ML18136A211

From kanterella
Jump to navigation Jump to search
Forwards IE Insp Repts 50-280/79-45 & 50-281/79-64 on 790730-0803 & Notice of Violation
ML18136A211
Person / Time
Site: Surry  Dominion icon.png
Issue date: 09/07/1979
From: Murphy C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Proffitt W
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
Shared Package
ML18136A209 List:
References
REF-SSINS-5400 NUDOCS 7911260137
Download: ML18136A211 (2)


See also: IR 05000280/1979045

Text

..

To:

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTA ST., N.W., SUITE 3100

ATLANTA, GEORGIA 30303

SEP O 7 1979

Virginia Electric and Power Company

Attn:

W. L. Proffitt

Senior Vice President, Power

Post Office Box 26666

Richmond, Virginia 23261

Gentlemen:

This refers to the inspection conducted by J. l- Blake of this office on

July 30 through August 3, 1979 of activities authorized by NRC License

Nos. DPR-32 and DPR-37 for the Surry Nuclear Power facility, and to the

discussion of our findings held with J. L. Wilson at the conclusion of

the inspection.

Areas examined during the inspection and our findings are discussed in

the enclosed inspection report.

Within these areas, the inspection

consisted of selective examinations of procedures and representative

records, interviews with personnel, and observations by the inspector.

One new unresolved item resulted from this inspection and is discussed

in the enclosed report.

This item will be examined during subsequent

inspections.

During the inspection, it was found that certain activities under your

license appear to be in noncompliance with NRC requirements.

These

items and references to pertinent requirements are listed in the Notice'

of Violation enclosed herewith as Appendix A.

This notice is sent to

you pursuant to the provisions of Section 2.201 of the NRC's "Rules of

Practice", Part 2, Title 10, Code of Federal Regulations.

Section 2.201

requires you to submit to this office, within 20 days of your receipt of

this notice, a written statement or explanation in reply including:

(1)

corrective steps which have been taken by you, and the results achieved;

(2) corrective steps which will be taken to avoid further noncompliance;

and (3) the date when full compliance will be achieved.

In accordance with Section 2.790 of the NRC's "Rules of Practice,"

Part 2, Title 10, Code of Federal Regulations, a copy of this letter and

the enclosed inspection report will be placed in the NRC's .Public Document

Room.

If this report contains any information that you (or your contractor)

believe to be proprietary, it is necessary that you make a written

\\

..

Virginia Electric and

Power Company

-2-

SEP O 7 1979

application within 20 days to this office to withhold such information

from public disclosure.

Any such application must include a full statement

of the reasons on the basis of which it is claimed that the information

is proprietary, and should be prepared so that proprietary information

identified in the application is contained in a separate part of the

document.

If we do not hear from you in this regard within the specified

period, the report will be placed in the Public Document Room.

Should you have any questions concerning this letter, we will be glad to

discuss them with you.

Enclosures:

Sincerely,

C * E . Murntw--;;-, -t1trn

Reactor Construction and

Engineering Support Branch

1.

Appendix A, Notice of Violation

2.

Inspection Report Nos. 50-280/79-45

and 50-281/79-64

cc w/enclosures:

W. *1. Stewart, Manager

Post Office Box 315

Surry, Virginia 23883