Other: ML18130A760, ML18130A820, ML18130A849, ML18130A885, NRC-2018-0187, Firstenergy Nuclear Operating Company (Fenoc); Firstenergy Nuclear Generation Company, LLC - Environmental Assessment, NRC-2018-0192, Firstenergy Nuclear Operating Company (Fenoc); Firstenergy Nuclear Generation, LLC; Environmental Assessment, NRC-2018-0193, First Energy Operating Company (FENOC) Firstenergy Nuclear Generation, LLC, Beaver Valley Power Station, Units 1 and 2
|
MONTHYEARL-17-112, Exemption Request for Physical Barrier Requirement2017-07-19019 July 2017 Exemption Request for Physical Barrier Requirement Project stage: Request ML17262A7232017-09-20020 September 2017 FENOC Fleet - Results of Acceptance Review of the Exemption Request Exemption from the Definition of Physical Barrier in 10 CFR 73.2 for Physical Security Plans Project stage: Acceptance Review L-18-061, Units. 1 & 2, Davis-Besse, and Perry, Response to Request for Additional Information Regarding Exemption Request for a Physical Barrier Requirement2018-03-16016 March 2018 Units. 1 & 2, Davis-Besse, and Perry, Response to Request for Additional Information Regarding Exemption Request for a Physical Barrier Requirement Project stage: Response to RAI L-18-125, Response to Follow-up Request for Additional Information Regarding Exemption Request for a Physical Barrier Requirement IEPID-L-2017-l-LE-0019 (CAC Nos.000976/05000334/-L-2017-LLE-0019 MG0010, 000976/05000334/L-2017-LLE-0019 MG0011,000976/02018-05-0202 May 2018 Response to Follow-up Request for Additional Information Regarding Exemption Request for a Physical Barrier Requirement IEPID-L-2017-l-LE-0019 (CAC Nos.000976/05000334/-L-2017-LLE-0019 MG0010, 000976/05000334/L-2017-LLE-0019 MG0011,000976/0 Project stage: Request ML18130A8852018-08-29029 August 2018 FENOC Fleet - Beaver Valley; Davis-Besse; Perry - Environment Assessment and Finding of No Significant Impact Related to Exemption Request for a Physical Barrier Requirement (CAC Nos. MG0010, MG0011, MG0012, and MG0013; EPID L-2018-LLE-0019 Project stage: Other ML18130A8892018-08-29029 August 2018, 4 September 2018 Environmental Assessment and Finding of No Significant Impact Related to Exemption Request for a Physical Barrier Requirement Project stage: Request ML18130A7602018-09-0404 September 2018 First Energy Operating Company (FENOC) Firstenergy Nuclear Generation, LLC, Beaver Valley Power Station, Units 1 and 2 Project stage: Other ML18130A8492018-09-0404 September 2018 Firstenergy Nuclear Operating Company (Fenoc); Firstenergy Nuclear Generation, LLC; Environmental Assessment Project stage: Other ML18130A8202018-09-0404 September 2018 Firstenergy Nuclear Operating Company (Fenoc); Firstenergy Nuclear Generation Company, LLC - Environmental Assessment Project stage: Other NRC-2018-0192, Firstenergy Nuclear Operating Company (Fenoc); Firstenergy Nuclear Generation, LLC; Environmental Assessment2018-09-0404 September 2018 Firstenergy Nuclear Operating Company (Fenoc); Firstenergy Nuclear Generation, LLC; Environmental Assessment Project stage: Other NRC-2018-0187, Firstenergy Nuclear Operating Company (Fenoc); Firstenergy Nuclear Generation Company, LLC - Environmental Assessment2018-09-0404 September 2018 Firstenergy Nuclear Operating Company (Fenoc); Firstenergy Nuclear Generation Company, LLC - Environmental Assessment Project stage: Other NRC-2018-0193, First Energy Operating Company (FENOC) Firstenergy Nuclear Generation, LLC, Beaver Valley Power Station, Units 1 and 22018-09-0404 September 2018 First Energy Operating Company (FENOC) Firstenergy Nuclear Generation, LLC, Beaver Valley Power Station, Units 1 and 2 Project stage: Other 2018-03-16
[Table View] |
|
---|
Category:Environmental Assessment
MONTHYEARML22147A1252022-07-14014 July 2022 Federal Register Notice: Environmental Assessment and Finding of No Significant Impact Regarding License Amendment Request to Revise the Emergency Plan for Davis-Besse Nuclear Power Station, Unit No. 1 ML19162A0092019-06-0707 June 2019 Enclosufinal Environmental Assessment (Memorandum to File Environmental Assessment and Finding of No Significant Impact for Firstenergy Nuclear Operating Company'S Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(B) an ML18130A8492018-09-0404 September 2018 Firstenergy Nuclear Operating Company (Fenoc); Firstenergy Nuclear Generation, LLC; Environmental Assessment NRC-2018-0192, Firstenergy Nuclear Operating Company (Fenoc); Firstenergy Nuclear Generation, LLC; Environmental Assessment2018-09-0404 September 2018 Firstenergy Nuclear Operating Company (Fenoc); Firstenergy Nuclear Generation, LLC; Environmental Assessment ML18130A8852018-08-29029 August 2018 FENOC Fleet - Beaver Valley; Davis-Besse; Perry - Environment Assessment and Finding of No Significant Impact Related to Exemption Request for a Physical Barrier Requirement (CAC Nos. MG0010, MG0011, MG0012, and MG0013; EPID L-2018-LLE-0019 ML16336A0622017-01-0404 January 2017 Environmental Assessment and Finding of No Significant Impact Related to License Amendment Request to Revise Technical Specification 5.5.3, Radioactive Effluents Controls Program ML1016102642010-06-17017 June 2010 Environmental Assessment and Finding of No Significant Impact ML1006105732010-03-18018 March 2010 Frn:General - Davis-Besse Environmental Assessment and Finding of No Significant Impact ML1006105462010-03-18018 March 2010 Environmental Assessment and Finding of No Significant Impact (Ltr.) ML0828400992008-10-0808 October 2008 Assessment -Davis-Besse Nuclear Power Station, Unit No. 1 - Environmental Assessment and Finding of No Significant Impact for the Proposed Conversion to the Improved Technical Specifications (TAC 6398) ML0820004512008-10-0808 October 2008 Environmental Assessment and Finding of No Significant Impact for the Proposed Conversion to the Improved Technical Specifications ML0822706622008-08-0707 August 2008 Improved Technical Specification Conversion License Amendment Request, Volume 2, Revision 1, Generic Determination of No Significant Hazards Consideration and Environmental Assessment ML0722004562007-08-0303 August 2007 Volume 2, Revision 0, Davis-Besse, Unit 1 - Improved Technical Specifications Conversion, Generic Determination of No Significant Hazards Consideration and Environmental Assessment. ML0509702532005-07-0606 July 2005 Environmental Assessment and Finding of No Significant Impact ML0413406962004-07-29029 July 2004 Environmental Assessment, Acceptance Criteria for Emergency Core Cooling Systems for Light-Water Nuclear Power Reactors and ECCS Evaluation Models ML0411002922004-05-12012 May 2004 Letter, Environmental Assessment and Finding of No Significant Impact Related to Your Application for Withdrawal of Exemption Alternative Shutdown Capability to Achieve Cold Shutdown within 72 Hours of Offsite Power 2022-07-14
[Table view] Category:Federal Register Notice
MONTHYEARML24134A1562024-09-19019 September 2024 Exemption from the Requirements of 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule (EPID L-2024-LLE-0005) - FRN ML24102A2572024-04-25025 April 2024 Federal Register Notice - Issuance of Multiple Exemptions Regarding 10 CFR Part 73 - March 2024 ML23237B4412023-09-29029 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Federal Register Notice, Direct and Indirect License Transfer Issuance Order ML23124A0772023-05-17017 May 2023 Notice of Consideration of Approval of Indirect and Direct License Transfer for Comanche Peak Plant, Units 1 & 2, Beaver Valley Station, Units 1 & 2, Davis Besse Station, Unit 1 and Perry Plant, Unit 1 (EPID L-2023-LLM-0000) (FRN) ML23129A0112023-05-16016 May 2023 Notice of Consideration of Approval of Indirect and Direct License Transfer for Comanche Peak Plant, Units 1 & 2, Beaver Valley Station, Units 1 & 2, Davis Besse Station, Unit 1 and Perry Plant, Unit 1 (EPID L-2023-LLM-0000) (Letter) ML22147A1252022-07-14014 July 2022 Federal Register Notice: Environmental Assessment and Finding of No Significant Impact Regarding License Amendment Request to Revise the Emergency Plan for Davis-Besse Nuclear Power Station, Unit No. 1 ML22147A1242022-07-14014 July 2022 Environmental Assessment and Finding of No Significant Impact Regarding License Amendment Request to Revise the Emergency Plan ML22034A9832022-02-15015 February 2022 FRN - Notice of Issuance of COVID-19 Exemptions Issued in January 2022 ML21123A0842021-05-19019 May 2021 FRN - Notice of Issuance of Multiple COVID-19 Exemptions Regarding Various Parts of 10 CFR Issued in April 2021 ML20335A0902020-12-21021 December 2020 Federal Register Notice - November 2020 COVID-19 Exemptions ML20119B0682020-05-0808 May 2020 Exemption ML20119B0702020-05-0808 May 2020 Federal Register Notice ML19303A0672019-12-0202 December 2019 Firstenergy Nuclear Operating Company - Federal Register Notice, Order Approving Direct and Indirect Transfer of Licenses and Draft Conforming Amendments for Beaver Valley Units 1 and 2, Davis-Besse Unit 1, and Perry Unit 1 ML19212A1372019-08-0606 August 2019 Federal Register Notice for Withdrawal of October 22, 2018, License Amendment Application ML19212A1352019-08-0606 August 2019 Federal Register Notice for Withdrawal of February 5, 2019, License Amendment Application for Post-Shutdown Emergency Plan ML19212A1362019-08-0606 August 2019 Federal Register Notice for Withdrawal of February 5, 2019, License Amendment Application for Permanently Defueled Technical Specifications ML19212A1392019-08-0606 August 2019 Withdrawal of Licensing Actions Associated with the Permanent Shut Down of the Plant (Epids L-2018-LLA-0287, L-2019-LLA-0011, L-2019-LLA-0012, L-2019-LLE-0011, and L-2019-LLQ-0000) ML19162A1332019-07-31031 July 2019 Federal Register Notice: Firstenergy Nuclear Operating Company Davis-Besse ISFSI - Environmental Assessment and Finding of No Significant Impact; Issuance ML19151A4742019-06-24024 June 2019 Letter to FENOC - Individual FRN Regarding Application for Order Consenting to Transfer of Licenses and Conforming Amendments. Notice of Consideration of Approval of Transfers and Conforming Amendments and Opportunity for Comments and a Hea ML19151A4932019-06-24024 June 2019 Individual FRN Regarding Application for Transfer of Licenses and Conforming Amendments. Notice of Consideration of Approval of Transfer of Facility Operating Licenses and Conforming Amendments, and Opportunity for Comments and a Hearing ML19067A0222019-06-0404 June 2019 FENOC - Exemption (EPID-L-2018-LLE-0016) ML19067A0232019-06-0404 June 2019 FENOC - Notice of Issuance of Exemption FRN (EPID-L-2018-LLE-0016) ML19133A0722019-05-16016 May 2019 FENOC Fleet - Beaver Valley 1 & Davis Besse 1 Withdrawal of an Amendment Request Administrative License Amendment Request to Reflect a Change in the Entity Providing a $400 Million Support Agreement (CAC Nos. MF9714 & MF9715, EPID L-2017-LL ML19133A0492019-05-16016 May 2019 FENOC Fleet FRN Notice Withdrawal of the Application ML19052A0412019-04-0404 April 2019 OEDO-18-00160 - Notice of Issuance of Final Director'S Decision in FRN ML19085A2172019-03-29029 March 2019 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 04/09/2019 ML19056A5352019-02-28028 February 2019 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 03/12/2019 NRC-2019-0065, Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 03/12/20192019-02-28028 February 2019 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 03/12/2019 NRC-2018-0192, Firstenergy Nuclear Operating Company (Fenoc); Firstenergy Nuclear Generation, LLC; Environmental Assessment2018-09-0404 September 2018 Firstenergy Nuclear Operating Company (Fenoc); Firstenergy Nuclear Generation, LLC; Environmental Assessment ML18130A8492018-09-0404 September 2018 Firstenergy Nuclear Operating Company (Fenoc); Firstenergy Nuclear Generation, LLC; Environmental Assessment ML18130A8852018-08-29029 August 2018 FENOC Fleet - Beaver Valley; Davis-Besse; Perry - Environment Assessment and Finding of No Significant Impact Related to Exemption Request for a Physical Barrier Requirement (CAC Nos. MG0010, MG0011, MG0012, and MG0013; EPID L-2018-LLE-0019 ML18220B3172018-08-27027 August 2018 OEDO-18-00160, Individual Fr Notice for Publication, 10 CFR 2206 Request-Action, FENOC Fleet 2.206 Petition ML18220B3142018-08-27027 August 2018 OEDO-18-00160 - Acknowledgement Letter 2.206 Petition for Citizen Complaint and Request for Enforcement Action Regarding Firstenergy Nuclear Facility Operations in Ohio and Pennsylvania NRC-2018-0174, OEDO-18-00160, Individual Fr Notice for Publication, 10 CFR 2206 Request-Action, FENOC Fleet 2.206 Petition2018-08-27027 August 2018 OEDO-18-00160, Individual Fr Notice for Publication, 10 CFR 2206 Request-Action, FENOC Fleet 2.206 Petition ML16336A0622017-01-0404 January 2017 Environmental Assessment and Finding of No Significant Impact Related to License Amendment Request to Revise Technical Specification 5.5.3, Radioactive Effluents Controls Program ML16250A3132016-09-0707 September 2016 EA-16-022 Davis Besse FRN Notice NRC-2016-0191, EA-16-022 Davis Besse FRN Notice2016-09-0707 September 2016 EA-16-022 Davis Besse FRN Notice ML16061A3012016-03-0202 March 2016 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: March 15, 2016 ML15294A4112015-12-0808 December 2015 License Renewal FRN ML15070A4002015-04-29029 April 2015 FRN-Notice of Availability of the Final Plant-Specific Supplement 52 to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Davis-Besse Nuclear Power Station, Unit 1 ML13018A2392015-04-0808 April 2015 G20110171 - Letter to Petitioner Saporito on Proposed Director'S Decision Regarding 2.206 Petition Dated: March 12, 2011 NRC-2014-0162, Federal Register Notice - Confirmatory Order Modifying License, Davis-Besse Nuclear Power Station, Unit 12014-06-30030 June 2014 Federal Register Notice - Confirmatory Order Modifying License, Davis-Besse Nuclear Power Station, Unit 1 ML14164A2102014-06-30030 June 2014 Federal Register Notice - Confirmatory Order Modifying License, Davis-Besse Nuclear Power Station, Unit 1 ML14050A0782014-02-24024 February 2014 Notice of Availability of Draft Plant-Specific Supplement 52 to Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Davis-Besse Nuclear Power Station, Unit 1 ML13225A5572013-08-12012 August 2013 Rescission of Certain Security Orders Concerning Spent Nuclear Fuel in Transit ML13228A3992013-08-12012 August 2013 Letter to Holders of Independent Spent Fuel Storage Installation (ISFSI) Licenses Re Rescission of Certain Security Orders Concerning Spent Nuclear Fuel in Transit - Rin 3150-AI64 (NRC-2009-0163) EA-02-109 ML13155A1132013-06-0404 June 2013 Federal Register Notice Published 6/4/2013, 78 Fr 33448-33449, Application for License to Export High-Enriched Uranium ML12237A1572012-08-28028 August 2012 Federal Register Notice Regarding the ACRS Plant License Renewal (Davis Besse)Subcommittee Meeting, September 19, 2012 ML1208002922012-03-20020 March 2012 Sunshine Federal Register Notice for Week of March 26, 2012 ML12056A0442012-03-12012 March 2012 Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Effective Immediately) - to All Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status 2024-09-19
[Table view] Category:Finding of No Significant Impact
MONTHYEARML19162A0092019-06-0707 June 2019 Enclosufinal Environmental Assessment (Memorandum to File Environmental Assessment and Finding of No Significant Impact for Firstenergy Nuclear Operating Company'S Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(B) an ML18130A8492018-09-0404 September 2018 Firstenergy Nuclear Operating Company (Fenoc); Firstenergy Nuclear Generation, LLC; Environmental Assessment NRC-2018-0192, Firstenergy Nuclear Operating Company (Fenoc); Firstenergy Nuclear Generation, LLC; Environmental Assessment2018-09-0404 September 2018 Firstenergy Nuclear Operating Company (Fenoc); Firstenergy Nuclear Generation, LLC; Environmental Assessment ML18130A8852018-08-29029 August 2018 FENOC Fleet - Beaver Valley; Davis-Besse; Perry - Environment Assessment and Finding of No Significant Impact Related to Exemption Request for a Physical Barrier Requirement (CAC Nos. MG0010, MG0011, MG0012, and MG0013; EPID L-2018-LLE-0019 ML1006105462010-03-18018 March 2010 Environmental Assessment and Finding of No Significant Impact (Ltr.) ML0413406962004-07-29029 July 2004 Environmental Assessment, Acceptance Criteria for Emergency Core Cooling Systems for Light-Water Nuclear Power Reactors and ECCS Evaluation Models ML0411002922004-05-12012 May 2004 Letter, Environmental Assessment and Finding of No Significant Impact Related to Your Application for Withdrawal of Exemption Alternative Shutdown Capability to Achieve Cold Shutdown within 72 Hours of Offsite Power 2019-06-07
[Table view] |
Text
[7590-01-P]
NUCLEAR REGULATORY COMMISSION
[Docket No. 50-346; NRC-2018-0192]
FirstEnergy Nuclear Operating Company (FENOC)
FirstEnergy Nuclear Generation, LLC Davis-Besse Nuclear Power Station, Unit No. 1 AGENCY: Nuclear Regulatory Commission.
ACTION: Environmental assessment and finding of no significant impact; issuance.
SUMMARY
- The U.S. Nuclear Regulatory Commission (NRC) is making a finding of no significant impact (FONSI) for a proposed issuance of an exemption to FirstEnergy Nuclear Operating Company (FENOC, the licensee), for Davis-Besse Nuclear Power Station (DBNPS), Unit No. 1, located in Ottawa County, Ohio. The proposed action would grant the licensee a partial exemption from the Physical barrier requirements in the NRCs regulations, to allow FENOC to continue using vertical, rather than angled, barbed wire fence toppings in certain limited protected area sections on-site. The NRC is considering an Exemption to Renewed Facility Operating License No. NPF-3, issued on December 8, 2015, and held by FirstEnergy Nuclear Operating Company (FENOC);
and First Energy Nuclear Generation, LLC; for the operation of DBNPS, Unit No. 1.
DATES: The environmental assessment referenced in this document is available on September 4, 2018.
ADDRESSES: Please refer to Docket ID NRC-2018-0192 when contacting the NRC about the availability of information regarding this document. You may obtain publicly-available information related to this document using any of the following methods:
- Federal Rulemaking Web Site: Go to http://www.regulations.gov and search for Docket ID NRC-2018-0192. Address questions about NRC dockets to Jennifer Borges; telephone: 301-287-9127; e-mail: Jennifer.Borges@nrc.gov. For technical questions, contact the individual listed in the FOR FURTHER INFORMATION CONTACT section of this document.
- NRCs Agencywide Documents Access and Management System (ADAMS): You may obtain publicly-available documents online in the ADAMS Public Documents collection at: http://www.nrc.gov/reading-rm/adams.html. To begin the search, select Begin Web-based ADAMS Search. For problems with ADAMS, please contact the NRCs Public Document Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or by e-mail to PDR.Resource@nrc.gov. For the convenience of the reader, the ADAMS accession numbers are provided in a table in the Availability of Documents section of this document.
- NRCs PDR: You may examine and purchase copies of public documents at the NRCs PDR, Room O1-F21, One White Flint North, 11555 Rockville Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT: Bhalchandra K. Vaidya, Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington DC 20555-0001; telephone: 301-415-3308; e-mail: Bhalchandra.Vaidya@nrc.gov.
2
SUPPLEMENTARY INFORMATION:
I. Introduction The NRC is considering issuance of a partial exemption, pursuant to section 73.5 of title 10 of the Code of Federal Regulations (10 CFR) , Specific exemptions, from the Physical barrier requirements of 10 CFR 73.2, specifically with respect to the design criteria specified in 10 CFR 73.2 (1) fences, as it applies to the angular specification for brackets used to support the required barbed wire (or similar material) topper, to FirstEnergy Nuclear Operating Company (FENOC) and First Energy Nuclear Generation, LLC (collectively, the licensee), for DBNPS, Unit No. 1, located in Ottawa County, Ohio.
In accordance with 10 CFR 51.21, the NRC has prepared an environmental assessment (EA) that analyzes the environmental effects of the proposed action. Based on the results of the EA, and in accordance with 10 CFR 51.31(a), the NRC has prepared a FONSI for the proposed exemption.
II. Environmental Assessment Description of the Proposed Action The proposed action would grant the licensee a partial exemption from the physical barrier requirements of 10 CFR 73.2, specifically with respect to the design criteria specified in 10 CFR 73.2 (1) fences, as it applies to the angular specification for brackets used to support the required barbed wire (or similar material) topper. As stated in 10 CFR 73.2, fences must be constructed of No. 11 American wire gauge, or heavier wire fabric, topped by three strands or more of barbed wire or similar material on 3
brackets angled inward or outward between 30 and 45 degrees from the vertical, with an overall height of not less than 8 feet, including the barbed topping. If approved, the partial exemption would allow the licensee to continue to use, without modification, the current configuration of vertical barbed wire fence toppings in limited protected area sections on-site, as specified on the maps submitted by the licensee in its letter dated March 16, 2018, to meet the regulatory requirements of 10 CFR part 73, Physical protection of plants and materials. Specifically, barbed wire on top of physical barrier fencing on gates, near gates, near interfaces with buildings, and on corners is oriented vertically.
The proposed action is in accordance with the licensees application dated July 19, 2017, as supplemented by letters dated March 16, 2018; and May 2, 2018.
Need for the Proposed Action Physical protection consists of a variety of measures to protect nuclear facilities and material against sabotage, theft, diversion, and other malicious acts. The NRC and its licensees use a graded approach for physical protection, consistent with the significance of the facilities or material to be protected. In so doing, the NRC establishes the regulatory requirements and assesses compliance, and licensees are responsible for providing the protection.
The proposed action is needed to allow the licensee to continue to use, without modification, the current configuration of vertical barbed wire fence toppings in certain limited protected area sections on-site, as shown on the maps submitted by the licensee in its March 16, 2018, letter. Currently, some of the barbed wire bracketing on top of the protected area physical barrier fencing do not meet certain design criteria specified in 4
10 CFR 73.2. Specifically, barbed wire on top of physical barrier fencing on gates, near gates, near interfaces with buildings, and on corners is oriented vertically.
Separate from this EA, the NRC staff is evaluating the licensees proposed action which will be documented in a safety evaluation report. The staffs review will determine whether there is reasonable assurance that the site maintains adequate protection from the current physical barriers in accordance with the requirements in 10 CFR part 73.
Environmental Impacts of the Proposed Action The NRC has completed its environmental evaluation of the proposed action.
The proposed action would grant the licensee a partial exemption from the physical barrier requirements of 10 CFR 73.2, specifically with respect to the design criteria specified in 10 CFR 73.2 (1) fences, as it applies to the angular specification for brackets used to support the required barbed wire (or similar material) topper. This will allow the licensee to continue using vertical, rather than angled, barbed wire fence toppings in certain limited protected area sections on site.
The proposed action would have no direct impacts on land use or water resources, including terrestrial and aquatic biota as the proposed action involves no new construction or modification of plant operational systems. There would be no changes to the quality or quantity of non-radiological effluents. No changes to the plants National Pollutant Discharge Elimination System permit are needed. In addition, there would be no noticeable effect on air pollutant emissions, socio-economic conditions in the region, no environment justice impacts, and no impacts to historic and cultural resources.
Therefore, there would be no significant non-radiological impacts associated with the proposed action.
5
The NRC has concluded that the proposed action would not significantly affect plant safety and would not have a significant adverse effect on the probability of an accident occurring. There would be no change to radioactive effluents that affect radiation exposures to plant workers and members of the public. No changes would be made to plant buildings or the site property. Therefore, implementing the proposed action would not result in a change to the radiation exposures to the public or radiation exposure to plant workers.
Environmental Impacts of the Alternatives to the Proposed Action As an alternative to the proposed action, the NRC considered denial of the proposed action (i.e., the no-action alternative). Denial of the exemption request would result in the licensee having to replace the vertical barbed wire fence toppings with angled barbed wire that meets the definition of Physical barrier in 10 CFR 73.2. This could result in temporary, minor changes in vehicular traffic and associated air pollutant emissions due to any construction-related impacts of performing the necessary modifications, but no significant changes in ambient air quality would be expected.
Alternative Use of Resources There are no unresolved conflicts concerning alternative uses of available resources under the proposed action.
Agencies and Persons Consulted The NRC staff did not enter into consultation with any other Federal agency or with the State of Ohio regarding the environmental impact of the proposed action.
6
III. Finding of No Significant Impact The licensee has requested an exemption from the physical barrier requirements of 10 CFR 73.2, specifically with respect to the design criteria specified in 10 CFR 73.2(1) fences, to allow the licensee to continue using vertical, rather than angled, barbed wire fence toppings in limited protected area sections on site. The NRC is considering issuing the requested exemption. The proposed action would not significantly affect plant safety, would not have a significant adverse effect on the probability of an accident occurring, and would not have any significant radiological and non-radiological impacts. This FONSI incorporates by reference the EA in Section II of this notice. Therefore, the NRC concludes that the proposed action will not have a significant effect on the quality of the human environment. Accordingly, the NRC has determined not to prepare an environmental impact statement for the proposed action.
The related environmental document is NUREG-1437 Generic Environmental Impact Statement for License Renewal of Nuclear Plants: Regarding the Davis-Besse Nuclear Power Station, Final Report, Supplement 52, Volumes 1 and 2, which provides the latest environmental review of current operations and a description of environmental conditions at DBNPS.
The finding and other related environmental documents may be examined, and/or copied for a fee, at the NRCs Public Document Room (PDR), located at One White Flint North, 11555 Rockville Pike, Rockville, Maryland 20852. Publicly-available records will be accessible electronically from ADAMS Public Electronic Reading Room on the Internet at the NRCs Web Site: http://www.nrc.gov/reading-rm/adams.html.
Persons who do not have access to ADAMS or who encounter problems in accessing the documents located in ADAMS should contact the NRCs PDR Reference 7
staff by telephone at 1-800-397-4209 or 301-415-4737, or send an e-mail to pdr.resource@nrc.gov.
IV. Availability of Documents The documents identified in the following table are available to interested persons through one or more of the following methods, as indicated.
DOCUMENT ADAMS ACCESSION NO.
FirstEnergy Nuclear Operating Company ML17200D139 Exemption Request for a Physical Barrier Requirement Dated July 19, 2017 FirstEnergy Nuclear Operating Company ML18078A033 Response to Request For Additional Information Regarding Exemption Request for a Physical Barrier Requirement Dated March 16, 2018 FirstEnergy Nuclear Operating Company ML18122A133 Response to Request For Additional Information Regarding Exemption Request for a Physical Barrier Requirement Dated May 2, 2018 NUREG-1437, Supplement 52, Vol. 1 and 2 ML15112A098, ML15113A187 Generic Environmental Impact Statement for License Renewal of Nuclear Plants:
Regarding the Davis-Besse Nuclear Power Station, Final Report Dated April 2015 8
Dated at Rockville, Maryland, this 29th day of August, 2018.
For the Nuclear Regulatory Commission.
/RA/
Bhalchandra K. Vaidya, Project Manager, Plant Licensing Branch III, Division of Operating Reactor Licensing, Office of Nuclear Reactor Regulation.
9