Forwards IE Info Notice 80-26, Evaluation of Contractor QA Programs. No Written Response Required
ML18139A464
Person / Time
Site: Surry, North Anna  Dominion icon.png
Issue date: 06/10/1980
From: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Ferguson J
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
References
NUDOCS 8007220066
Download: ML18139A464 (4)


Text

. *...*

  • - -~-- -*-~----~----*----~~=-.-~:::;-~.~.<;:.:,;..~

.. -..... :-:--=.::=:::===--=:-==~-* ---~-.. -. -.----,---:-:--:---,,------,---------

e e

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 101 MARIETTA ST., N.W., SUITE 3100 ATLANTA, GEORGIA 30303 JUN l O 1980 In Reply Refer To:

~AL'-

~1*

Virginia Electric and Power Company Attn:

J. H. Ferguson Executive Vice President-Power P. 0. Box 26666 Richmond, VA 23261 Gentlemen:

This Information Notice is being forwarded to you for information.

No written response to this Information Notice is required. If you have any questions related to the subject, please contact this office.

Sincerely,

~~

Enclosures:

1.

IE Information Notice No. 80-26

2.

List of Recently Issued IE Information Notices 8 0072 2 O o, (

  • Director 9

e Virginia Electric FoweJ;" Company cc w/encl:

W.. R. Cartwr~ght, Station Manager P.- 0. Box 402 Mineral, Virginia 23261 P. G. Perry Senior Resident Engineer Post Office Box 38 Mineral, Virginia 23117 J. L. Wilson, Manager Post Office Box 315 Surry, Virginia 23883 JUN 1 0 1980

-. 2.,..

UNITED STATES NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT WASHINGTON, D.C.

20555 June 10, 1980 SSINS No.:

6835 Accession No. :

8005050064 IE Information Notice No. 80-26 EVALUATION OF CONTRACTOR QA PROGRAMS Description of Circumstances:

Appendix B to 10 CFR 50 requires that each applicant and licensee establish and execute a Quality Assurance Program, and that each licensee "shall require contractors or subcontractors to provide a quality assurance program".

Further Appendix B requires each applicant and licensee to regularly review the status and adequacy of subcontractor programs.

The NRC is becoming increasingly concerned by continuing evidence that many holders of construction permits and operating licenses are not properly implementing these facets of their quality assurance programs.

Examples of this lack of effectiveness of contractor QA program implementation, and inadequacy of licensee ~verview of contractor QA program implementation are appearing in every facet of project activity.

Instances have been observed where architect-engineers have released documents for procurement with inappropriate material specifications.

Nuclear steam system suppliers have overlooked erroneous assumptions in analysis of instrument system response to design basis transients.

Other cases have been observed where both AE's and NSSS have not followed through on commitments to review vendor detailed designs.

Vendors' quality assurance programs have been found to contain errors of both omission and commission.

A containment tendon installation contract was awarded to a specialty contractor.

During a licensee audit some three months after work started it appeared that a contractor inspector was falsifying records by initialing inspection points not actually observed.

A subsequent investigation by the licensee revealed that the contractor had required that QC inspections be performed only on a random basis even though all records had QC signatures.. The signatures could mean that the activity was inspected or that record signoffs by others were reviewed; or that the data were recorded by the QC inspector. It is apparent that the licensee had not appropriately reviewed the contractor's inspection program prior to the start of work.

In another instance, after completion and acceptance of a major structural steel installation, the licensee found that significant rework would be required to correct construction quality problems.

NRC inspection at the contractors fabrication facility disclosed that in addition to work for that licensee, the contractor had contracts for "high density" fuel storage racks from several operating licensees. None of the.NRC licensees had inspected the contractor's shop or examined his quality assurance programs.

Response to Information Notice No. 80-26 is not required.

The NRC expects appropriate action from all licensees and organizations engaged in nuclear activities and actions will be examined in the ongoing NRC inspection program.

e IE Information Notice No. 80-26 June 10, 1980 Information Notice No. 80-26 80-25 80-24 80-23 80-22 80-21 80-20 80-19 80-18 RECENTLY ISSUED IE INFORMATION NOTICES Subject Evaluation of Contractor QA Programs Date*

Issued 6/10/80 Transportation of 5/30/80 Pyrophoric Uranium Low Level Radioactive 5/30/80 Waste Burial Criteria Loss of Suction to 5/29/80 to Emergency Breakdown In Contamination 5/28/80 Control Programs Anchorage and Support of 5/16/80 Safety-Related Electrical Equipment Loss of Decay Heat Removal 5/8/80 Capability at Davis-Besse Unit 1 While in a Refueling Mode NIOSH Recall of Recircu-5/6/80 lating-Mode (Closed-Circuit)

Self-Contained Breathing Apparatus (Rebreathers)

Possible Weapons Smuggling 5/5/80 Pouch e

Enclosure Issued To All power reactor facilities with an OL or CP, near-term CPs and 50 Fuel Facility Licensees Material Licensee in Priority/Categories II-A, II-D, III-I and IV-DI; Agreement State Licensees in equivalent categories All NRC and Agreement State Licensees All power reactor facilities with an OL or CP All power reactor OLs and near term CPs All power reactor facilities with an OL or CP All light water reactor facilities holding power reactor OLs or CPs All holders of a power reactor 01, Research Reactor License, Fuel Cycle Facility License and Priority I Material License All power reactor facilities with an OL, fuel fabrication and processing facilities and Materials Priority I licensees (processors and distributors)