

days.

The inspectors discussed work priority assignment, the absence of

post maintenance test requirements, and the delay in measuring post

charge cell voltage with licensee management.

The licensee stated that*

these issues wer~ under review, but were not fully evaluated at the

close of this inspection report.

The licensee initiated DR S-94-1994 to

determine the reason why the severe degradation of cell 52 had not been

identified, raised to management's attention, and evaluated for

operability in a timely manner.

The licensee intends to document

resulting corrective actions in a Licensee Event Report .

6

Degrading cell 52 performance was identified in the system engineer's

quarterly report that was issued in early October. This document stated

that cell 52's performance was not adequate to achieve full operability.

Based on this quarterly report, station management began to review the

performance of cell 52. A work plan to replace or jumper cell 52 was

initiated on October 26 and implemented on October 28 as documented in

NRC Inspection Report Nos. 50-280/94-28 and 50-281/94-28.

Licensee

corrective action systems did not elevate the questionable cell 52

performance to the appropriate station management's attention in a

timely manner.

Ineffective management of this issue and limited

tracking of corrective maintenance effectiveness resulted in operation

with a degraded safety component.

The licensee had the opportunity, while cell 52 was in ALERT

(July - September), to develop a contingency work plan to jumper the

cell in the event that cell 52 further degraded to an inoperable

condition. The-licensee began preparing the work plan on October 26,

but the plan was not ready for implementation when the 2A station

battery was declared inoperable on October 27.

The inspectors concluded

that this untimely planning led to the need to obtain NRC enforcement

discretion from TS 3.16.B.3 in order to complete corrective maintenance.

During post event review, station management recognized that multiple

factors had contributed to the organization's failure to promptly

address the degrading condition of the 2A station battery. Management

therefore elevated the level of review and directed that a Case Study be

performed.

This action is independent of the DR and LER corrective

action processes.

The Case Study process uses a time line development

approach to provide independent insight into causal factors.

Management

requested the Case Study to include independent recommendations

regarding corrective action.

The inspectors discussed the Case Study

process with licensee personnel and concluded that this tool was

appropriate to evaluate this event.

Station procedure O-EPT-0102-01 specifies that a battery cell be

considered inoperable and a DR be submitted if a cell voltage

measurement of~ 2.07 volts is recorded.

On October 7, 17, 22,

and 26, 1994, although not during the performance of procedure

O-EPT-0102-01, cell 52 voltage of the 2A station battery was~ 2.07

volts and the cell was not declared inoperable and DRs were not issued.

10 CFR SO, Appendix B, Criterion XVI, as implemented by the Operational

Quality Assurance Program Topical Report (VEP-1-SA, Section 17.~.16)

requires that measures be established to assure that conditions adverse

to quality are promptly identified and corrected.

Failure to establish

measures to assure that a condition adverse to quality 1 a degraded

station battery, were promptly identified and corrected is identified as

VIO 50-281/94-32-0l, Ineffective Corrective Action Associated With The

2A Station Battery.

..

7

  • 5.

. Exit Interview

The inspection scope and findings were summarized on November 15, 1994,

with those persons indicated in paragraph 1.

The inspectors described

the areas inspected and discussed in detail the inspection result

addressed in the Summary section and listed below.

Item Number

VIO 50-281/94-32-01

Status *

Open

Description/(Paraqraph No.)

Ineffective Corrective Action

Associated With The 2A Station

Battery (paragraph 4)

Proprietary information is not contained in this report. Dissenting

comments were not received from the licensee.

6.

Index of Acronyms and Initialisms

CFR

CODE OF FEDERAL REGULATIONS

DR

DEVIATION REPORT

IEEE

INSTITUTE OF ELECTRICAL AND*ELECTRONICS ENGINEERS, INC

LCO

LIMITING CONDITIONS OF OPERATION *

LER

LICENSEE EVENT REPORT

NRC

NUCLEAR REGULATORY COMMISSION

OMA

OPERATIONS MAINTENANCE ADVISOR

SS

SHIFT SUPERVISOR

VDC

VOLTS DIRECT CURRENT

VIO

VIOLATION

WO

WORK ORDER

WR

WORK REQUEST