UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION II
101 MARIETTA ST., N.W., SUITE 3100
ATLANTA, GEORGIA 30303
DEC - 5 1979
In Reply Refer To:
RII:JDW
50-281/79-81
Virginia Electric and Power Company
ATTN:
W. L. Proffitt
Senior Vice President, Power
P. 0. Box 26666
Richmond, VA 23261
Gentlemen:
This refers to the inspection conducted by J. D .,, Wilcox, Jr., of this office on
October 31 - November 2, 1979, of activities ~uthorized by NRC License No. DPR-37
for the Surry Power Station facility, and to the discussion of our findings held
with W. L. Stewart at the conclusion of the inspection.
Areas examined during the inspection and our findings are discussed in the
enclosed inspection report.
Within these areas,* the inspection consisted of
selective examinations of procedures and representative records, interviews with
personnel, and observations by the inspector.
We have examined actions you have taken with regard to previously identified en-
forcement matters. These are discussed in the enclosed inspection report.
During the inspection, it was found that certain activities under your license
appear to be in noncompliance with NRC requirements.
These items and references
to pertinent requirements ar~ listed in the Notice of Violation enclosed herewith
as Appendix A.
This notice is sent to you pursuant to the provisions of Section
2.201 of the NRC's "Rules of Practice," Part 2, Title 10, Code of Federal Regula-
tions.
Section 2.201 requires you to submit to this office, within 20 days of
your receipt of this notice, a written statement or explanation in reply including:
(1) corrective steps which have been taken by you and the results achieved; (2)
corrective steps which will be taken to avoid further noncompliance; and (3) the
date when full compliance will be achieved.
In accordance with Section 2.790 of the NRC's "Rules of Practice," Part 2, Title
10, Code of Federal Regulations, a copy of this letter and the enclosed inspection
report will be placed in the NRC's Public Document Room. If this report contains
any information that you (or your contractor) believe to be proprietary, it is
necessary that you make a written application within 20 days to this office-to
withhold such information from public disclosure.
Any such application must
include a full statement of the reasons on the basis of which it is claimed th~t
the information is proprietary, and should be prepared so that proprietary
information identified in the application is contained in a separate part of the
document. If we do not hear from you in this regard within the specified period,
the report will be placed in the Public Document Room.
soo2oso ~13
Virginia Electric and Power Company
-2-
DEC - 5 1979
Should you have any questions concerning this letter, we will be glad to discuss
them with you.
Sincerely,
~~
C. E. M~r J~
Reactor onstruction
Supp rt Branch
Enclosures:
1.
Appendix A, Notice of Violation
2.
Inspection Report No. 50-281/79-81
cc w/encl:
W. L. Stewart, Manager
P. 0. Box 315
Surry, VA
23883
and Engineering
__ __J