ML18153B055

From kanterella
Jump to navigation Jump to search
Insp Repts 50-280/94-18 & 50-281/94-18 on 940725-29.One non-cited Violation Identified Re Misuse of Design Info in Thrust Calculation.Major Areas Inspected:Implementation of MOV Program to Meet Commitments in Response to GL 89-10
ML18153B055
Person / Time
Site: Surry  Dominion icon.png
Issue date: 08/23/1994
From: Casto C, Mark Miller
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML18153B054 List:
References
50-280-94-18, 50-281-94-18, GL-89-10, NUDOCS 9409120044
Download: ML18153B055 (20)


See also: IR 05000280/1994018

Text

.*

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTA STREET, N.W., SUITE 2900.

ATLANTA, GEORGIA 30323-0199

Report Nos.:

50-280/94-18 and 50-281/94-18

Licensee:

Virginia Electric and Power Company

5000 Domimion Boulevard

Glen Allen, VA

23060

Docket Nos.:

50-280 and 50-281

License Nos.:

DPR-32 and DPR-37

Facility Name:

Surry 1 and 2

Inspection Conduc~e~ul~ 25--29, i_:: .

Inspec]r: ~/+-~

c.,1--M.

.

111 er

Aecom anying Personnel: R. Cain, Consultant, INEL

T. Scarbrough, Office of Nuclear

D. Tamia, Intern

Approved by: /_~-./*~

~ief

Scope*

Test Programs Section

Engineering Branch

Division of Reactor Safety

SUMMARY

~y9Y

Dae Signed

Reactor Regulation

<t/~J/7 f

Date Signed

This special, *announced inspection was performed at the Surry Nuclear Plant to

examine the implementation of the licensee's motor-operated valve (MOV)

program to meet *commitments in response to Generic Letter (GL) 89-10, "*Safety-

Rel ated Motor-Operated Valve Testing and Surveillance." The inspectors

utilized the guidance provided in Temporary Instruction (TI) 2515/109 (Part

2), "Inspection Requirements for Generic Letter 89-10, Safety-Related Motor-

Operated Valve Testing and Surveillance." As delineated in Part 2 of TI

2515/109, this inspection was the initial review of the licensee's MOV program

implementation in response to GL 89-10.

The inspectors reviewed six MOVs in detail including selected portions of

design calculations, test packages, and diagnostic signature traces. In

addition, three MOVs in three different groups were reviewed for comparison

9409120044 940823

PDR

ADOCK 05000280

G

PDR

2

purposes.

The inspectors also reviewed followup issues from the previous NRC

inspection of the MOV program {TI 2515/109, Part 1) conducted November 18-22,

1991, and documented in NRC Inspection Report Nos. 50-280,281/91-32.

Results

In the areas inspected one non-cited violation was identified for the misuse

of design information in a thrust calculation.

NCV-50-280/94-18-0l, MOV Design Thrust Calculation Error (Section 2.3)

The overall conclusion was that the licensee was in the process of

implementing a very good GL 89-10 MDV program.

However, several concerns

identified during the Part 1 inspection and items identified during this

inspection will require further NRC evaluation prior to closure of GL 89-10.

These concerns pertain to 1) MOV thrust calculations; 2) use of the Kalsi

study for overthrust conditions; 3) MDV grouping; 4) valve factor assumptions;

5) valve stem friction coefficient; 6) periodic verification; and, 7) MDV

failures addressed in NRC Information Notice IN 94-10.

In addition, ten MDVs

in Unit 2 remain for dynamic testing during the next refueling outage.

Several minor modifications remain for five MOVs (Section 2.3).

Based on the evaluation completed during this inspection the following

strengths were noted in the licensee's GL 89-10 program:

The System Engineering Department's support of both the design-basis

parameters and testing of the MOVs through the use of the "Testing And

Results Docum~nts" made a significant contribution to the GL 89-10

program. (Section 2.1)

The licensee evaluates the test results for DP tested valves prior to

any mode change during the MDV testing phases. (Section 2.3)

A large number of MDVs have been tested.

(Section 2.3)

The MDV program was well organized and documentation was detailed and

complete .. (Section 2.0)

Both the corporate engineering staff and the on-site personnel exhibited

knowledge and expertise.

(Section 2.2 and 2.3}

Except as noted above, the inspectors concluded that the licensee was in the

process of implementing an effective program in response to GL 89-10 thereby

ensuring the design-basis capability of MDVs at the facility .

REPORT DETAILS

1.

Persons Contacted

Licensee Employees

  • R. Beger, Nuclear Operations Support
  • W. Benthall, Supervisor, Licensing
  • R. Blount, Supervisor, Maintenance
  • D. Christian, Assistant Station Manager
  • P. DeTine, Project Engineer, Nuclear Engineering
  • R. MacManus, Supervisor, System Engineering
  • J. McCarthy, Superintendent, Operations
  • E. Smith Jr., Manager, Quality Assurance
  • J. Staffer, MOV Coordinator, Maintenance
  • A. Wright, MOV Engineer, System Engineering

Other licensee employees contacted during this inspection included

engineers, technicians, and administrative personnel.

NRC Resident Inspectors

  • Attended exit interview

Acronyms and initialisms used in this report are listed on the last

page.

2.0

GENERIC LETTER (GL) 89-10 "SAFETY-RELATED MOTOR-OPERATED VALVE [MOV]

TESTING AND SURVEILLANCE"

(2515/109)

On June 28, 1989, the NRC issued GL 89-10, which requested licensees and

construction permit holders to establish a program to ensure that switch

settings for safety-related MOVs were selected, set, and maintained

properly. Subsequently, six supplements to the GL have been issued.

NRC inspections of licensee actions implementing commitments to GL 89-10

and its supplements have been conducted.based.on.guidance provided.in

Temporary Instruction (TI) 2515/109, "Inspection Requirements for

Generic Letter 89-10, Safety-Related Motor-Operated Valve Testing and

Surveillance." TI 2515/109 is divided into Part 1, "Program Review,"

and Part 2,- "Verification of Program Implementation."

The focus of this inspection was to evaluate, in depth, the test results

of a sample of six MOVs that had been dynamically tested and review the

licensee's corrective actions for the concerns identified during the

GL 89-10, Part 1 MOV inspection. The test results and engineering

documentation were examined for the MOVs listed below:

Valve No.

l-CH-MOV-1286B

l-CH-MOV-1286C*

MOV Function, Size, and Type

B Charging Pump Normal Discharge Valve

3 inch flex wedge gate - Velan

1-CH-MOV-1287A

2-CH-MOV-1287A*

1-FW-MOV-160A

1-FW-MOV-1608*

1-SI-MOV-1863A

1-SI-MOV-I890C

2-SI-MOV-2842

2

A Charging Pump Alternate Discharge Valve

3 inch flex wedge gate - Westinghouse

Auxiliary Feedwater Cross Connect Valve

6 inch flex wedge gate - Crane

Low Head Safety Injection to High Head

Safety Injection Cross-Connect Isolation

Valve - 8 inch solid wedge gate - Aloyco

Low Head Safety Injection Pump Discharge

Valve to RCS Cold Leg Injection - 8 inch

double disc gate - Anchor Darling

Alternate High Head Safety Injection to

Cold Leg Isolation Valve - 4 inch double

disc gate - Anchor Darling

  • Indicates MOV's test data was reviewed for comparison purposes.

The inspectors verified that the system design-basis differential

pressures (DP) and flows used for diagnostic testing of the GL 89-10

Program MOVs listed were reasonable and correct. This examination

included review of piping and instrumentation drawings; design-basis

calculation results of the expected differential pressures; the sizing

and switch setting calculations; and diagnostic test data.

The

inspectors also conducted a walkdown of the MOVs.

The inspectors found the licensee's MOV program documentation,

procedures, test packages, and technical reports were detailed, complete

and well organized.

The licensee's engineering personnel were

knowledgeable and cooperative in assisting the inspectors.

Except as

noted in the following paragraphs, the inspectors concluded that the

licensee was in the process of implementing an effective program in

response to GL 89-10 thereby ensuring the design-basis capability of

MOVs at the facility.

2.1

Design-Basis Reviews

The inspectors reviewed the licensee's design-basis documentation (DBD)

to determine and verify its adequacy for all the MOVs in the licensee's

GL 89-10 program including the nine MOVs examined during this

inspect ion.

In addition, recommended action.

11 a

II of GL 89-10 requested

licensees determine the maximum differential pressure and flow expected

for both normal and abnormal (design-basis accident) conditions.

The

inspectors verified these values were used in thrust calculations.

These follow-up reviews were performed to determine and verify that

changes were implemented to address concerns identified during the

GL 89-10, Part 1 inspection conducted in November 1991. That inspection

identified several concerns related to the review of the design-basis

calculations. At that time the design-basis differential pressure

3

calculations did not include flow rates (as discussed in GL 89-10).

In

addition, .the degrading effects of high ambient temperature on the

output torque of MDV motors had not been considered.

Limitorque had not

yet issued their Potential Part 21 Notice dated May 13, 1993, and the

Technical Update 93-03 dated September 1993, that discussed the effects

of elevated temperature on motor torque.

The inspectors reviewed the licensee's General Nuclear Standard, STD-GN-

0002, Revision 2, dated March 1994, "Motor-Operated Valve Sizing &

Calculations" that addressed Limitorque's Potential Part 21 Notice.

In

addition, electrical calculations (EE-0306 and EE-501) were examined to

verify that high ambient temperature effects were included.

The

inspectors verified that these electrical calculations were revised to

include the effects of elevated temperature on both motor torque and

thermal overloads.

During this inspection, the inspectors reviewed the documentation

referenced in the "Differential Pressure Calculations" and "Testing

Basis and Results Documents" {TBRD) to verify that the maximum flow and

differential pressure were used in the thrust calculations. The

documentation reviewed included the operational procedures, system flow

drawings {P&ID), pump curves, the system description documents in the

Operator.Development Program for the Safety Injection, Charging,

Feedwater, Auxiliary Feedwater, and Chemical and Volume Control Systems .

The System Engineering Department developed a series of DBDs identified

as GL 89-10 TBRD.

The TBRDs supplemented the Nuclear Engineering

design-basis Galculations by providing design-basis flow and

differential pressure test parameters. Additionally, evaluations and

conclusions for the DP test results were included in the TBRDs.

The

TBRDs provided a description of the limiting condition assumed in the

thrust calculations at design-basis flow and DP.

The DP test results

were analyzed and compared against the thrust calculations to verify

their adequacy.

The inspectors concluded the TBRDs addressed the flow

parameter and provided a method of interfacing between design

engineering and the site for both testing and analysis.

The TBRDs made

a significant contribution to the GL 89-lO_program and are-considered a

strength in the MOV program.

The inspectors verified the licensee's MOV calculations for DP,

electrical degraded grid voltage, flow, temperature, design thrust, and

torque addressed the recommendations in GL 89-10.

The inspectors

verified that degraded grid calculations were included to ensure that

the lowest motor terminal voltage commensurate with design-bases

conditions was factored into the determination of thrust ratings. The

inspectors also verified that the licensee satisfactorily addressed the

design, replacement and testing of thermal overloads in the electrical

circuits for the MOVs.

In the areas inspected the inspectors concluded the licensee had

adequately implemented the design-basis review .

4

2.2

MOV Sizing and Switch Setting

The inspectors reviewed the licensee's General Nuclear Standard STD-GN-

0002, "Motor-Operated Valve Sizing and Calculations," Revision 2, dated

March 1994,- to determine the thrust calculations used for the six

sampled valves.

STD-GN-0002 specified that the standard industry

equations for calculating thrust for gate and globe valves was to be

used.

The licensee used a valve factor (VF) of 0.30 for flex wedge gate

valves and 0.20 for parallel disc gate valves. A valve factor of 1.10

was used for globe valves.

For Westinghouse valves, the licensee used

data provided by the valve vendor, where available, or assumed a valve

factor of 0.45 or 0.55.

The valve orifice diameter was used in the

valve disc area calculations. A stem friction coefficient (SFC) of 0.15

was used in the calculations for the minimum required torque.

The

minimum required thrust, including packing load and stem rejection

force, was then adjusted by the use of a multiplying factor of 1.15 to

account for variations in valve factor, potential load sensitive

behavior (also known as "rate-of-loading"), and other phenomena.

The upper and lower thrust ~indow settings were adjusted for diagnostic

inaccuracies and torque switch repeatability. The licensee had

addressed the concerns discussed in Limitorque Maintenance Update 92-2

with respect to torque switch repeatability. This information had been

incorporated into the General Nuclear Standard, STD-GN-0002.

Limiter plates were not installed on all their GL 89-10 valves.

Further, the licensee assumed a stem friction coefficient of 0.15 and

did not routinely measure torque.

The inspectors discussed with the

licensee the possibility of exceeding the actuator's torque rating by

increasing the torque switch setting to achieve the desired thrust

output.

The licensee had taken the spring pack capability rating and

motor torque rating and converted these values to thrust using an

assumed stem factor. If the "as left" thrust readings approached the

spring pack or motor capability rating, an engineering evaluation was

performed.

The inspectors noted that the spring pack and motor

capability were computed using a stem friction coefficient of 0.15.

The

licensee's. intentions are to use the_stem friction coefficient

information from the EPRI prediction program and apply it to MOVs in

their program.

The licensee's justification for the use of a 0.15 stem

friction coefficient factor and the use of the EPRI information will

require further NRC evaluation prior to closure of GL 89-10.

As

discussed in Item 5 of Section 2.7 the inspectors were concerned about

the applicability of the stem friction coefficient data obtained by EPRI

to the Surry MOVs.

In the areas inspected, the inspectors concluded the licensee was

implementing an effective program to meet the recommendations of

GL 89-10.

However, further NRC evaluation will be required prior to

closure.

5

2.3

Design-Basis Capability

The inspectors reviewed the licensee's static and dynamic test data for

the sampled MOVs.

The licensee had completed static tests for 188 of

the 190 GL 89-10 MOVs.

As of June 1993, the licensee had completed 46%

of the differential pressure (DP) testing on rising stem, testable

valves.

The licensee's intentions for completion of the GL 89-10

program are to use grouping and plant specific data for the non-tested

MOVs.

The licensee used guidance from the Generic Letter 89-10,

Supplement 6 and separated the MOVs into 37 different groups.

Their

intentions were to test a minimum of 30% of the MOVs in a group and at

least two MOVs in groups containing three or more MOVs.

The MOV

grouping was established by selecting the same type of valve and

operator in the same type of application. This selection was further

defined by valve manufacturer, type, model, size, and manufacturer's

drawing number.

In situations where a MOV was used in both high and low

DP pressure systems, the test results from the high DP test was used to

bound the lower pressure application. This methodology would result in

the testing of 58% of the testable MOVs.

The inspectors considered the

grouping technique to be generally consistent with the recommendations

in the GL 89-10.

However, the licensee had eight groups with only two

MOVs in each group.

The intent was to test only one of the two MOVs in

each of these groups.

The inspectors did not consider this consistent

with recommendations in Supplement 6 of GL 89-10.

Further, testing only

one valve in each group limits consistency of test results between

groups.

The inspectors concluded further NRC evaluation in this area

would be required prior to closure of GL 89-10.

The licensee had four MOVs in their program with motor brakes installed,

l-RH-MOV-1720 A/Band 2-RH-MOV-2720 A/8.

The licensee compared the

calculated minimum required thrust against the motor capability for

these limit open MOVs.

There was approximately 16,000 ft-lbs of

additional (extra) thrust available to compensate for the possible added

drag due to the motor brakes.

However, the inspectors determined

further NRC evaluation concerning motor brakes would be required prior

to closure of GL 89-10.

The licensee had operability reviews performed for the MOVs from the

requirements in Procedure SES-3.03, Revision 2, "Controlling Procedure

Providing Guidelines For Addressing MOV Design Issues." These reviews

were completed prior to returning the MOVs to service after design-basis

DP testing. There were no operability concerns by the inspectors s i nee . ~ ...

design-basis DP testing was conducted when the plant was in the shutdown

mode.

The acceptance criteria for the review was developed to evaluate

thrust at flow cutoff with the calculated minimum required thrust. This

evaluation had three cases. Case 1 was where test DP was equivalent to

design-basis DP.

Case 2 was where test DP was at least 80% or greater

than design-basis DP.

For these valves, the licensee used the ratio of

test DP to design basis DP and multiplied this by the thrust at flow

cutoff. Case 3 was where test DP was less than 80% design-basis DP.

For these cases, the licensee performed a qualitative review of the

thrust margin.

In all three cases, the licensee checked for margin

6

between the required thrust from the dynamic test and the calculated

minimum required thrust. The required thrust was also compared to the

thrust measured at control switch trip (CST).

Load sensitive behavior

was also checked by comparing CST thrust during dynamic testing with CST

thrust during static testing.

The inspectors, accompanied by licensee engineering personnel, reviewed

diagnostic traces for the sampled MOVs and several other selected MOVs.

Licensee personnel were knowledgeable in the use of the VOTES system and

the VOTES methodology of marking the diagnostic traces.

The inspectors

considered this to be a strength in the licensee's MOV program.

However, the inspectors noted that flow cutoff for valve 2-SI-MOV-2842

appeared to be improperly marked.

Licensee personnel agreed and

immediately revised the point marked for flow cutoff and verified that

an operability concern did not exist. Further NRC review of the

diagnostic traces indicated that the non-conservative marking of flow

cutoff for 2-SI-MOV-2842 was an isolated case.

The licensee's method of comparing thrust at flow cutoff against the

calculated minimum required thrust was developed to account for

variations in valve factor, load sensitive behavior, and other

uncertainties. The licensee had several valves (e.g., 2-SI-MOV-2864A

and l-CH~MOV-1287C) where the DP test thrust results were in excess of

that predicted by this methodology.

In all cases, the licensee took

immediate action to correct any deficiency and evaluate the impact on

the other MOVs in the group.

The inspectors considered this action

appropriate for evaluating deficiencies. However, these examples

indicated that this methodology was not always bounding.

The licensee

used both in-plant and industry test results to set up MOVs for design-

basis capability.

For MOVs that are not dynamically tested, the

licensee's methodology for "setting up" the MOVs from both in-plant and

industry test results will require additional NRC review.

The

licensee's justification for ensuring design-basis capability will

require further NRC evaluation as part of GL 89-10 closure.

The inspectors reviewed Memorandum "MOV Evaluations Supplement To Design

Basis Review Of l-SI-MOV-1842 Surry Power Station NIT 1 NP::-:2319" dated

June 27, 1994.

The purpose of this memorandum was to document the

further review of MOV operator "capability" regarding minimum required

thrust.

The minimum required thrust calculations were included in the

review.

The "capability" calculation used "stall torque" in the open

direction and used "stall efficiency" in the closed direction. The term

"stall torque" was misused.

Stall torque is defined as the torque at

zero speed (20 ft.lbs). The licensee used the derated torque at rated

speed (13 ft.lbs).

The open direction calculation used the motor rated

torque (derated for high ambient temperature and degraded voltage)

multiplied by 1.10 to derive "stall torque." However, in the closed

direction, the licensee misused the "stall efficiency" selected from

Limitorque's guidelines. Section 7 of Limitorque Maintenance Update 92-

1 indicates that "stall efficiencies" are not to be used to calculate

MOV capability. The use of "stall efficiency" in the closed direction

calculation was in violation of NRC requirements.

10 CFR 50 Appendix B,

7

Criterion III, Design Control, requires, in part, that "design control

measures shall provide for verifying or checking the adequacy of

design ... " The inspectors reviewed the calculation to verify

operability of the MOV.

The licensee used a DP derived from the

"mispositioning" scenario that required recovery to the closed position

(non-safety position}. Licensee personnel recalculated the minimum

required thrust using a lower DP derived from a mispositioning scenario

that required recovery to the open (safety} position.

Further, licensee

personnel recalculated the motor capability using torque (13 ft-lbs

derated for high ambient temperature and degraded voltage}, an

application factor of 0.9, and the pullout efficiency. After the

recalculation, the motor had sufficient capability to meet design-basis

requirements.

The inspectors considered this adequate and did not

identify an operability concern with 1-SI-MOV-1842. * However, this NRC

identified violation is not being cited because criteria specified in

Section VII.B of the NRC Enforcement Policy were satisfied. The

violation was of minor safety significance and there was no operability

concern.

The misuse of "stall efficiency" in the thrust calculation is

identified as non-cited violation NCV-50-280/94-18-01, MOV Design Thrust

Calculation Error.

The inspectors reviewed additional "engineering evaluations" to

determine if any other MOVs used "stall torque" or "stall efficiency."

Six other MOVs were identified that misused the term "stall torque," but

did not use "stall efficiency." These MOVs were 1-RS-MOV-155 A/B, 1-SI-

MOV-1862 A/B, and 2-SI-MOV-2862 A/B which are Xomox plug valves.

The

actual torque value used was rated nominal torque at rated speed

(derated for high ambient temperature and degraded voltage}.

Further,

these MOVs used an application factor of 0.9 and pullout efficiency.

The inspectors did not identify any operability concerns with these

valves.

In addition, as part of their own evaluation, the corporate Nuclear

Engineering Department had recommended a gear change for these MOVs to

improve their margins.

Engineering also recommended that the operator

for 1-SI-MOV-1842 be upgraded to a larger size. The licensee stated all

these MOVs will be.modified during the*next.refuelingoutages.

The inspectors concluded the licensee had been implementing an effective

MOV program to verify design-basis capabilities. However, further NRC

evaluation will be required prior GL 89-10 closure.

2.4

Periodic Verification of MOV Capability

Recommended action "d" of the generic letter requests the preparation or

revision of procedures to ensure that adequate MOV switch settings are

determined and maintained throughout the life of the plant. Section "j"

of the generic letter recommends surveillance to confirm the adequacy of

the settings. The interval of the surveillance was to be based on the

safety importance of the MOV as well as its maintenance and performance

history, but was recommended not to exceed five years or three refueling

8

outages.

Further, GL 89-10 recommended.that the capability of the MOV

be verified if the MOV was replaced, modified, or overhauled to an

extent that the existing test results are not representative of the MOV.

The inspectors found that GL 89-10 MOVs were in the process of being

included in the licensee's database and that the database contained

model preventive maintenance work orders that specified VOTES diagnostic

testing at a three refueling outage or five year frequency.

The

diagnostic testing was not specified to be performed at DP; that is,

only static diagnostic testing would be performed.

The licensee's

criteria for test performance and acceptance of periodic verifications

and its justification that the criteria are adequate will require

further NRC evaluation prior to closure of GL 89-10.

The inspectors verified that post maintenance testing for different

maintenance operations was specified in the licensee's electrical and

mechanical Post Maintenance Test/Verification matrices.

Comprehensive

(static) diagnostic testing was required following valve replacement or

repair.

For packing adjustment, thrust verification was specified.

Licensee personnel were questioned as to why only static testing was

required for valve replacement.

The inspectors were informed that a DP

test should be performed for any valve replacement and that it was

provided.for as a "verification" on the related matrix. Only static

testing was considered necessary for a repair unless the repair might

affect the functioning of the valve. If functioning was affected, it

should be considered a modification rather than maintenance and the need

for DP testing should be evaluated.

The inclusion of "verification" DP

testing for the matrix that covered valve replacement was confirmed by

the inspectors.

The inspectors concluded that the specified testing was

appropriate.

The inspectors concluded that the licensee's periodic verifications were

not fully implemented.

Complete implementation, including adequately

justified test methodology and acceptance criteria, will require further

NRC evaluation prior to closure of GL 89-10.

The licensee was

implementing a satisfactory post maintenance testing program for the

MOVs.

2.5

MOV Failures, Corrective Actions, and Trending

Recommended action "h" of the generic letter requests that licensees

analyze and justify each MOV failure and corrective action.

The

documentation should include the results and history of each as-found

deteriorated condition, malfunction, test, inspection, analysis, repair,

or alteration. All documentation should be retained and reported in

accordance with plant requirements.

It is also suggested that the

material be periodically examined (every two years or after each

refueling outage after program implementation) as part of the monitoring

and feedback effort to establish trends of MOV operability .

9

The licensee issues a quarterly report prepared by the MOV Coordinator

that lists the status of the program testing efforts and MOV failures

occurring during the period covered .. The reports also indicate the root

cause for the failures and tracks the failures by item type since 1991.

The inspectors reviewed 323 deviation report (DR) summaries and their

associated corrective actions.

Fourteen DRs were selected for detailed

review.

The corrective action taken that included the work order and

the engineering evaluation were verified for adequacy and completion.

Nine examples of the 14 DRs examined in detail are as listed as follows:

1) DR S-94-0481 - The Maximum thrust appeared to be exceeded.

2) DR S-93-0977 - Review classified 24 MOVs to EQ and GL 89-10.

3) DR S-94-1078 - Thermal overloads were not sized and replaced.

4) DR S-93-0741

Inspect MOV's gears for fatigue cracking.

5) DR S-94-0496

There was no acceptance criteria for switch.

6) DR S-94-0374 - Motor leads have 260 V reading to ground.

7) DR S-94-0274

Water was in switch housing.

8) DR S-94-0635 - Breaker tripped motor when switch failed.

9) DR S-95-0609

High current indicated during testing.

These nine examples were presented to show that the licensee's program

had requirements for identifying failures, taking appropriate corrective

action, and trending the problems.

The inspectors concluded the

licensee's program in this area was satisfactory.

2.6

Schedule

By letter dated December 26, 1989, the licensee committed to meet the

recommendations and schedule of GL 89-10.

In a letter dated June 29,

1993, the licensee informed the NRC Staff that they were revising its

schedule commitments for Unit 1.

On August 19, 1993, the staff notified

the licensee that it would assess the licensee's justification for the

schedule extension during an inspection.

The factors for review listed

in the August 19, 1993, letter are similar to those that were

subsequently issued in Supplement 6 to GL89.-:-10 *. At. Surry, .the.

inspectors discussed the present schedule for completing the GL 89-10

programs with licensee personnel.

The licensee stated that the present

GL 89-10 completion schedules for its nuclear plants are the Fall of

1995 for Unit 1 (including schedule extension) and the Spring of 1995

for Unit 2.

For the GL 89-10 schedule extension, the factors listed in the

August 19, 1993, letter and the licensee's action are summarized below:

ACTION 1

STATUS 1

Establish the actual completion status of the GL 89-10

program for MOVs not yet set up under the program.

Design-basis reviews and calculations determining setpoints

are complete for rising stem and quarter-turn MOVs.

Static

diagnostic tests have been performed on rising-stem MOVs.

10

Differential pressure testing complete for 32 rising-stem

and 15 quarter-turn MOVs in Unit 1, and 21 rising-stem and

11 quarter-turn MOVs in Unit 2.

The licensee stated that

eight rising-stem and two quarter-turn MOVs remain to be

tested in Unit 2 at the next refueling outage.

ACTION 2

Establish the basis for confirming the operability for each

MOV not set up under the program by June 28, 1994.

STATUS 2

The inspectors reviewed the status of the licensee's GL 89-

10 program and the MOVs not set up under the GL 89-10

program.

The inspectors found the thrust output at the

present torque switch settings for those MOVs requiring a

schedule extension compare favorably with best available

data from plant and industry data. However, the inspectors

considered MOVs CH-1115E and 2350 will require further NRC

review of their capability based on best available data and

encouraged the licensee to address those MOVs on a priority

basis.

ACTION 3

Establish the schedule for completing MOV testing and

modifications.

STATUS 3

Differential pressure testing will be completed during the

next Unit 2 refueling outage. Modifications are being

considered for 1-SI-MOV-1842, 1-RS-1558, and 1-SI-1862A/B.

(Section 2.3)

ACTION 4

Provide the extent of completing MOV testing under dynamic

testing.

STATUS 4

See ACTION 1 status.

ACTION 5

Provide the extent that plant and industry data have been

used to establish the sizing and setting methodology.

STATUS 5.

With respect to the licensee's.overall MOV sizing and.switch

setting methodology, the licensee evaluates test data to

verify the assumptions in their methodology and, where the

data does not support the assumptions, the licensee revises

the switch setting requirements for the tested MOVs and

other applicable MOVs.

The licensee has prepared

documentation for the verification of design-basis

capability for non-tested MOVs that also cannot be grouped

with other MOVs.

Based on the inspectors' summary review of

the licensee's documentation, the inspectors considered that

some of the justifications for verifying design-basis

capability in lieu of dynamic testing will require further

NRC review as part of GL 89-10 closure.

ACTION 6

STATUS 6

ACTION 7

STATUS 7

11

Provide the maintenance and modification activities to

improve the performance of the MOVs.

The licensee has reset torque switches on GL 89-10 MOVs as

necessary. Eight actuators have been replaced to increase

their design margins.

Four MOVs have undergone gear changes

to increase their design margins. Also, see ACTION 3

status.

Establish justification for any grouping methods used.

The licensee has established a grouping methodology that, in

many respects, follows the provisions of Supplement 6 to GL 89-10.

The inspectors raised concerns with the licensee's

plan to test only one MOV for some groups containing two

MOVs.

The testing of only one MOV in a group does not

provide confidence that the performance of the tested MOV is

representative of the group.

The licensee will need to

justify the design-basis capability of the grouped MOVs not

differential pressure tested as part of GL 89-10 closure.

The inspectors raised concerns regarding the licensee's

grouping and testing of butterfly valves.

The licensee

presently plans to perform dynamic testing of butterfly

valves without diagnostics. The licensee is performing

static tests with limited diagnostics.

For example, the

licensee might monitor motor current and spring pack

deflection, but not torque, during a static test. The

licensee believes that its use of vendor test data,

surveillance testing of some butterfly valves under dynamic

conditions, and its evaluation of industry test data, will

be sufficient to justify initial and periodic design-basis

capability verification without additional diagnostic data.

The licensee will need to justify its butterfly valve

grouping and testing as part of GL 89-10 closure.

The inspectors concluded that the licensee satisfactorily addressed the*

factors listed in the August 19, 1993, letter for justifying the GL 89-

10 schedule extension for Surry 1.

2.7

Followup of Previous Inspection Findings

The inspectors reviewed the status of the 11 open findings identified

during the previous GL 89-10, Part 1, inspection conducted November 18-

22, 1991.

The findings and the results of the inspectors' review are

briefly described below:

1.

The process for consideration of flow in design-basis

testing and analysis was not adequately specified in the MOV

program .

12

The licensee developed a "Testing Basis & Results Document"

to address testing conditions including flow and to provide

analysis.after the testing was performed. (Section 2.1)

2.

The licensee used the Kalsi Study to justify overthrust

conditions.

The inspectors found the licensee's overthrust procedure to

be inconsistent with Limitorque Maintenance Update 92-1 for

visually inspecting an actuator following an overthrust or

overtorque condition.

The licensee stated that the

procedure would be reviewed and updated.

This will require

further NRC evaluation as part of GL 89-10 closure.

3.

The licensee plans to use MOV grouping.

(Section 2.6, Action Item 7)

4.

The valve factor assumptions were not conservative.

Initially, the licensee assumes a valve factor of 0.3 for

wedge gate and 0.2 for double disk gate valves in setting

the MOVs in its GL 89-10 program, except for Westinghouse

gate valves, which have a 0.55 valve factor assumption in

response to vendor guidance.

The licensee increases the

thrust predicted from the standard industry equation

(including dynamic thrust load, stem rejection load, and

packing load) by a 1.15 factor.

The licensee compares test

data at an apparent flow cutoff with the thrust requirement

prediction. The inspectors were concerned with the

selection of flow cutoff for certain tests and the overall

applicability of flow cutoff data between tested and non-

tested MOVs.

The inspectors did not identify any immediate

operability problems.

The licensee increases its thrust

requirement for all MOVs in a group when test data exceeds

the predicted value.

The licensee justification will

require further NR~ evaluation as part of GL 89-10 closure-

(Section 2.2 and 2.3)

5.

The valve stem friction coefficient was not conservative.

The licensee assumes a stem friction coefficient of 0.15 for

its MOVs.

The licensee does not have plant data to support

its stem friction coefficient assumption, but relies on EPRI

and Kalsi laboratory test data.

The inspectors were

concerned that the lack of specific plant data will be

insufficient to justify the stem friction coefficient in

light of information from other utilities that a 0.15 stem

friction coefficient cannot always be justified. The

licensee justification will require further NRC evaluation

as part of GL 89-10 closure.

(Section 2.2 and 2.3)

13

6.

The licensee did not have "as found" diagnostic testing

specified as a requirement after preventative maintenance.

The licensee plans to perform "as-found" MOV diagnostic

testing as part of its periodic verification of MOV

capability.

In Technical Report PE-0016 (Rev. 1, July

1994), the licensee describes periodic stati~ testing to

attempt to identify design-basis capability degradation.

The licensee does not provide justification for monitoring

dynamic performance degradation. The licensee will need to

address this issue as part of GL 89-10 closure.

7.

The documents and procedures in the GL 89-10 MOV Program

need updating.

The inspectors verified that the GL 89-10 documents and

procedures referenced in Technical Report No. PE-0016 (MOV

Program) had been revised and updated since the Part 1

inspection.

8.

The high ambient temperature effects on motor torque had not

been accounted for.

The inspectors verified the high temperature were accounted

for in calculations EE-0083 and EE-0501. (Section 2.1)

9.

Thermal overload resistance had not been used in the

electrical calculations.

The inspectors verified that thermal overload resistances

were used in the revised electrical calculations. (Section

2.1)

10.

A set screw failure caused the motor pinion to slide causing

2-CW-MOV-200D to fail a stroke test.

The.licensee.was .responding to.NRC Information- Notice 94-10

(February 4, 1994), "Failure of Motor-Operated Valve

Electric Power Train Due to Sheared or Dislodged Motor

Pinion Gear Key."

The licensee has not completed the

response. This item will be require further NRC review as

part of GL 89-10 closure.

11.

At the time of the Part 1 inspection there was minimal DP

testing completed

Since then, the licensee has completed dynamic tests of 53

rising-stem and 26 quarter-turn MOVs at Surry.

The

inspectors considered the large number of DP tested MOVs to

be acceptable .

- ..

14

2.8

Pressure Locking and Thermal Binding

The Office for Analysis and Evaluation of Operational Data (AEOD) has

completed a study of pressure locking and thermal binding of gate

valves.

AEOD concluded in their report that licensees have not taken

sufficient action to provide assurance that pressure locking and thermal

binding will not prevent a gate valve from performing its safety

function.

The NRC regulations require that licensees design safety-

related systems to provide assurance that those systems can perform

their safety functions.

In GL 89-10, the staff requested licensees to

review the design basis of their safety-related MOVs.

The licensee provided documentation of its evaluation of the potential

for pressure locking and thermal binding of gate valves as follows:

(1)

Report, Thermal Binding/Bonnet Pressurization of Gate Valves

October 2, 1991.

(2)

Memo, E. May to P. Boulden,

Response to Nuclear Licensing

Review Comments on the Pressure Locking/Thermal Binding of

Gate Valves, Type 1 Reports, North Anna and Surry Power

Stations, NP 2196/NP 5479, September 11, 1992.

(3)

Memo, E. May to P. Boulden, Response to Operating Experience

Review Group Comments on the Pressure Locking/Thermal

Binding of Gate Valves, Type 1 Reports, North Anna and Surry

Power Stations, NP 2196/NP 5479, dated November 9, 1992.

The inspectors found that the Reference (1) report indicated that a

review of all safety related gate valves had been performed and

concluded that none of the valves had a significant probability of

thermal binding or pressure locking. References (2) and (3) described

concerns and related responses identified from internal reviews of NRC

Information Notice 92-26 and Reference (1).

The responses provided

additional support for the conclusion of Reference (1). These licensee

reports are two to three years old and do not reflect recent information

and-concerns regarding this issue. The. l.icensee-will be expected to

show additional progress in this area before GL 89-10 closure.

The licensee was informed that the NRC plans to issue a Generic Letter

to address continued concerns regarding pressure locking/thermal

binding.

2.9

Quality Assurance {QA) Involvement

The inspectors evaluated the licensee's implementation of QA for

GL 89-10 activities. The inspectors reviewed QA and quality control

(QC) entries in the QA Tracking and Trending System.

QA reports

(Maintenance Audit 92-17, four quarterly MOV assessment reports in 1989

and 1990); the 1992 and 1993 corporate annual MOV assessment reports;

the last eight quarterly status reports for MOVs from System

Engineering; and the last four maintenance (MOV coordinator} quarterly

. j

'

15

reports.

QA's initial reports identified issues that were resolved;

however, QA recent involvement in the MOV program has been minimal.

QC

recent involvement in MOV activities was limited to observing testing

and followup of the DRs discussed in Section 2.5.

The main QA efforts are with the System Engineers and the MOV

Coordinator in the Maintenance Department.* The System Engineers provide

quarterly reports of both past and current MOV issues. The MOV

Coordinator provides quarterly reports that track and trend each MOV

issue, concern, failure, and the corrective action.

The corporate

annual assessments review the program for adequacy and the need for

improvement.

The inspectors concluded the licensee's efforts in

providing QA for the MOV program are appropriate.

2.10 Walkdown

A walkdown inspection of selected MOVs was conducted by the inspectors

to observe the installed yoke sensors and the condition of the valve

stems.

In general, the valves were found in good condition. The valve

stems were satisfactorily lubricated. It was noted that valves other

than MOVs (air-operated and manual) were well-maintained, as indicated

by proper stem lubrication and cleanliness. The yoke sensors that had

been installed for diagnostic testing were examined to determine their

general condition including the installed location and wiring

connections.

The inspectors concluded the condition of the MOVs

examined was satisfactory.

2.11

GL 89-10 Program Closure

For program closure, some of the principal areas that the NRC will

evaluate include the licensee's justification and appropriate

information:

that thrust requirements are established for MOVs that are

not dynamically tested to support design basis capability;

that the VF and SFC used.are.specifi~to the valves and the.

plant;

that plans for periodic verification of MOV design~basis

  • capability are established;*

that the assumed VF and SFC used in thrust calculations

should be demonstrated appropriate for the MOVs not

dynamically tested;

that the torque switch settings ensure that the torque

rating is not exceeded in support of the 2.25 torque switch

settings;

that progress in addressing pressure locking and thermal

binding of gate valves is made;

... . .

  • r

16

that adequate capability of MOVs with motor brakes exists.

3.

EXIT INTERVIEW

The inspection scope and results were summarized on April 15, 1994, with

those persons indicated in paragraph 1.

The inspectors described the

areas inspected and discussed in detail the inspection results listed

below.

Proprietary information is not contained in this report.

Dissenting comments were not received from the licensee.

One unresolved item (URI) concerning the misuse of "stall torque" and

"stall efficiency" in thrust calculations was identified. After staff

review this URI was changed to a non-cited violation, NCV-50-280/94-18-

01, MDV Design Thrust Calculation Error.

The licensee was informed by

telecon on August 25, 1994.

4.

ACRONYMS AND INITIALISMS

AC

AEOD

AFW

CH

cs

CST

DBD

DR

DC

DP

EE

EPRI

EWR

FSAR

FT-LB

FW

GL

INEL

ME

MOV

NRC

NRR

P&ID

PSID

QA

QC

RCS

ROL

SFC

SI

Alternating Current

Office for Analysis & Evaluation of Operational Data

Auxiliary Feedwater

Charging

Charging System

Control Switch Trip

Design Basis Document

Deviation Report

Direct Current

Differential Pressure

Electrical Engineering

Electric Power Research Institute

Engineering Work Request

Final Safety Analysis Report

Foot pounds (torque)

Feedwater

Generic Letter

Idaho National En-gineering Laboratory

Mechanical Engineering

Motor Operated Valve

Nuclear Regulatory Commission

Office of Nuclear Reactor Regulation

Process/Piping and Instrumentation Diagram

Pounds Per Square Inch Differential

Quality Assurance

Quality Control

Reactor Coolant System

Rate of Loading

Stem Friction Coefficient

Safety Injection

I*

f ,'!

f

TBRD

TI

TOL

URI

V

VF

VOTES

17

Testing Basis & Review Document

Temporary Instruction

Thermal Overload

Unresolved Item

Volts

Valve Factor

Valve Operation Test and Evaluation System

e

APPENDIX A.

SURRY POWER STATION GATE VALVE DATA

Diagnostics: VOTES

VALVE

VALVE

TEST

%

DYNAMIC

STEM

%

NO.

TYPE

CONDIDONS

DESIGN

VALVE

FRICTION

LOAD'*

(psid)

BASIS

FACTOR'*

COEFFICIBNT

SENSITIVE

BEHAVIOR

Ope

Clos

Open

Clos

Ope

Close

Stati

Dynamic

n

e

e

n

C

1-SI-

8" Aloyco

163

163

82

82

N/C3

N/C

N/C

N/C

2.0

MOV-

300#

1863A

Solid Wedge

Gate

1-FW-

6" Crane

1360

1360

94

94

NIC

N/C

N/C

N/C

Limit

MOV-

600#

Closed

160A

Flex Wedge

Gate

2-SI-

4" Darling

2660

2660

100

100

NIC

N/C

N/C

N/C

-3.4

MOV-

1500#

2842

Double Disc

Gate

1-CH-

3" Velan

2675

2675

97

'97

N/C

N/C

N/C

N/C

-2.6

MOV-

1500#

1286B

Flex Wedge

Gate

1* Valve factor was calculated using orifice diameter.

2* A negative number indicates that the thrust observed at CST during the dynamic test was greater than the thrust observed at CST during the static

test.

3* "N/C" = Not Calculated. Virginia Power does not routinely back calculate valve factor. Virginia Power assumes a stem friction coefficient of

0.15.