OCT 3 o 1981
Virginia Electric and Power Company
ATTN:
Mr. R. H. Leasburg, Vice President
Nuclear Operations
P. 0. Box 26666
Richmond, VA
23261
Gentlemen:
Subject:
Report Nos. ~~and 50-281/81-27
This refers to the routine safety inspection conducted by Mr. D. J. Burke of this
office on September 1-30, 1981, of activities authorized by NRC Operating License
Nos. DPR-32 and DPR-37 for the Surry facility and to the discussion of our
findings held with Mr. J. L. Wilson, Plant Manager, at the conclusion of the
inspection.
Areas examined during the inspection and our findings are discussed in the
enclosed inspection report. Within these areas, the inspection consisted of
selective examinations of procedures and representative records, interviews with
personnel, and observations by the inspector.
Within the~scope of this inspection, no violations or deviations were disclosed .
We have examined actions you have taken with regard to previously identified
enforcement matters. These are discussed in the enclosed inspection report.
In accordance with 10 CFR 2.790 of the Commission
1s regulations, a copy of this
letter and the enclosed report will be placed in the NRC's Public Document Room.
If the report contains any information that you believe to be exempt from dis-
closure unqer 10 CFR 9.5(a)(4), it is necessary that you:
(a) notify this office
by telephone within ten days from the date of this letter of your intention to
file a request for withholding; and (b) submit within twenty-five days from the
date of this letter a written application to this office to withhold such infor-
mation.
If your receipt of this letter has been delayed such that less than
seven days are available for your review, please notify this office promptly so
that a new due date may be established. Consistent with section 2.790(b)(l),
such application must be accompanied by an affidavit executed by the owner of the
information which identifies the document or part thereof sought to be withheld,
and a full statement of the reasons on the basis of which it is claimed that the
information should be withheld from public disclosure. This sec ti on further
requires the statement to address with specificity the considerations listed in
The information sought to be withheld shall be incorporated
as far as possible into a separate part of the affidavit.
If we do not hear from
you in this iegard within the specified periods noted above, the report will be
placed in the Public Document Room .
( 8112070464 811030 1
PDR ADOCK 05000280 J
-- G
_
PDR,
\\r, *
e
Virginia Electric and Power Company
.2
OCT 3 0 1981
Should you have any questions concerning this letter, we will be glad to discuss
them with you.
Enclosures:
Inspection Report No. 50-280/81-27
and 50-281/81-27
cc w/encl:
J. H. Ferguson, Executive
Vice President
J. L. Wilson, Manager
bee w/encl:
Document Management Branch
State of Virginia
\\
Sincerely,
fs(
Paul J. Kellogg, Chief
Reactor Projects Branch 2,
Division of Resident and
Reactor Project Inspection
RII :RR~~1
l:J-Cy
HDance
l0/17/81
RII: Rt'7
PJK~
10/?0/81