MONTHYEARML18152B3591999-08-23023 August 1999 Revised Tech Specs Basis Pages for TS 3.1.B,deleting Reactor Vessel Toughness Data Duplicated in UFSAR & Includes Ref to Applicable UFSAR Section ML18152B6591999-04-28028 April 1999 Proposed Tech Specs Re Refueling Water Chemical Addition Tank Min Vol ML18152A2131999-02-16016 February 1999 Proposed Tech Specs,Consolidating AFW cross-connect Requirements by Relocation of Electrical Power Requirements from TS 3.16 to TS 3.6 ML18152B5451999-02-16016 February 1999 Proposed Tech Specs Pages,Revising Augmented Insp Requirements for Reactor Coolant Pump Flywheels ML18152B6151998-11-0404 November 1998 Proposed Tech Specs 4.6.A.1.b,re EDG Start & Load Time Testing Requirements & TS 3.16 Bases Re EDG Ratings ML18153A3311998-09-24024 September 1998 Proposed Tech Specs Modifying Testing Requirements for Reactor Trip Bypass Breaker ML18153A3351998-09-24024 September 1998 Proposed Tech Specs Pages Affected by Suppl to 960912 Resubmittal of Change Request Re Relocation of Fire Protection Requirements from TS to UFSAR ML18152B7551998-06-19019 June 1998 Proposed Tech Specs Establishing Requirements for Use of Temporary Supply Line (Jumper) to Provide Svc Water to Component Cooling Heat Exchangers ML18152A3651998-03-25025 March 1998 Proposed Tech Specs Revising Station Mgt Titles to Reflect New Positions Approved by Vepc Board of Directors on 980220 ML18153A3481997-12-18018 December 1997 Proposed Tech Specs Clarifying Terminology Used for Describing Equipment Surveillances Conducted on Refueling Interval Frequency.Clarification Consistent W/Info Contained in Rev 1 to NUREG-1431 ML18153A1761997-11-0505 November 1997 Proposed Tech Specs Re Temporary Svc Water Supply Line to Component Cooling Heat Exchangers ML18153A3941997-11-0505 November 1997 Proposed Tech Specs Re Change for Increased Enrichment of Reload Fuel ML18153A5231997-04-24024 April 1997 Proposed Corrected Tech Specs Pages 6.1-3 & 6.1-8 Re Relocation of Fire Protection TS to Updated Final Safety Analysis Rept ML18153A5031997-03-18018 March 1997 Proposed Tech Specs Rev to Section 4.15 for Surry Power Station to Include Pp Inadvertently Omitted from 970203 Request for Amend to Licenses DPR-32 & DPR-37 ML18153A4921997-02-0303 February 1997 Proposed Tech Specs Re Deletion of Specific ASME Section XI Code Ref ML18153A6351996-11-26026 November 1996 Proposed Tech Specs Re Removal of Record Retention Requirements,Per GL 95-06 & Administrative Ltr 95-06 ML18153A0671996-09-12012 September 1996 Proposed Tech Specs Re Relocation of Fire Protection Requirements ML18153A6901996-04-15015 April 1996 Proposed Tech Specs,Clarifying Applicability of Quadrant Power Tilt Ration Requirements ML18153A5391996-03-21021 March 1996 Proposed Tech Specs Re Charcoal Filter Testing Clarification ML18153A5271996-03-14014 March 1996 Proposed Tech Specs,Permitting Use of 10CFR50 App J,Option B,performance-based Containment Lrt ML18153A5801996-01-30030 January 1996 Proposed Tech Specs Re Reactor Coolant Sys Liquid Sampling ML18153A6761995-11-20020 November 1995 Proposed Tech Specs Re App J Option B,performance-based Containment Leakage Rate Testing ML18153A7141995-07-20020 July 1995 Proposed Tech Specs Establishing New Setpoint Limit for SG high-high Level & Provides More Restrictive Setting Limits for Certain Rps/Esfas Setpoints ML18153A6991995-07-14014 July 1995 Proposed Tech Specs,Providing Two H Allowed Outage Time for One RHR Pump to Accommodate Plant Safety,Emergency Power Sys Surveillance Testing & Permit Depressurizing SI Accumulators in Lieu of Accumulator Isolation ML18153A8371995-06-0808 June 1995 Proposed Tech Specs,Incorporating Revised Pressure/Temp Limits & Associated Ltops Setpoint That Will Be Valid to end-of-license ML18153B2301995-02-14014 February 1995 Proposed Tech Specs Re App J Testing Requirements ML18153B2131995-01-24024 January 1995 Proposed Tech Specs,Modifying as-found Test Acceptance Criterion for Pressurizer Safety Valves ML18153B1621994-11-29029 November 1994 Proposed Tech Specs Implementing Zirlo Fuel Cladding ML18153B1581994-11-22022 November 1994 Proposed Tech Specs,Deleting Unnecessary Descriptive Phrases Re Number of Cells in Station & EDG Batteries ML18153B1501994-11-10010 November 1994 Proposed Tech Specs Re Changes to TS Will Clarify SR for Reactor Protection & Engineered Safeguard Sys Instrumentation & Actuation Logic ML18153B0941994-10-11011 October 1994 Proposed Tech Specs Surveillance Frequencies for Hydrogen Analyzers ML18152A5061994-09-0606 September 1994 Proposed Tech Specs Re Mgt Safety Review Committee & Station Nuclear Safety & Operating Committee Responsibilities ML18152A1191994-08-30030 August 1994 Proposed Tech Specs to Accomodate Core Uprating ML18153B0061994-07-14014 July 1994 Proposed Tech Specs Changes Will Eliminate Remaining References to cycle-specific Parameters in Surry TS ML18152A1821994-06-0909 June 1994 Proposed TS Re Chemical & Vol Control Sys & Safety Injection Sys ML20065P6111994-04-19019 April 1994 Proposed Tech Specs,Modifying Control Rod Movement Surveillance Frequency ML18153A8821994-02-25025 February 1994 Proposed Tech Specs Modifying Surveillance Frequency of Nozzles in Containment & Recirculation Spray Sys ML18153B4321993-12-27027 December 1993 Proposed Tech Specs Reflecting Revised Review Responsibilities of Station Nuclear Safety & Operating Committee & Mgt Safety Review Committee ML18153B4081993-12-10010 December 1993 Proposed Tech Specs,Establishing Upper Limit on Allowable COLR Mtc Values ML18153B4021993-12-10010 December 1993 Proposed Tech Specs,Modifying Surveillance Frequency of Auxiliary Feedwater Sys Pumps from Monthly to Quarterly Per Generic Ltr 93-05 & NUREG-1431 ML18153B4051993-12-10010 December 1993 Proposed Tech Specs,Updating Augmented Insp Program for Sensitized Stainless Steel by Incorporating Newer Code Requirements,While Maintaining Augmented Insp Philosophy ML18153B3751993-11-15015 November 1993 Proposed Tech Specs Implementing Revised 10CFR20,revising Frequency Radiological Release Repts from Semiannual to Annual & Clarifying Site Maps ML18153B3501993-10-19019 October 1993 Proposed Tech Specs for RSHX Svc Water Outlet Radiation Monitors ML18153B3321993-09-29029 September 1993 Proposed Tech Specs Modifying Required Insp Frequency of Low Pressure Turbine Blades to Permit Blade Insp to Be Performed Concurrent W/Disk & Hub Insp ML18152A0481993-07-20020 July 1993 Proposed Tech Specs Deleting Requirement for Station Nuclear Safety & Operating Committee & Audit Frequencies ML18153D3921993-07-16016 July 1993 Proposed Tech Specs for Operation W/Three Degree Increase in Svc Water Temp Limit for Containment Air Partial Pressures of 9.1,9.2 & 9.35 Psia ML18152A0461993-07-16016 July 1993 Proposed Tech Specs Implementing Revised 10CFR20,revise Frequency of Radiological Effluent Release Repts from semi-annual to Annual,& Clarify Site Maps ML18152A4511993-07-0202 July 1993 Proposed Tech Specs to Include COLR Which Presents reload- Specific Limits for Key Core Operating Parameters ML18153D3811993-07-0202 July 1993 Proposed TS Table 4.2-1 Re Miscellaneous Insps & Sensitized Stainless Steel Exams ML18153D3331993-05-0606 May 1993 Proposed Tech Specs Supporting Operation of Unit 2 w/100 Psi Reduction in RCS Nominal Operating Pressure Through End of Operating Cycle 12 1999-08-23
[Table view] Category:TECHNICAL SPECIFICATIONS & TEST REPORTS
MONTHYEARML18152B3591999-08-23023 August 1999 Revised Tech Specs Basis Pages for TS 3.1.B,deleting Reactor Vessel Toughness Data Duplicated in UFSAR & Includes Ref to Applicable UFSAR Section ML18151A6641999-08-0606 August 1999 Rev 0 to Surry Unit 2 Cycle 16 Startup Physics Tests Rept. ML18152B6591999-04-28028 April 1999 Proposed Tech Specs Re Refueling Water Chemical Addition Tank Min Vol ML18152A2131999-02-16016 February 1999 Proposed Tech Specs,Consolidating AFW cross-connect Requirements by Relocation of Electrical Power Requirements from TS 3.16 to TS 3.6 ML18152B5451999-02-16016 February 1999 Proposed Tech Specs Pages,Revising Augmented Insp Requirements for Reactor Coolant Pump Flywheels ML18151A5511999-02-10010 February 1999 to NE-1187, Surry Unit 1,Cycle 16 Startup Physics Tests Rept. ML18152B6151998-11-0404 November 1998 Proposed Tech Specs 4.6.A.1.b,re EDG Start & Load Time Testing Requirements & TS 3.16 Bases Re EDG Ratings ML18153A3351998-09-24024 September 1998 Proposed Tech Specs Pages Affected by Suppl to 960912 Resubmittal of Change Request Re Relocation of Fire Protection Requirements from TS to UFSAR ML18153A3311998-09-24024 September 1998 Proposed Tech Specs Modifying Testing Requirements for Reactor Trip Bypass Breaker ML18152B7551998-06-19019 June 1998 Proposed Tech Specs Establishing Requirements for Use of Temporary Supply Line (Jumper) to Provide Svc Water to Component Cooling Heat Exchangers ML20249B9911998-05-0606 May 1998 Analysis of Capsule X Virginia Power Surry Unit 1 Reactor Vessel Matl Surveillance Program. W/Evaluation of Surry Unit 1 Surveillance Capsule X Results & Response to NRC RAI Re GL 92-01,rev 1,suppl 1 ML18151A1931998-05-0404 May 1998 Rev 1 to Summary of Changes to Surry Units 1 & 2 Third Interval IST Program. ML18152A3651998-03-25025 March 1998 Proposed Tech Specs Revising Station Mgt Titles to Reflect New Positions Approved by Vepc Board of Directors on 980220 ML20199B0711998-01-0505 January 1998 Rev 0 to NE-1148, Surry Unit 2,Cycle 15 Startup Physics Test Rept ML18153A3481997-12-18018 December 1997 Proposed Tech Specs Clarifying Terminology Used for Describing Equipment Surveillances Conducted on Refueling Interval Frequency.Clarification Consistent W/Info Contained in Rev 1 to NUREG-1431 ML18150A4661997-12-16016 December 1997 ISI Plan for Third Insp Interval,Vol 2,Rev 9 for Components & Component Supports,940510-040510, for Surry Power Station,Unit 2 ML18153A3941997-11-0505 November 1997 Proposed Tech Specs Re Change for Increased Enrichment of Reload Fuel ML18153A1761997-11-0505 November 1997 Proposed Tech Specs Re Temporary Svc Water Supply Line to Component Cooling Heat Exchangers ML18150A4641997-10-27027 October 1997 Risk-Informed ISI (RI-ISI) Pilot Program Submittal. ML18151A3911997-10-16016 October 1997 Rev 8 to VPAP-2103, Odcm. ML18151A7231997-08-0707 August 1997 Rev 1 to Nuclear Safety Analysis Manual Part Iv,Chapter a Probabilistic Safety Assessment Products. ML20210J5031997-07-31031 July 1997 Rev 0 to NE-1132, Surry Unit 1,Cycle 15 Startup Physics Tests Rept ML18150A4441997-06-0909 June 1997 Vol 2,Rev 8 to ISI Plan for Third Insp Interval for Components & Component Supports,Oct 14,1993-Oct 13,2003. ML18153A5231997-04-24024 April 1997 Proposed Corrected Tech Specs Pages 6.1-3 & 6.1-8 Re Relocation of Fire Protection TS to Updated Final Safety Analysis Rept ML18153A5031997-03-18018 March 1997 Proposed Tech Specs Rev to Section 4.15 for Surry Power Station to Include Pp Inadvertently Omitted from 970203 Request for Amend to Licenses DPR-32 & DPR-37 ML18153A4921997-02-0303 February 1997 Proposed Tech Specs Re Deletion of Specific ASME Section XI Code Ref ML18153A6351996-11-26026 November 1996 Proposed Tech Specs Re Removal of Record Retention Requirements,Per GL 95-06 & Administrative Ltr 95-06 ML18153A0671996-09-12012 September 1996 Proposed Tech Specs Re Relocation of Fire Protection Requirements ML18151A9761996-08-13013 August 1996 Cycle 14 Startup Physics Test Rept. W/960830 Ltr ML20134J9861996-07-30030 July 1996 /Unit 2 Fuel Assembly Insp Program ML18152A4701996-06-13013 June 1996 Cycle 13 Control Rod Performance Test Results. ML18153A6901996-04-15015 April 1996 Proposed Tech Specs,Clarifying Applicability of Quadrant Power Tilt Ration Requirements ML18153A5391996-03-21021 March 1996 Proposed Tech Specs Re Charcoal Filter Testing Clarification ML18153A5271996-03-14014 March 1996 Proposed Tech Specs,Permitting Use of 10CFR50 App J,Option B,performance-based Containment Lrt ML18153A5801996-01-30030 January 1996 Proposed Tech Specs Re Reactor Coolant Sys Liquid Sampling ML18152A0571995-12-20020 December 1995 Startup Physics Test Rept,Surry Unit 1,Cycle 14. W/960111 Ltr ML18153A6761995-11-20020 November 1995 Proposed Tech Specs Re App J Option B,performance-based Containment Leakage Rate Testing ML18151A6421995-08-0101 August 1995 Change 3 to Rev 0 to Third Interval IST Program ML18153A7141995-07-20020 July 1995 Proposed Tech Specs Establishing New Setpoint Limit for SG high-high Level & Provides More Restrictive Setting Limits for Certain Rps/Esfas Setpoints ML18153A6991995-07-14014 July 1995 Proposed Tech Specs,Providing Two H Allowed Outage Time for One RHR Pump to Accommodate Plant Safety,Emergency Power Sys Surveillance Testing & Permit Depressurizing SI Accumulators in Lieu of Accumulator Isolation ML18153A8371995-06-0808 June 1995 Proposed Tech Specs,Incorporating Revised Pressure/Temp Limits & Associated Ltops Setpoint That Will Be Valid to end-of-license ML20083C9951995-05-0808 May 1995 Rev 0 to Surry Unit 2,Cycle 13 Startup Physics Tests Rept ML18153B2301995-02-14014 February 1995 Proposed Tech Specs Re App J Testing Requirements ML18153B2131995-01-24024 January 1995 Proposed Tech Specs,Modifying as-found Test Acceptance Criterion for Pressurizer Safety Valves ML18153B1621994-11-29029 November 1994 Proposed Tech Specs Implementing Zirlo Fuel Cladding ML18153B1581994-11-22022 November 1994 Proposed Tech Specs,Deleting Unnecessary Descriptive Phrases Re Number of Cells in Station & EDG Batteries ML18153B1501994-11-10010 November 1994 Proposed Tech Specs Re Changes to TS Will Clarify SR for Reactor Protection & Engineered Safeguard Sys Instrumentation & Actuation Logic ML18153B0941994-10-11011 October 1994 Proposed Tech Specs Surveillance Frequencies for Hydrogen Analyzers ML18152A5061994-09-0606 September 1994 Proposed Tech Specs Re Mgt Safety Review Committee & Station Nuclear Safety & Operating Committee Responsibilities ML18152A1191994-08-30030 August 1994 Proposed Tech Specs to Accomodate Core Uprating 1999-08-06
[Table view] |
Text
TS 3.2-1 3.2 CHEMICAL AND VOLUME CONTROL SYSTEM Applicability Applies to the operational status of the Chemical and Volume Control Sys-tem.
Objective To define those conditions of the Chemical and Volume Control System necessary to ensure safe reactor operation.
Specification A. When fuel is in a reactor, there shall be at least one flow path to the core for boric acid injection. The minimum capability for boric acid injection shall be equivalent to that supplied from the refuel-ing water storage tank.
B. For one-unit operation, the reactor shall not be critical unless the following Chemical and Volume Control System conditions are met:
- 1. Two charging pumps shall be operable and one charging pump from the opposite unit shall be available*.
- 2. Two boric acid transfer pumps shall be operable.
- 3. The boric acid tanks (tank associated with the unit plus the common tank) together shall contain a minimum of 6000 gallons of at least 7.0% (but not >8.5%) by weight boric acid solution at a temperature of at least 112°F.
- Available means (1) operable except for automatic initiation instrumentation, (2) offsite or emergency power source may be inoperable in cold shutdown, and (3) it is capable of being used for alternate shutdown with the opening of the charging pump cross-connect.
, a4041001es 040403-----~1 PDR ADOCK 05000280 P PDR
TS 3.2-2
- 4. System piping and valves shall be operable to the extent of establishing two flow paths to the core; one flow path from the boric acid tanks to the charging pumps and a flow path from the refueling water storage tank to the charging pumps.
- 5. Two channels of heat tracing shall be operable for the flow paths requiring heat tracing.
- 6. System piping, valves and control board indication required for the operation of the two charging pumps in Specification 3.2.B.1 shall be operable, and system piping, valves and con-trol board indication required for the operation of the oppo-site unit charging pump in Specification 3.2.B.1 shall be available 7*.
C. For two-unit operation, the reactor shall not be critical unless the following Chemical and Volume Control System conditions are met:
- 1. Two charging pumps shall be operable per unit.
- 2. Three boric acid transfer pumps shall be operable.
- 3. When the common tank is in service, it shall be assigned to only one unit at a time. For that unit which has usage of the common tank, the boric acid tanks (unit's tank plus common tank) together shall contain a minimum of 6000 gallons of at least 7.0% (but not >8.5%) by weight boric acid solution at a temperature of at least 112°F.
- Available means (1) operable except for automatic initiation instrumentation, (2) offsite or emergency power source may be inoperable in cold shutdown, and (3) it is capable of being used for alternate shutdown with the opening of the charging pump cross-connect.
e TS 3.2-3 For that unit which does not have usage of the common tank, the unit's own tank shall contain a minimum of 6000 gallons of at least 7.0% (but not >8.5%) by weight boric acid solution at a temperature of at least 112°F.
When the common tank is assigned to one unit, valves shall be positioned to establish a flow path to that unit and prevent flow to the other unit.
- 4. System piping and valves shall be operable to the extent of establishing two flow paths to the core; one flow path from the boric acid tanks to the charging pumps and a flow path from the refueling water storage tank to the charging pumps.
- 5. Two channels of heat tracing shall be operable for the flow paths requiring heat tracing.
D. The requirements of Specifications 3. 2. B and 3. 2. C above may be modified to allow one of the following components to be inoperable at any one time. If the system is not restored within the time period specified, the reactor shall be placed in hot shutdown condi-tions. If the requirements of Specifications 3.2.B and 3.2.C are not satisfied within an additional 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br />, the reactor shall be placed in the cold shutdown condition.
- 1. One of the stipulated boric acid transfer pumps may be inoper-able for a period not to exceed 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> provided immediate attention is directed to making repairs.
- 2. Two charging pumps may be inoperable subject to the provisions of Specification 3.3.B.
- 3. One heat tracing circuit my be inoperable for a period not to exceed 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> provided immediate attention is directed to making repairs.
e TS 3.2-4 E. The requirements of Specifications 3.2.B.1 and 3.2.B.6, concerning the opposite unit's charging pumps and associated piping, valves and control board indications, may be modified to allow the follow-ing components to be unavailable.
- 1. The opposite unit's charging pumps may be unavailable for a period not to exceed 7 days provided immediate attention is directed to making repairs. If not available within 7 days, be in at least hot shutdown within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in cold shutdown within the next 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.
- 2. The cross tie piping, associated valves and control board instrumentation and controls may be unavailable for a period not to exceed 7 days provided immediate attention is directed to making repairs. If not available within 7 days, be in at least hot shutdown within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in cold shutdown within the next 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />.
Basis The Chemical and Volume Control System provides control of the Reactor Coolant System Boron inventory. This is normally accomplished by using boric acid transfer pumps which discharge to the suction of each unit's charging pumps. The Chemical and Volume Control System contains four boric acid transfer pumps. Two of these pumps are normally assigned to each unit but, valving and piping arrangements allow pumps to be shared such that three out of four pumps can service either unit. An alternate (not normally used) method of boration is to use the charging pumps taking suction directly from the refueling water storage tank. There are two sources of borated water available to the suction of the charging pumps through two different paths; one from the refueling water storage tank and one from the discharge of the boric acid transfer pumps.
A. The boric acid transfer pumps can deliver the boric acid tank contents (7.0% solution of boric acid) to the charging pumps.
e e TS 3.2-5 B. The charging pumps can take suction from the volume control tank, the boric acid transfer pumps and the refueling water storage tank.
Reference is made to Technical Specification 3.3.
The quantity of boric acid in storage from either the boric acid tanks or the refueling water storage tank is sufficient to borate the reactor coolant in order to reach cold shutdown at any time during core life.
Approximately 6000 gallons of the 7.0% solution of boric acid are required to meet cold shutdown conditions. Thus, a minimum of 6000 gallons in the boric acid tank is specified. An upper concentration limit of 8.5% boric acid in the tank is specified to maintain solution solubility at the specified low temperature limit of 112°F. For redundancy, two channels of heat tracing are insta1led on lines normally containing concentrated boric acid solution.
The Boric Acid Tank(s), which are located above the Boron Injection Tank(s), are supplied with level alarms which would annunciate if a leak in the system occurred.
For one-unit operation, it is required to ~aintain available one charging pump with a source of borated water on the opposite unit, the associated piping and valving, and the associated instrumentation and controls in order to maintain the capability to cross-connect the two unit's charging pump discharge headers. In the event the operating unit's charging pumps become inoperable, this permits the opposite unit's charging pump to be used to bring the disabled unit to cold shutdown conditions. Initially, the need for the charging pump cross-connect was identified during fire protection reviews.
e TS 3.2-6 REFERENCES FSAR Sections 9.1 Chemical and Volume Control System
e ATTACHMENT 2
DISCUSSION OF PROPOSED TECHNICAL SPECIFICATION CHANGE This proposed change supplements a previous change to Specification 3.2. A charging pump cross-connect modification was implemented in response to commitments made to the staff concerning Appendix A to Branch Technical Position 9. 5-1 and the Fire Protection Safety Evaluation Report for Surry Power Station dated September, 1979. The purpose of the charging pump cross-connect modification is to provide alternate shutdown capability.
Specification 3. 2 is revised to address the availability of charging pump capability from the non-operating unit during one unit operation. In the event the operating unit's charging pumps become inoperable, the opposite unit's charging pump may be used to bring the disabled unit to cold shutdown conditions. This proposed change allows the status of opposite unit charging pump to be "available". Available is defined as (1) operable except for automatic initiation instrumentation, (2) offsite or emergency power source may be inoperable in cold shutdown, and (3) it is capable of being used for alternate shutdown with the opening of charging pump cross-connect. This proposed change defines the condition where the opposite unit charging pump is available and capable of performing its intended function but may not meet the strict requirements of operable as defined in the Technical Specifications.
This proposed change also provides specific action to be in hot shutdown within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in cold shutdown within the next 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br /> in the event that the opposite unit's charging pumps, cross-tie piping, associated valves and control board instrumentation and controls are unavailable for a period of more than 7 days.
This proposed change does not involve a significant hazards consideration.
This change is best encompassed by Example (vi) of the examples provided for guidance by the NRG in the April 6, 1983 FR[l4870]; a change which either may result in some probability or consequences of a previously analyzed accident or may reduce in some way a safety margin, but where the results of the change are clearly within the acceptance criteria for the system or component. This proposed change does not degrade the use of the system. Any change to the margin of safety is insignificant because essentially the status of the opposite unit charging pump is unchanged. The component is still required to be able to perform its intended function. This change is to avoid the possibility of violating a definition of the Technical Specification when the opposite unit is in cold shutdown.
In addition, the editorial changes in this proposed change are encompassed by Example (i), of the examples provided for guidance by the NRG to determine that a significant hazards consideration is not involved. Example (i) states, A purely administrative change to technical specifications, for correction of errors, in this instance, typographical and minor editorial errors.
These changes are suggested by the NRG to clarify our previous submittal.