ML18120A321

From kanterella
Jump to navigation Jump to search
Email, NRC Staff Comments/Questions on Licensing Modernization Project Draft Rev H Guidance for Non-Light Water Reactor Licensing Basis Development
ML18120A321
Person / Time
Issue date: 04/20/2018
From: William Reckley
NRC/NRO/DSRA/ARPB
To: Afzali A, Austgen K, Redd J, Tschiltz M
Nuclear Energy Institute, Southern Co
Reckley W
References
Download: ML18120A321 (98)


Text

From: Reckley, William To: "Redd, Jason P."; aafzali@southernco.com; "AUSTGEN, Kati"; "TSCHILTZ, Michael" Cc: Segala, John; Cubbage, Amy

Subject:

NRC Staff Comments, Suggestions and Questions.

Date: Friday, April 20, 2018 12:30:00 PM Attachments: LMP RIPB Guidance Document DRAFT H - NRC COMMENTS 20 Apr 2018.docx NRC General Comments Draft Report Revision H - 20 Apr 2018.docx Attached are two files - a set of general comments, suggestions and questions and also a redline/strikeout version of Draft Report Revision H with additional comments, suggestions, and questions. There is some repetition of comments/questions within the two files. Some of the comments/suggestions would carry throughout the guidance but our comment/question may have been provided only once; and some of the comments may relate to a general theme that is identified in early sections but would also impact the later sections.

In general, the revision was a good step in the process. There are a couple key issues that we will need to resolve - and some of those will likely come after the next revision supporting our June 2018 milestone (you may notice a few that state to be finalized before Sept 2018). A concept within several of the comments is to begin identifying future guidance such that we have established pointers and thereby do not need to try to answer everything in this first guidance document.

Please distribute to your team as appropriate and review our comments, suggestions, and questions. I suggest that we have a call sometime next week to go through them to make sure there are no misunderstandings on our side in generating a comment/question or on your side before you set out to disposition our comments/questions. Please give me a call if you have any questions or issues. Thanks..

William D. Reckley Advanced Reactor Program william.reckley@nrc.gov (301) 415-7490

General Comments/Questions

1. It is stated in the draft guidance document that the PRA supporting licensing basis event selection will include sequences involving multiple modules and multiple sources of radiation. Standards for multi-module and multi-unit PRA do not yet exist and there are currently no standards development activities for such PRAs underway. Given the current development schedule for the guidance document, guidance on technical adequacy of these parts of the PRA may need to be covered in the guidance document (perhaps in an appendix) or a pointer provided to expected future guidance documents.
2. It is stated in the draft guidance document that the PRAs quantification of frequencies and consequences will address uncertainties. Methods for doing this should be documented in the guidance document or perhaps an appendix or companion document (existing or planned) referenced in the document and endorsed by the NRC. See also specific comment within RLSO version of guidance document.
3. The staff agrees that for non-LWRs, and when endorsed by the NRC, the guidance in the ASME/ANS RA-S-1.4 will provide an acceptable means to establish the scope and technical adequacy of the base PRA for a non-LWR plant. The subject guidance document (LMP) should provide the means for a designer to establish the technical adequacy of the way in which the PRA is applied in determining the frequency and consequences of licensing basis events (e.g., use of sequence families, treatment of uncertainties, etc.). That is, the guidance (this document or an expected future document that can be pointed to) should identify the additional work that a designer will need to do in order to use a PRA meeting the standard within the process described in the guidance document.
4. It is stated in the draft guidance document (e.g., Figure 41: SSC Function Safety Classification Process) that the class of safety significant SSCs will include both those found to be risk-significant from the PRA and those found to be relied upon for assuring defense-in-depth. The staff believes that this is an important principle.
5. As written, the qualitative overall guideline in Table 5-2 seems to depart from the key principle of striving for independence among the 5 levels of DiD to the extent practical. The guideline indicates that dependency between all 5 levels of DiD should be avoided but seems to allow for dependencies between up to 4 levels. Is this a correct reading or could the discussion be clarified in terms of the desired degree of independence of features being used within the layers or levels.
6. The terms prevention and mitigation appear through the guidance document, but are not defined. For example:
  • Page 6: prevention or mitigation functions
  • Page 22: prevention and mitigation of accidents
  • Page 30: prevention and mitigation of LBEs The guidance should define these terms, which have different meanings than their LWR counterparts (for LWRs, prevention means prior to core damage and mitigation means after core damage).
7. The guidance needs to specify the external hazard curves (e.g., the set of seismic hazard curves) to be used in the design certification PRA. The staff expects that these external hazard curves will be selected to envelop a large portion of the potential sites in the U.S.

(including Alaska, Hawaii, and territories such as Puerto Rico, etc.). How will the site specific external hazards be addressed while also maintaining a consistent set of LBEs for a certified design under Part 52? This is expected to be part of a broader discussion related to the handling of external events within the guidance.

8. Suggest that the term multi-module be replaced with multi-source throughout the guidance to reinforce the concept that the TI-RIPB guidance addresses all radiological sources with the plant (reactor and non-reactor). See also insights from B. John Garrick related to LMP PRA white paper. In a related matter, this may be an opportunity, at least for non-LWRs, to achieve within the guidance and glossary consistent terminology related to module, reactor, unit, plant, etc.
9. Page 16: The first cumulative risk target (the total frequency of exceeding a site boundary dose of 100 mrem from all LBEs shall not exceed 1/plant-year) could be interpreted as a definition of large release for non-LWRs. What role does the term large release have in the methodology being provided in this guidance?
10. Guidance on the identification of risk-significant SSCs and LBEs, which is scattered through the guidance document, should be consolidated and clarified:
  • Pages 27-29 discuss traditional importance measures (e.g., Fussell-Vesely - FV and risk achievement worth - RAW), which are defined on a relative basis. The non-LWR PRA standard uses these traditional importance measures to identify risk-significant basic events (FV > 0.005 or RAW > 2); however, the guidance document does not refer to the non-LWR PRA standard or use these traditional importance measures to identify risk-significant SSCs.
  • Table 3-1 on page 28 only provides computational definitions of the traditional importance measures, which may be confusing to non-PRA practitioners.
  • The footnote on page 29 provides detailed guidance on identifying risk-significant SSCs using an absolute basis. This detailed guidance is very important, and should be expanded by moving it from a footnote to the main text and providing some numerical examples.
  • Since risk-significant SSCs will be identified using an absolute basis, it is possible that no risk-significant SCCs will be identified.
  • Page 30, second bullet, first sub-bullet states that Risk significant SSCS are those that perform functions that prevent or mitigate any LBE from exceeding the F-C target [emphasis added] or make significant contributions to the cumulative risk metrics selected for evaluating the total risk from all analyzed LBEs. Under the discussion of Task 3 on page 38, it is stated that The scope of the PRA includes all the plant SSCs that are responsible for preventing or mitigating the release of radioactive material. Hence the LBEs derived from the PRA include all the relevant SSC prevention and mitigation functions. Taken together, these statements imply that any SSC modeled in the PRA is risk-significant, which apparently contradicts the discussion on pages 28-29 concerning the use of an absolute basis to identify risk-significant SSCs.
11. It is anticipated that PRA results will deviate from those obtained from the design certification PRA as operating experience accrues. Such deviations may change the LBE selection, SSC classification and/or the assessment of DID adequacy. The LMP and the staff need to arrive at a common understanding about how deviations in PRA results due to the accrual of operating experience will be considered over a plants lifetime. As mentioned in the RLSO version of the guidance, a discussion and identification of a future guidance document could address the desire to better define establishing and maintaining licensing basis information over the whole life cycle of a facility - design, construction, operation, and decommissioning. See also comments within the RLSO version of the guidance.

Modernization of Technical Requirements for Licensing of Advanced Non-Light Water Reactors Risk-Informed Performance-Based Guidance for Non-Light Water Reactor Licensing Basis Development WORKING DRAFT Draft Report Revision H Document Number SC-29980-xx Rev H March 29, 2018 NRC Comments, Suggestions and Questions Provided in this Redline/Strikeout Version of the Guidance Document April 20, 2018

NRC regulatory requirements for a reactor design refer to several different kinds of events in-cluded within the licensing basis including AOOs, DBEs, postulated accidents, design basis acci-dents (DBAs), and BDBEs. The guidance document definitions in Table 3-1 are intended to es-tablish transparent and consistent quantification of existing terms without changing their intent or expected use.

Disclaimer This report was prepared as an account of work sponsored by an agency of the United States Government. Neither the United States Government nor any agency thereof, nor any of their employees, nor Southern Company Services, Inc., nor any of its employees, nor any of its sub-contractors, nor any of its sponsors or co-funders, makes any warranty, expressed or implied, or assumes any legal liability or responsibility for the accuracy, completeness, or usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not in-fringe privately owned rights. Reference herein to any specific commercial product, process, or service by trade name, trademark, manufacturer or otherwise, does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States Government or any agency thereof. The views and opinions of authors expressed herein do not necessarily state or reflect those of the United States Government or any agency thereof.

2

Prologue This guidance document represents a framework for the efficient licensing of advanced non-light water reactors (non-LWRs). It is the result of a Licensing Modernization Project (LMP) led by Southern Company and cost-shared by the U.S. Department of Energy (DOE). The LMP pre-pared this document for establishing licensing technical requirements to facilitate risk-informed and performance-based design and licensing of advanced non-LWRs. Such a framework acknowledges enhancements in safety achievable with advanced designs and reflects current states of knowledge regarding safety and design innovation, creating an opportunity for reduced regulatory complexity with increased levels of safety.

Abstract This guideline presents a modern, technology-inclusive, risk-informed, and performance-based (TIRIPB) process for selection of Licensing Basis Events (LBEs); safety classification of struc-tures, systems, and components (SSCs) and associated risk-informed special treatments; and de-termination of defense-in-depth (DID) adequacy for non-light water reactors. This guidance pro-vides an acceptable means for addressing the aforementioned topics as part of demonstrating a specific design provides reasonable assurance of adequate radiological protection.

3

Table of Contents Disclaimer ............................................................................................................................................... 2 Prologue.................................................................................................................................................. 3 Abstract .................................................................................................................................................. 3 Table of Contents...................................................................................................................4 List of Figures .......................................................................................................................................... 7 List of Tables ........................................................................................................................................... 8 List of Abbreviations ................................................................................................................................ 9

1. Introduction .................................................................................................................................... 0 1.1. Purpose ......................................................................................................................................... 0 1.2. Background..................................................................................................................................... 0 1.3. Applicability and Scope .................................................................................................................. 1
2. LICENSING BASIS DEVELOPMENT PROCESS ...................................................................................... 2
3. SELECTION OF LICENSING BASIS EVENTS .......................................................................................... 4 3.1. Licensing Basis Event Definitions ..................................................................................................... 4 3.2. Advanced Non-LWR LBE Selection Approach ................................................................................... 6 3.2.1. TLRC Frequency-Consequence Evaluation Criteria ....................................................................... 6 3.2.2. LBE Selection Process ................................................................................................................... 9 3.2.2.1.Evolution of LBEs Through Design and Licensing Stages ............................................................. 15 3.3. Role of the PRA in LBE Selection .................................................................................................... 16 3.3.1. Use of PRA in LBE Selection Process Summary............................................................................ 20 3.3.2. Non-LWR PRA Scope for LBE Selection ....................................................................................... 20 3.3.3. PRA Scope Adequacy ................................................................................................................. 21 3.3.4. PRA Safety Functions ................................................................................................................. 21 3.3.5. Selection of Risk Metrics for PRA Model Development ............................................................... 22 3.3.5.1.Overall Plant Risk Metrics .......................................................................................................... 22 3.3.5.2.Risk Significance Evaluations ...................................................................................................... 23 3.3.6. Contributors to Risk and Risk Importance Measures .................................................................. 25
4. Safety Classification and Performance Criteria for Structures, Systems, and Components .............. 28 4.1. SSC Safety Classification Approach for Advanced Non-LWRs ......................................................... 29 4.2. Definition of Safety Significant and Risk-Significant SSCs ............................................................... 37 4.2.1. Safety Significant SSCs................................................................................................................ 37 4.2.2. Risk Significant SSCs ................................................................................................................... 37 4.3. SSCs Required for Defense-in-Depth Adequacy ............................................................................. 38 4

4.4. Development of SSC Design and Performance Requirements ........................................................ 38 4.4.1. Functional Design Criteria for Safety-Related SSCs ..................................................................... 39 4.4.2. Regulatory Design Requirements for Safety-Related SSCs .......................................................... 40 4.4.3. Evaluation of SSC Performance Against Design Requirements .................................................... 40 4.4.4. Barrier Design Requirements ..................................................................................................... 40 4.4.5. Special Treatment Requirements for SSCs .................................................................................. 41 4.4.5.1.Purpose of Special Treatment .................................................................................................... 41 4.4.5.2.Relationship Between SSC Capability, Reliability, Mitigation, and Prevention ............................. 41 4.4.5.3.Role of SSC Safety Margins......................................................................................................... 42 4.4.6. Specific Special Treatment Requirements for SR and NSRST SSCs ............................................... 42 4.4.6.1.Reliability Assurance for SSCs ..................................................................................................... 46 4.4.6.2.Capability Requirements for SSCs............................................................................................... 46

5. Evaluation of Defense-in-Depth Adequacy ..................................................................................... 47 5.1. Defense-in-Depth Philosophy ........................................................................................................ 47 5.2. Framework for Establishing DID Adequacy .................................................................................... 48 5.3. Integrated Framework for Incorporation and Evaluation of DID .................................................... 51 5.4. How Major Elements of the TI-RIPB Framework are Employed to Establish DID Adequacy ............ 58 5.5. RIPB Compensatory Action Selection and Sufficiency .................................................................... 59 5.6. Establishing the Adequacy of Plant Capability DID ......................................................................... 60 5.6.1. Guidelines for Plant Capability DID Adequacy............................................................................. 60 5.6.2. DID Guidelines for Defining Safety Significant SSCs..................................................................... 62 5.6.3. DID Attributes to Achieve Plant Capability DID Adequacy ........................................................... 62 5.7. Evaluation of LBEs Against Layers of Defense ................................................................................ 63 5.7.1. Evaluation of LBE and Plant Risk Margins ................................................................................... 66 5.7.2. Integrated Decision Panel Focus in LBE Review .......................................................................... 66 5.8. Establishing the Adequacy of Programmatic DID ........................................................................... 67 5.8.1. Guidelines for Programmatic DID Adequacy .............................................................................. 67 5.8.2. Application of Programmatic DID Guidelines .............................................................................. 68 5.9. Risk-Informed and Performance-Based Evaluation of DID Adequacy ............................................. 75 5.9.1. Purpose and Scope of Integrated Decision Panel Activities ......................................................... 75 5.9.2. Risk-Informed and Performance-Based Decision Process ........................................................... 75 5.9.3. IDP Actions to Establish DID Adequacy ....................................................................................... 77 5.9.4. IDP Considerations in the Evaluation of DID Adequacy ............................................................... 78 5.9.5. Baseline Evaluation of Defense-in-Depth.................................................................................... 79 5.9.6. Considerations in Documenting Evaluation of Plant Capability and Programmatic DID ............... 80 5.9.7. Evaluation of Changes to Defense-in-Depth ............................................................................... 81 5
6. References .................................................................................................................................... 82 6

List of Figures Figure 31. Frequency-Consequence Target ............................................................................................. 9 Figure 32. Process for Selecting and Evaluating Licensing Basis Events .................................................. 12 Figure 33. Flow Chart for Initial PRA Model Development ..................................................................... 20 Figure 41. SSC Function Safety Classification Process ............................................................................ 32 Figure 42. Definition of Risk Significant and Safety Significant SSCs ....................................................... 34 Figure 43. SSC Safety Categories ........................................................................................................... 36 Figure 51. U.S. Nuclear Regulatory Commissions Defense-in-Depth Concept [xx] ................................. 49 Figure 52. Framework for Establishing DID Adequacy ........................................................................... 50 Figure 53. Process for Evaluating LBEs Using Layers of Defense Concept Adapted from IAEA [xx].......... 51 Figure 54. Integrated Process for Incorporation and Evaluation of Defense-in-Depth............................ 53 7

List of Tables Table 31. Definitions of Licensing Basis Events ........................................................................................ 8 Table 32. Risk Importance Measures..................................................................................................... 28 Table 44. Summary of Special Treatment Requirements for SR and NSRST SSCs .................................... 44 Table 51. Role of Major Elements of TI-RIPB Framework in Establishing DID Adequacy ......................... 59 Table 52. Guidelines for Establishing the Adequacy of Overall Plant Capability Defense-in-Depth ......... 62 Table 53. Plant Capability Defense-In-Depth Attributes ........................................................................ 64 Table 54. Event Sequence Model Framework for Evaluating Plant Capabilities for Prevention and Mitigation of LBEs ............................................................................................................. 65 Table 57. Programmatic DID Attributes................................................................................................. 69 Table 58. Evaluation Considerations for Evaluating Programmatic DID Attributes ................................. 70 Table 59. Examples of Special Treatments Considered for Programmatic DID ....................................... 74 Table 510. Risk-Informed and Performance-Based Decision-Making Attributes .................................... 76 Table 511. Evaluation Summary - Qualitative Evaluation of Plant Capability DID .................................. 80 Table 512. Evaluation Summary - Qualitative Evaluation of Programmatic DID .................................... 80 8

List of Abbreviations AOO Anticipated Operational Occur- LMP Licensing Modernization Project rence ATWS anticipated transient without LRF large release frequency scram LWR light water reactor BDBE* Beyond Design Basis Event MHTGR a specific prismatic modular high-CDF core damage frequency temperature gas-cooled reactor developed by the Department of CFR Code of Federal Regulations Energy DBA Design Basis Accident NEI Nuclear Energy Institute DBE* Design Basis Event DID defense-in-depth NRC Nuclear Regulatory Commission EAB Exclusion Area Boundary EPA Environmental Protection Agency NSRST Non-Safety-Related with Special Treatment F-C Frequency-Consequence NST Non-Safety-Related with No Spe-cial Treatment FDC Functional Design Criteria O&M Operations and Maintenance FMEA failure modes and effects analysis PAG Protective Action Guide GDC General Design Criteria PBMR Pebble Bed Modular Reactor HAZOP hazard and operability study PHA process hazard analysis HPB helium pressure boundary PRA probabilistic risk assessment HTGR high temperature gas-cooled reac- PRISM Power Reactor Innovative Small tor Module HTS Heat Transport System QA Quality Assurance IAEA International Atomic Energy QHO Quantitative Health Objective Agency RCCS Reactor Cavity Cooling System IDP Integrated Decision Panel RCS Reactivity Control System IE Initiating Event RIDM risk-informed integrated decision-ISI In-service inspection making LBE* Licensing Basis Event RIM Reliability and Integrity Manage-ment LERF large early release frequency 9

RIPB risk-informed and performance- SRP Standard Review Plan based SSC structures, systems, and compo-RIPB-DM risk-informed and performance- nents based integrated decision-making TI-RIPB* technology-inclusive, risk-in-formed, and performance-based SAP Safety Assessment Principle SBO station blackout TLRC* Top Level Regulatory Criteria SCS Shutdown Cooling System SR Safety-Related

  • These terms have special meanings defined in this document.

3

1. INTRODUCTION 1.1. Purpose This document presents a technology-inclusive, risk-informed, performance-based (TIRIPB) pro-cess for selection of Licensing Basis Events (LBEs); safety classification of structures, systems, and components (SSCs) and associated risk-informed special treatments; and determination of defense-in-depth (DID) adequacy for non-light water reactors including but not limited to molten salt reactors, high temperature gas cooled reactors, and a variety of fast reactors. This guidance provides applicants a potentially acceptable method for establishing the aforementioned topics as part of demonstrating a specific design provides reasonable assurance of adequate radiological protection.

1.2. Background The Nuclear Regulatory Commission (NRC) communicated their expectations for advanced re-actors in the 2008 NRC Policy Statement on the Regulation of Advanced Reactors, [73 FR 60612; ADAMS ML082750370],

the Commission expects that advanced reactors will provide enhanced margins of safety and/or use simplified, inherent, passive, or other innovative means to accom-plish their safety and security functions.

The advanced non-light water reactor (non-LWR) developers are proposing new and innovative designs which promise to meet these Commission expectations. The NRC intends to achieve its missions through adhering to the principles of good regulationindependence, openness, effi-ciency, clarity, and reliability. As a result, the NRC Staff recognizes noted in the report Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident that the current nu-clear regulatory infrastructure, was developed for the purpose of reactor licensing in the 1960s and 1970s and supplemented as necessary to address significant events or new issues.

To modernize the regulation, in 1995 the Commission published their Final Policy Statement on the Use of Probabilistic Risk Assessment Methods in Nuclear Regulatory Activities [60 FR 42622; ADAMS ML021980535] which states in part, The use of PRA technology should be increased in all regulatory matters to the ex-tent supported by the state-of-the art in PRA methods and data and in a manner that complements the NRCs deterministic approach and supports the NRCs traditional defense-in-depth philosophy.

This document builds on these landmark policy statements by providing a foundation upon which a more fully risk-informed performance-based technical licensing environment can be de-veloped while allowing the current regulatory framework to be used by the early movers.

0

1.3. Applicability and Scope This document describes acceptable processes for selection of LBEs; safety classification of SSCs and associated risk-informed special treatments; and determination of DID adequacy appli-cable to a technology-inclusive array of advanced non-light water reactor designs. The scope of this document is focused on establishing guidance for advanced (i.e., non-LWR) designs so li-cense applicants can develop inputs that can be used to comply with key regulatory require-ments, including but not limited to the following:

  • 10 CFR 50.34(a) describes the content required in the Preliminary Safety Analysis Report (PSAR) for a Construction Permit application.
  • 10 CFR 50.34(b) describes the content required in the Final Safety Analysis Report (FSAR) for an Operating License application.
  • 10 CFR 52.47 describes the required information for a FSAR associated with a Standard Design Certification application.
  • 10 CFR 52.79 describes the required information for a FSAR associated with a Combined License application.
  • 10 CFR 52.137 describes the required information for a FSAR associated with a Standard Design Approval application
  • 10 CFR 52.157 describes the required information for a FSAR associated with a Manufac-turing License application Based on these and other regulatory requirements and their implementation guidance, an appli-cant must answer the following questions:
  • What are the plant events and accidents that are associated with the design?
  • How does the proposed design and its SSCs respond to those events?
  • What are the margins provided by the facilitys response, as it relates to radiological release limits and protecting public health and safety?
  • Is the philosophy of DID adequately reflected in the design and operation of the facility?

Detailed discussions of each of these topics, including examples, may be found in the four draft white papers submitted to the NRC in the course of development of the guidance document con-tent: Defense-in-Depth Adequacy [ML17354B174], Licensing Basis Event Selection

[ML17104A254], Probabilistic Risk Assessment [ML17158B543], and Structures, Systems, and Components Safety Classification [ML17290A463].

1

2. LICENSING BASIS DEVELOPMENT PROCESS The overall objective of this guidance document is to describe a systematic and reproducible framework for selection of LBEs, classification of SSCs, and determination of DID adequacy such that different knowledgeable parties would come to like conclusions. These assessments are key to the development of applications for licenses, certifications or approvals because they provide necessary insights into the scope and level of detail for plant SSCs and programmatic controls. This framework facilitates a systematic iterative process for completion of tasks as the Commented [NRC1]: Example of language that could be design progresses, providing immediate feedback to the designer to make better informed deci- used to reinforce that this guidance is tied to contents of ap-plications.

sions.

It would be useful to repeat this general theme in several This section includes descriptions of the following TI-RIPB processes: places to connect the guidance with the associated regula-tions

  • Systematic safety classification of SSCs and application of special treatments.
  • Guidelines for demonstration of DID adequacy.

These processes are:

  • Risk-informed to fully utilize the insights from the systematic risk assessment in combina-tion with structured prescriptive rules to address the uncertainties which are not addressed in the risk assessment. This approach will provide reasonable assurance that adequate pro-tection is provided for considered LBEs.
  • Performance-based to evaluate effectiveness relative to realizing desired outcomes. This is an alternative to a prescriptive approach specifying particular features, actions, or program-matic elements to be included in the design or process as the means for achieving desired objectives.

The processes in this guidance document can be used to:

  • Develop simplified, yet logical, coherent, and complete bases for the safety design; and, evaluation of the safety case based on the specific technology, design, and/or minimal source terms.

In summary, the outcomes from executing the processes include design specific physical features (SSCs), actions, or programmatic elements that gives the NRC adequate confidence that:

  • The selected LBEs adequately cover the range of hazards that a specific design is exposed to.

2

  • The functions that deal with these range of events are adequately reliable, diverse, and re-dundant across the layers of defense in the design.
  • The SSC that perform the desired functions are adequately reliable and available within the layers of defense they participate in.
  • The safety functions and SSCs have measurable performance criteria and their performance can be adequately monitored.
  • The philosophy of DID is apparent in the design and programmatic features included in the licensing application and outcomes of systematic evaluations of DID adequacy
  • Sufficient and integrated design decisions are made, trading off plant capabilities and pro-grammatic capabilities based on risk-informed insights with respect to providing reasona-ble assurance of adequate protection,
  • The scope and level of detail for plant SSCs and programmatic controls included in appli-cations are commensurate with safety and risk significance.

The processes covered in this guidance document are integrated and highly interdependent, start-ing with the process for the licensing basis events selection. The SSC classification process en-sures that the SSCs that are considered to be risk significant based on their contribution to the credited prevention or mitigation functions, or are considered to be important DID contributors, Commented [NRC2]: Terminology related to prevention have adequate reliability and availability. This guidance document is organized as follows for and mitigation functions likely to need further discussion, perhaps addition to glossary. No immediate changes needed the implementation process:

  • Section 3.0 provides a description of the LBE selection process.
  • Section 4.0 provides a description of SSC classification.
  • Section 5.0 provides a description of the DID adequacy determination.

3

3. SELECTION OF LICENSING BASIS EVENTS April 5-6 Workshop Discussion Topic:

What content is needed regarding regulatory foundations and precedents in the Guidance Document? Please see ML17104A254 Section 2.0 for a de-tailed discussion of these topics in the LBE white paper.

3.1. Licensing Basis Event Definitions 4

Table 31. Definitions of Licensing Basis Events Event Type NRC Current Definition or Common Usage Guidance Document Definition Conditions of normal operation that are expected to occur one or more times Conditions of plant operation, events, and event sequences expected to occur one or Anticipated during the life of the nuclear power unit and include but are not limited to loss of more times during the life of the nuclear power plant, which may include one or more re-Operational power to all recirculation pumps, tripping of the turbine generator set, isolation actor modules. Events and event sequences with frequencies of 1x10-2/plant-year and Occurrences of the main condenser, and loss of all offsite power. [SRP 15.0 and 10 CFR 50 greater are classified as AOOs. AOOs take into account the expected response of all SSCs (AOOs)

Appendix A] within the plant, regardless of safety classification.

Conditions of normal operation, including AOOs, design-basis accidents, exter- Events and event sequences that are expected to occur one or more times in the life of nal events, and natural phenomena, for which the plant must be designed to en- an entire fleet of nuclear power plants, but are less likely than an AOO. Events and event sure functions of safety-related electric equipment that ensures the integrity of sequences with frequencies of 1x10-4/plant-year to 1x10-2/plant-year are classified as Design Basis the reactor coolant pressure boundary; the capability to shut down the reactor DBEs. DBEs take into account the expected response of all SSCs within the plant regard-Events (DBEs) and maintain it in a safe shutdown condition; or the capability to prevent or mit- less of safety classification. The objective and scope of DBEs to form the design basis of igate the consequences of accidents that could result in potential offsite expo- the plant is the same as in the NRC definition. However, DBEs do not include normal op-sures. [SRP 15.0] eration and AOOs as defined in the NRC references.

Events and event sequences that are not expected to occur in the life of an entire fleet of This term is used as a technical way to discuss accident sequences that are pos-nuclear power plants. Events and event sequences with frequencies of 5x10-7/plant-year sible but were not fully considered in the design process because they were Beyond De- to 1x10-4/plant -year are classified as BDBEs. BDBEs take into account the expected re-judged to be too unlikely. (In that sense, they are considered beyond the scope sign Basis sponse of all SSCs within the plant regardless of safety classification. The objective of of design-basis accidents that a nuclear facility must be designed and built to Events BDBEs to assure the capability of the plant can prevent or mitigate unlikely events and withstand.) As the regulatory process strives to be as thorough as possible, be-(BDBEs) such capabilities are addressed within the licensing basis of the plant (note - properly yond design-basis accident sequences are analyzed to fully understand the ca-identifying and addressing BDBEs should better address ATWS, SBO, etc., than does cur-pability of a design. [NRC Glossary]

rent rules).

Postulated accidents that are used to set design criteria and limits for the de- Postulated accidents that are used to set design criteria and performance objectives for sign and sizing of safety-related systems and components. [SRP 15.0] the design and sizing of SSCs that are classified as safety-related. DBAs are derived from Design Basis DBEs based on the capabilities and reliabilities of safety-related SSCs needed to mitigate Accidents A postulated accident that a nuclear facility must be designed and built to with- and prevent accidents, respectively. DBAs are derived from the DBEs by prescriptively as-(DBA) stand without loss to the systems, structures, and components necessary to en- suming that only SSCs classified as safety-related are available to mitigate postulated ac-sure public health and safety. [NRC Glossary and NUREG-2122] cident consequences to within the 10 CFR 50.34 dose limits.

Licensing Ba- The entire collection of events considered in the design and licensing basis of the plant, sis Events Term not used formally in NRC documents. which may include one or more reactor modules. LBEs include normal operation, AOOs, (LBEs) DBEs, BDBEs, and DBAs.

5

For normal operations, including AOOs, the NRC regulations are, for the most part, generic and can be applied to an advanced non-LWR plant. The applicant is required to classify the events considered within the design basis as either AOO or Design-Basis Accident (DBA) based on a list of historically considered events and with subjective assessment of the expected frequency of occurrence. For advanced non-LWRs, the supplied lists of generic LWR events is not adequate and a subjective frequency assignment will be subject to significant uncertainty. Therefore, the following systematic and reproducible process is provided to derive the appropriate list of LBEs April 5-6 Workshop Discussion Topics:

Definition of a plant in the context of many individual reactors at a given site; definition of a fleet of plants in the context of developing the F-C Target; industry positions on multi-unit /

multi-module risks; and present regulatory requirements and position(s) addressing multi-unit /

multi-module risks.

as one acceptable process to assist with meeting the requirements.

3.2. Advanced Non-LWR LBE Selection Approach 3.2.1. TLRC Frequency-Consequence Evaluation Criteria Based on insights from the review of existing regulatory criteria, this approach uses a set of fre-quency-consequence criteria; this frequency-consequence evaluation correlation, hereafter re-ferred to as the F-C target, is shown in Figure 31. Commented [NRC3]: The calculation of consequences are dependent on assumptions of distance (e.g., EAB or X me-ters), exposure times, demographics, meteorology, and pro-tective actions. Some additional discussion may be useful on how a designer may make conservative assumptions or oth-erwise represent site characteristics.

6

Figure 31. Frequency-Consequence Target The F-C target in this figure is based on the following considerations:

  • LBE categories are based on mean event sequence frequency of occurrence per plant-year.

AOOs are off-normal events that are expected to occur in the life of the plant with frequen-cies exceeding 102 per plant-year, where a plant may be comprised of multiple reactor modules. DBEs are less frequent events that may be expected to occur in the lifetime of a fleet of plants with frequencies between 10-4 to 10-2 per plant-year. BDBEs are rare events with frequencies less than 104/plant-year but with upper bound frequencies greater than 5x10-7/plant-year. LBEs may or may not involve release of radioactive material and may involve two or more reactor modules or radionuclide sources. Commented [NRC4]: Note that demarcations and cut off remain under discussion with plans to finalize by Sept 2018

  • The regions of the graph separated by the frequency-dose evaluation line are identified as Increasing Risk and Decreasing Risk to emphasize that the purpose of criteria is to evaluate the risk significance of individual LBEs and to recognize that risk evaluations are not performed on a pass-fail basis in contrast with deterministic safety evaluation criteria.

This change is consistent with NRC risk-informed policies such as those expressed in RG 1.174 in which risk is evaluated for risk significance.insights are used along with other fac-tors within an integrated decision making process.

  • The target values shown in the figure should not be considered as a demarcation of accepta-ble and unacceptable results. The targets provide a general reference to assess events, SSCs, and programmatic controls in terms of sensitivities and available margins.

7

  • The evaluation line doses for high frequency AOOs down to a frequency of 10-1/plant-year are based on an iso-risk profile defined by the annual exposure limits of 10 CFR 20, i.e.

100 mrem/plant-year.

  • The doses for AOOs at frequencies of 10-1/plant-year down to 10-2/plant-year are cappedset at a reference value of at 1 rem corresponding with the Environmental Protection Agency (EPA) Protective Action Guide (PAG) limits and consistent with SRP Chapter 15.0 ac-ceptance criteria for lower frequency AOOs for PWRs. It is expected that many LBEs will not release any radioactive material and the identification of plant capabilities to prevent such releases is a factor considered in the formulation of SSC safety classification and per-formance requirements as discussed more fully in the section below on SSC safety classifi-cation. [xx]
  • The F-C target for DBEs range from 1 rem at 10-2/plant-year to 25 rem at 10-4/plant-year.

This aligns the lowest frequency DBEs to the limits in 10 CFR 50.34 and provides continu-ity to the lower end of the AOO criteria. A straight line on the log-log plot connects these criteria.

  • The F-C target for the BDBEs range from 25 rem at 10-4/plant-year to 750 rem at 5x107/plant year to ensure that the Quantitative Health Objective (QHO) for early health effects is not exceeded for individual BDBEs. The question of meeting the QHOs for the integrated risks over all the LBEs is addressed using separate cumulative risk targets de-scribed later in this guidance document.
  • The frequency-dose anchor points used to define the shape of the curve are indicated in the figure. The lines between the anchor points are straight lines on a log frequency vs. log dose graph.
  • In consideration of the risk aversion principle, the logarithmic slope of the curve in the DBE and BDBE regions exceeds -1.5 which corresponds to the most conservative limit-line proposed by Farmer to address risk aversion. [reference]
  • The EPA PAG dose guidance value for a specified distance (e.g. the exclusion area bound-ary) is used as the F-C target for those designs trying to establish alternative requirements of offsite emergency planning zones. Commented [NRC5]: Is this the appropriate interpreta-tion? The role of the PAG design goal needs clarified in sev-eral places within the guidance. The goal is the event selec-Across the entire spectrum of the F-C target, the risk defined as the product of the frequency and tion process, analyses, etc from LMP to support regulatory consequence should not increase as the frequency decreases. In addition, the principle of risk decisions in areas such as EP (an integrated process). While aversion is applied at frequencies below 10-1/plant-year. this may go beyond the original intent of LMP, the staff would like to make sure the logic is defined sufficiently to support the integrated approach.

While interpreting the 10 CFR 20 annual exposure limits of 100 mrem/year, it is recognized that the use of this criteria in developing the F-C target is to be applied to individual LBEs. To en-sure that the cumulative releases considering all the LBEs do not exceed this limitestablish an aggregate risk measure including AOOs and other lower consequence events, the LBE process includes an activity to insure that the integrated risks summed over all the LBEs do not exceed 100 mrem/year. This limit serves to control the risks in the high frequency low consequence end of the event spectrum noting that the NRC Safety Goal QHO cumulative risk targets are most ef-fective in controlling the low frequency, high consequence end of the spectrum. The LBE ap-proach includes performance of an integrated assessment over all the LBEs to ensure that NRC safety goal QHOs for both early and latent health effects are met.

8

3.2.2. LBE Selection Process A flow chart indicating the steps in identifying and evaluating LBEs in concert with the design evolution is shown in Figure 32. These steps are carried out by the design and design evaluation teams responsible for establishing the key elements of the safety case and preparing a license ap-plication. The process can be used to prepare an appropriate licensing document, e.g., licensing topical report, that describes the derivation of the LBEs. The LBE selection and evaluation pro-cess is implemented in LBE selection tasks described below.

Figure 32. Process for Selecting and Evaluating Licensing Basis Events 9

Task 1: Propose Initial List of LBEs During design development, it is necessary to select an initial set of LBEs which may not be complete but are necessary to develop the basic elements of the safety design approach. These events are to be selected deterministically based on all relevant and available experience includ-ing prior experience from the design and licensing of reactors. InThe initial selection of events can also be supported by analysis techniques such as engineering judgment, FMEAs, and HAZOPs. In many cases, the designer may also have an initial assessment regarding which Commented [RW6]: This and some later suggestions at-SSCs will be classified as safety-related to meet the business case for the reactor design. This tempt to offer some flexibility into the process. Do not be-lieve it is actually at odds with other parts of discussion -

classification would also be deterministically based using the same information utilized for the just a matter of timing of when a designer would introduce or initial selection of LBEs. transition to PRA from the initial system engineering ap-proach.

Task 2: Design Development and Analysis The design development is performed in phases and often includes a pre-conceptual, conceptual, preliminary, and final design phase and may include iterations within phases. The design devel-opment and analysis includes definition of the key elements of the safety case, the design ap-proach to meet the top level design requirements for energy production and investment protec-tion, and analyses to develop sufficient understanding to perform a PRA and the deterministic safety analyses. The subsequent Tasks 3 through 10 may be repeated for each design phase or iteration until the list of LBEs becomes stable and is finalized. Because the selection of deter-ministic DBAs requires the selection of safety-related SSCs, this process also yields the selection of safety-related SSCs that will be needed for the deterministic safety analysis in Task 7d.

Task 3: PRA Development/Update A PRA model is developed and then updated as appropriate for each phase of the design. Prior to first introduction of the PRA, it is necessary to develop a technically sound understanding of the potential failure modes of the reactor concept, how the reactor plant would respond to such failure modes, and how protective strategies will be incorporated into formulating the safety de-sign approach. The incorporation of safety analysis methods appropriate to early stages of de-sign, such as failure modes and effects analysis (FMEA) and process hazard analysis (PHA), pro-vide early stage evaluations that are systematic, reproducible and as complete as the current stage of design permits. As described in Section 3.3, developers are encouraged to begin developing the PRA early to support all design phases. However, developers have flexibility regarding when to introduce and develop the PRA to improve upon the initial risk management approaches or intentionally conservative analyses and related design features. If undertaken Iin the early de-sign phases, the PRA is of limited scope, coarse level of detail, and makes use of engineering Commented [NRC7]: Possible language to offer flexibility judgment much more than a completed PRA that would meet applicable PRA standards. [xx] for developers wanting to defer development of PRA to later stages of design The scope and level of detail of the PRA are then enhanced as the design matures and siting in-formation (or site envelope) is defined. For modular reactor designs, the event sequences mod-eled in the PRA would include event sequences involving a single or multiple reactor modules or radionuclide sources. This approach provides useful risk insights to the design to ensure that ac-cident sequences involving multiple reactor modules are not risk significant. The PRA process exposes sources of uncertainty encountered in the assessment of risk and provides estimates of the frequencies and doses for each LBE including a quantification of the impacts of uncertainties using quantitative uncertainty analyses and supported by sensitivity analyses.

10

Task 4: Identify/Revise List of AOOs, DBEs, and BDBEs The event sequences modeled and evaluated in the PRA are grouped into accident families each having a similar initiating event, challenge to the plant safety functions, plant response, and mechanistic source term if there is a release. Each of these families is assigned to an LBE cate-gory based on mean event sequence frequency of occurrence per plant-year. The event families Commented [NRC8]: Would it be more appropriate for from this step may confirm the initial events identified in step 1. the assignment to be based on the sum of the frequencies of the events within a family instead of the mean ?

AOOs are off-normal events that are expected to occur in the life of the plant with frequencies exceeding 102 per plant-year, where a plant may be comprised of multiple reactor modules.

DBEs are less frequent events that may be expected to occur in the lifetime of a fleet of plants with frequencies between 10-4 to 10-2 per plant-year. BDBEs are rare events with frequencies less than 104/plant-year but with upper bound frequencies greater than 5x10-7/plant-year. LBEs may or may not involve release of radioactive material and may involve two or more reactor modules or radionuclide sources. LBEs with no release are important to identify challenges to SSCs, including barriers that are responsible for preventing or mitigating a release of radioactive material. It may be feasible for some designs with limited source terms to simplify the selection and evaluation of LBEs by identifying a maximum hypothetical accident (MHA) and showing the radiological consequences are below the F-C targets or more restrictive regulatory criteria.

For example, some research and test reactors show that the consequences of an MHA are below regulatory criteria defined in 10 CFR Part 20. Such a process may simplify the analyses needed Commented [RW9]: Effort to introduce possibility that for some of the event categories making up the LBEs. some mini or micro reactors may use MHA approach- be-lieve such an approach could be accommodated within the LMP .

Event sequences with upper 95th percentile frequencies less than 5x10-7/plant-year are retained in the PRA results and used to confirm there are no cliff-edge effects. They are also taken into ac-count in the RIPB evaluation of defense-in-depth in Task 7e.

Note: Tasks 5 and 6 should be performed together in parallel rather than sequentially.

Task 5 Select/Revise Safety-Related SSCs Structures, and physical barriers, and programmatic controls that are required to protect any safety-related SSCs in performing their required safety functions in response to any design basis external event are also classified as safety-related. Safety-related SSCs are also selected for any Commented [NRC10]: Topic for discussion, while exist-required safety function associated with any high consequence BDBEs in which the reliability of ing sentence is generally true for seismic, other hazards such as flooding are not as clear.

the SSC is required to keep the event in the BDBE frequency region. High consequence BDBEs are those with consequences that exceed 10 CFR 50.34 dose criteria. The remaining SSCs that are not classified as safety-related are considered in other evaluation tasks including Tasks 7b, 7c, 7d, and 7e. Performance targets and design criteria for both safety-related and non-safety-related SSCs are developed and described more fully in the following section on SSC safety clas-sification. [xx]

Task 6: Select Deterministic DBAs and Design Basis External Events For each DBE identified in Task 4, a deterministic DBA is defined that includes the required safety function challenges represented in the DBE, but assumes that the required safety functions are performed exclusively by safety-related SSCs and all non-safety SSCs that perform these Commented [NRC11]: Is there an intent to define each of same functions are assumed to be unavailable. These DBAs are then used in Chapter 15 of the the three fundamental safety functions as a required safety function with a corresponding safety related SSC to perform that function (reactivity, heat removal, retention) ?

11

license application for supporting the conservative deterministic safety analysis. NRC Regula-tory Guide 1.203, Transient and Accident Analysis Methods, provides additional discussion of developing appropriate evaluation models for analyzing DBAs.

DBEs initiated by an external event would be used to help define requirements to protect safety-related SSCs from such events. When supported by available methods, data, design and site in-formation, and available PRA guides and standards, external events reflected in the LBEs will be derived from the PRA. In other cases not supported by the PRA, e.g. external flooding from river sites, design basis external events may be selected using traditional methods common to ex-isting reactors. Commented [NRC12]: The topic of external events needs additional discussion. For example, would assumptions for Some design basis external events such as a design basis external flood or design basis seismic external events within DBE establish design basis earth-quakes, flooding, wind loadings, etc similar to current prac-event may impact multiple modules concurrently, however a design objective would be to pre- tices. How would mixture of methodologies between exter-vent a substantial release for such events. To achieve these design objectives, there should be no nal hazard curves (e.g., for seismic) be used in combination DBEs involving a substantial release from two or more modules, and any BDBEs that involve with deterministic external hazards? In design phase, would conservative hazard curves or values be assumed and how releases from multiple reactor modules would not be high consequence BDBEs. would standardization be maintained ? Believe that this will be one of the key areas of discussion to finalize by Sept.

Task 7: Perform LBE Evaluations The deterministic and probabilistic safety evaluations that are performed for the full set of LBEs are covered in the following five tasks.

Task 7a: Evaluate LBEs Against F-C Target In this task the results of the PRA which have been organized into LBEs will be evaluated against a F-C target as shown in Figure 31. The figure does not define specific acceptance crite-ria for the analysis of LBEs but rather a tool to focus the attention of the designer and those re-viewing the design and related operational programs to the most significant events and possible means to address those events. The NRCs Advanced Reactor Policy Statement includes expec-tations that advanced reactors will provide enhanced margins of safety. The safety margin be-tween the design-specific PRA results and the F-C target provides one useful and practical demonstration of how the design fulfills the Commission expectations for enhanced safety.

These margins also are useful in the evaluation of defense-in-depth adequacy in Step 7d. The evaluations performed in this task are done for each LBE separately. The mean values of the fre-quencies are used to classify the LBEs into AOOs, DBEs, and BDBE categories. However, when the uncertainty bands defined by the 5th percentile and 95th percentile of the frequency esti- Commented [NRC13]: The guidance seems to imply that mates straddles a frequency boundary, the LBE is evaluated in both LBE categories. An LBE all uncertainties (parametric and modeling) will be captured in the quantitative uncertainy bands. Satisfactory quantifica-with mean frequency above 10-2/plant-year and 5th percentile less than 102/plant-year is evalu- tion of modeling uncertainty is difficult to achieve. The ated as an AOO and DBE. An LBE with mean frequency less than 104/plant-year with a 95th guidance might the recommendations in NUREG-1855 for percentile above 10-4/plant-year is evaluated as a BDBE and a DBE. Uncertainties about the addressing modeling uncertainty in risk-informed decision making.

mean values are used to help evaluate the results against the frequency-consequence criteria and to identify the margins against the criteria.

Unless the developer has chosen to use conservative, deterministic approaches (e.g., MHA),

DBE doses are evaluated against the F-C target based on the mean. This approach is based on the fact that the use of conservative dose evaluation is appropriate for the deterministic safety analysis in Task 7a, but is not consistent with the way in which uncertainties are addressed in risk-informed decision making in general, where mean estimates supported by a robust uncer-tainty analysis are generally used to support risk significance determinations. When evaluating 12

risk significance, comparing risks against safety goal QHOs, evaluating changes in risk against RG 1.174 change in risk criteria, the accepted practice has been to first perform a quantitative uncertainty analysis and then to use the mean values to compare against the various goals and criteria, which are set in the context of uncertainties in the risk assessments.

The primary purpose of comparing the frequencies and consequences of LBEs against the fre-quency-consequence curve is to evaluate the risk significance of individual LBEs. The objective for this approach is that uncertainties in the risk assessments are evaluated and included in dis-cussions of design features and related operational programs related to the most significant events and possible means to address those events. The evaluations in this task are based on mean frequencies and mean doses for all three LBE categories. One exception to this is that BDBEs with large uncertainties in their frequencies are evaluated as DBEs when the upper 95th percentile of the frequency exceeds 10-4 per plant-year; and AOOs with lower 5th percentile fre-quencies below 10-4/plant year are also evaluated as DBEs. The uncertainties about these means are considered as part of the RIPB DID evaluation in Task 7e.

Part of the LBE frequency-dose evaluation is to ensure that LBEs involving releases from two or more reactor modules do not make a significant contribution to risk and to ensure that measures to manage the risks of multi-module accidents are taken. Commented [NRC14]: Suggest multi-source. This may also be an opportunity to clarify use of module, unit, reactor, The final element of the LBE evaluation in this step is to identify design features that are respon- and plant. See also the comments included under general sible for keeping the LBEs within the F-C target including those design features that are respon-sible for preventing or mitigating risk-significant releases for those LBEs with this potential.

This evaluation leads to performance requirements and design criteria that are developed within the framework of the SSC classification step in the risk-informed, performance based approach.

Task 7b: Evaluate Integrated Plant Risk against QHOs and 10 CFR 20 In this task, the integrated risk of the entire plant including all the LBEs is evaluated against three cumulative risk targets including:

  • The total frequency of exceeding a site boundary dose of 100 mrem from all LBEs shall not exceed 1/plant-year. This metric is introduced to ensure that the consequences from the en-tire range of LBEs from higher frequency, lower consequences to lower frequency, higher consequences are considered. The value of 100 millirem is selected from the annual expo-sure limits in 10 CFR 20. are not exceeded. Commented [RW15]: Suggested wording, here and other places within document. Key point is to avoid saying to en-
  • The average individual risk of early fatality within 1 mile of the Exclusion Area Boundary sure Part 20 limits are not exceeded - The basis for the (EAB) from all LBEs shall not exceed 5x10-7/plant-year to ensure that the NRC Safety 100 millirem is from Part 20, but not want to confuse analy-sis with actual effluent releases addressed by Part 20 Goal QHO for early fatality risk is met.
  • The average individual risk of latent cancer fatalities within 10 miles of the EAB from all LBEs shall not exceed 2x10-6/plant-year to ensure that the NRC safety goal QHO for latent cancer fatality risk is met.

One element of this step is to identify design features that are responsible for preventing and mit-igating releases and for meeting the integrated risk criteria. This evaluation leads to performance requirements and design criteria that are developed within the framework of the SSC classifica-tion step in the guidance document.

13

In addition to the two QHOs, the 10 CFR 20 criterion is considered in recognition that the refer-enced regulatory requirement is for the combined exposures from all releases even though it has been used in developing the F-C target used for evaluating the risks from individual LBEs. Hav-ing these cumulative risk targets as part of the process provides a safeguard to ensure that the F-C target is conservatively defined for use as a tool for focusing attention on matters important to managing the risks from non-LWRs.

Task 7c: Evaluate Risk Significance of LBEs and SSCs Including Barriers In this task, the details of the definition and quantification of each of the LBEs in Task 7a and the integrated risk evaluations of Task 7b are used to define both the absolute and relative risk sig-nificance of individual LBEs and SSCs which include radionuclide barriers. These evaluations include the use of PRA risk importance metrics, where applicable, and the examination of the ef-fectiveness of each of the layers of defense in retaining radionuclides. LBEs are classified as risk significant if the LBE site boundary dose exceeds a small fraction of background radiation exposure and the frequency of the dose is within 1% of the F-C target. SSCs are classified as Commented [NRC16]: What criteria (margin) would be risk significant if the SSC function is required to keep any LBEs inside the F-C target, or if the used if the design is using the PAG reference value as the F-C target (given the target parallels the frequency axis) total frequency of LBEs with the SSC failed is within 1% of any of the three cumulative risk tar-gets identified in Step 7b. This information is used to provide risk insights, to identify safety sig-nificant SSCs, and to support the RIPB evaluation of defense-in-depth in Task 7e.

Task 7d: Perform Deterministic Safety Analyses Against 10 CFR 50.34 This task corresponds to the traditional deterministic safety analysis that is found in Chapter 15 of the license application. It is performed using conservative assumptions. The uncertainty anal-yses in the mechanistic source terms and radiological doses that are part of the PRA are available to inform the conservative assumptions used in this analysis and to avoid the arbitrary stacking of conservative assumptions.

Task 7e: Risk-Informed, Performance-Based Evaluation of Defense-in-Depth In this task, the definition and evaluation of LBEs will be used to support a RIPB evaluation of defense-in-depth. This task involves the identification of key sources of uncertainty, and evalua-tion against defense-in-depth criteria. Outcomes of this task include possible changes to the de-sign, as may be needed, to enhance the plant capabilities for defense-in-depth, formulation of conservative assumptions for the deterministic safety analysis, and input to defining and enhanc-ing programmatic elements of defense-in-depth.

It is noted that this DID evaluation does not change the selection of LBEs directly. This evalua-tion could lead to compensatory actions that change the design capability or programmatic con-trols on the design, which in turn would lead to changes in the PRA and thereby affecting the se-lection or evaluation of LBEs.

This may be a convenient point for designers to assess plant features for effective compliance with regulatory requirements such as 10 CFR 50.155, Mitigation of Beyond-Design Basis Events, and 10 CFR 73, Physical Protection of Plants and Materials. The results from the evaluation will also support related licensing matters such as defining appropriate constraints in terms of siting (10 CFR 100), offsite emergency planning, and development of plant procedures and guidelines.

14

Task 8: Decide on Completion of Design/LBE Development The purpose of this task is to make a decision as to whether additional design development is needed, either to proceed to the next logical stage of design or to incorporate feedback from the LBE evaluation that design, operational, or programmatic improvements should be considered.

Such design improvements could be motivated by a desire to increase margins against the fre-quency-consequence criteria, reduce uncertainties in the LBE frequencies or consequences, man-age the risks of multi-unit accidents, limit the need for restrictions on siting or emergency plan-ning, or enhance the performance against defense-in-depth criteria. The DID adequacy evalua-tion may result in additional need to iterate on the adequacy of design, operational, and program-matic programs, which in turn could influence the PRA and need for cycling through all the LBE evaluation steps.

Task 9: Proceed to Next Stage of Design Development The decision to proceed to the next stage of design is reflected in this task.

Task 10: Finalize List of LBEs and Safety-Related SSCs Establishing the final list of LBEs and safety-related SSCs signifies the completion of the LBE selection process and the selection of the safety-related SSCs. The next step in implementing the TI-RIPB approach is to complete the SSC safety classification process and to formulate perfor-mance requirements and design criteria for SSCs that are necessary to control the LBE frequen-cies and doses and other performance standards associated with the protection of fission product barriers. Important information from Task 7a through 7e is used for this purpose.

3.2.2.1.Evolution of LBEs Through Design and Licensing Stages The LBE selection flow chart in Figure 32 reflects an iterative process involving design develop-ment, PRA development, selection of LBEs, and evaluation of LBEs. The process flow chart can be viewed as beginning in the pre-conceptual or conceptual design phase when many design details are unavailable, the PRA effort has not begun, and the safety design approach is just be-ing formulated. To begin the process outlined in Figure 32, an initial set of LBEs is proposed based on engineering judgment in Task 1 of the process. This may generate an initial target se-lection of safety-related SSCs.

During the conceptual design phase, different design concepts are explored and alternatives are considered to arrive at a feasible set of alternatives for the plant design. The effort to develop a PRA should begin during this phase. Traditional design and analysis techniques are applied dur-ing conceptual design, including (1) use of traditional design bases of engineering analysis and judgment, (2) application of research and development programs, (3) use of past design and op-erational experience, (4) performance of design trade studies, and (5) decisions on how or whether to conform to established applicable LWR-based reactor design criteria and whether other principle criteria are needed.

Creation of the initial event list of LBEs includes expert evaluation and review of the relevant experience gained from previous reactor designs and associated PRAs, when available. It starts by answering the first question in the risk triplet series: What can go wrong?; How likely is it?; and What are the consequences? Care must be exercised to ensure that information taken from other reactor technologies is interpreted correctly for the reactor technology in question.

15

The body of relevant reactor design and PRA data that is available to draw upon may vary for different reactor technologies. Once design alternatives and trade studies are developed, the safety design approach can be defined. A review of the major systems can take place and tech-niques such as a failure modes and effects analysis (FMEAs) and process hazards analyses such as hazard and operability studies (HAZOPs) can be applied to identify initial failure scenarios and to support the initial PRA tasks to define initiating events.

Preliminary design activities need to balance regulatory and design requirements, cost, schedule, and other user requirements to optimize the design, cost, and capabilities that satisfy the objec-tives for the reactor facility.

As the design matures, the scope and level of detail of the PRA is expanded and is used to help support design decisions along the way. An early simplified PRA can be very helpful to support design trade studies that may be performed to better define the safety design approach. Questions that arise in the efforts to build a PRA model may be helpful to the design team especially in the mutual understanding of what kind of challenges will need to be addressed. Because the design is being changed more frequently at this point and better characterized as the design phases evolve, the PRA results and their inputs to the LBE selection process will also be subject to change. As a result, refinements to the list of LBEs are expected. The simplifying perception that a design has stages that contain bright lines is a frequent description at the system level but is not correct at the plant level. Different parts of the design mature at different times. Systems often go through design stages like this, however, at any moment, there may be systems in many design phases simultaneously. Consequently, the PRA development is a continuum as well, ma-turing with the systems design. PRA updates with system development then provide a more fre-quent, integrated plant performance check that is otherwise missing in the conventional design process and will also provide risk insights to help the design decisions. When the design, con-struction, and PRA are developed in a manner that is sufficient to meet PRA requirements re-flected in applicable PRA standards and regulatory guides, the LBEs will be finalized and in-cluded in the license application.

3.3. Role of the PRA in LBE Selection Applicants are required by NRC regulations to develop a PRA (10 CFR 50.71(h)) and to provide a description in their application (e.g., 10 CFR 52.79). The development and use of the PRA during the design process can be more efficient than completing the design and then developing the PRA. The primary motivation to utilize inputs from a PRA in the selection of LBEs is that it Commented [RW17]: Suggest citing requirement for PRA is the only method available that has the capability to identify the events that are specific and - the staff would envision this requirement being maintained for future reactors, and so adds context to recommended use unique to a new reactor design. Traditional methods for selecting LBEs, such as those reflected throughout the process versus using only as a confirmation in the General Design Criteria and Chapter 15 of the Standard Review Plan, do not refer to a sys- tool tematic method for identifying design specific events. The generic lists of events provided in the SRP guidance as examples for transients and postulated accidents to consider are specific to LWRs. Traditional systems analysis techniques that can be used to evaluate a design and were used to define the LBEs for currently licensed reactors, including FMEAs, HAZOPs, single fail-ure analyses, etc., have been incorporated into PRA methodology for selecting initiating events and developing event sequence models. PRA is also a mature technology that is supported by industry consensus standards and regulatory guides. [xx] There are no similar consensus stand-ards for deterministic selection of LBEs for new reactor designs. Although much of the available 16

experience in PRA has been with operating LWR plants, there is a rich history of PRA as applied to advanced non-LWR designs including HTGRs, MAGNOX and AGRs, and liquid metal-cooled fast reactors. A trial use PRA standard for advanced non-LWRs was issued by the ASME/ANS Joint Committee on Nuclear Risk Management in 2013 and, by 2018, a revised ver-sion for consideration as an ANSI standard is scheduled to be available for ballot. The trial use PRA standard has been subjected to a number of PRA pilot studies on the Power Reactor Innova-tive Small Module (PRISM), HTR-PM project in China, and several other non-LWR designs.

Lessons from these pilot studies are being incorporated into the revised non-LWR PRA standard.

Prior to first introduction of the PRA, it is necessary to develop a technically sound understand-ing of the potential failure modes of the reactor concept, how the reactor plant would respond to such failure modes, and how protective strategies will be incorporated into formulating the safety design approach. The incorporation of safety analysis methods appropriate to early stages of de-sign, such as FMEA and PHA, provide industry-standardized practices to ensure that such early stage evaluations are systematic, reproducible and as complete as the current stage of design per-mits. Commented [NRC18]: Based upon hearing the question frequently (including from ACRS), it may be useful to add The interfaces between traditional systems engineering processes and the initial development of some discussion of how approach addresses technologies/de-signs/SSCs with limited operating histories (including poten-the PRA model are shown in Figure 33. It is important to note that the systems engineering in- tially higher uncertainties, and performance based ap-puts on the left hand side of the diagram are fundamental to developing the design. However, proaches moving into operations that confirm assumptions with the concurrent development of the PRA model, the PRA is developed in parallel with the and build in logic (e.g., increasing or decreasing surveillance intervals) as operating experience gained design and thereby is available to provide important risk insights to the design development and supporting systems analyses. Decisions to defer the introduction of the PRA to later stages of design lead to reduced opportunities for cost-effective risk management.

17

Figure 33. Flow Chart for Initial PRA Model Development The PRA will be used to evaluate the safety characteristics of the design and to provide a struc-tured framework from which the initial set of LBEs will be risk-informed. The evaluation of the risks of the LBEs against the frequency-consequence correlation help make the LBE selection process both risk-informed and performance-based. This evaluation framework is critical to the development of a revised licensing framework. It highlights the issues that deserve the greatest attention in a safety-focused process. Subsequently the PRA will provide important input to the formulation of performance targets for the capability and reliability of the SSCs to prevent and 18

mitigate accidents and thereby contribute to the performance- based aspects of the design and li-censing development process. In addition, engineering judgment and utilization of relevant ex-perience will continue to be used to ensure that LBE selection and classification is complete.

The PRA will systematically enumerate event sequences and assesses the frequency and conse-quence of each event sequence. Event sequences will include internal events, internal plant haz-ards, and external events. The modeled event sequences will include the contributions from common cause failures and thereby will not arbitrarily exclude sequences that exceed the single failure criterion.

Each event sequence family reflected in the LBE definitions is defined as a collection of event sequences that similarly challenge plant safety functions. This means that the initiating events within the family have a similar impact on the plant such that the event sequence development following the plant response will be the same for each sequence within the family. If the event sequence involves a release, each sequence in the family will have the same mechanistic source term and offsite radiological consequences. Many of the LBEs do not involve a release, and un-derstanding the plant capabilities to prevent release is an extremely important insight back to the design. Event sequence family grouping facilitates selection of LBEs from many individual events into a manageable number.

The PRAs quantification of both frequencies and consequences will address uncertainties, espe-cially those associated with the potential occurrence of rare events. The quantification of fre-quencies and consequences of event sequences, and the associated quantification of uncertain-ties, provides an objective means of comparing the likelihood and consequence of different sce-narios against the F-C correlation. The scope of the PRA, when completed will be as compre-hensive and sufficiently complete as a full-scope, all modes, Level 3 PRA covering a full set of internal and external events when the design is completed and site characteristics well defined.

Designers may propose to address all or parts of the process by assessing fission product barriers and showing that radioactive materials are with a high degree of confidence retained within the facility. Such an approach would still require that some of the information provided by a PRA, including the identification challenges to the barriers and identification and evaluation of de-pendencies among the barriers, including challenges that may impact multiple reactor modules would be considered in the formulation of licensing basis events and the determination of safety significant SSCs.

The PRA will include event sequences involving two or more reactor modules, if applicable, as well as two or more sources of radioactive material. This will enable the identification and eval-uation of risk management strategies to ensure that sequences involving multiple modules and sources are not risk significant.

The LBE selection process is not risk-based, but rather risk-informed as there are strong deter-ministic inputs to the process. First, the PRA development is anchored to traditional determinis-tic system engineering analyses that involve numerous applications of engineering judgment, identified in the left side of Figure 33. These include FMEAs, process hazards assessment, ap-plication of relevant experience from design and licensing of other reactors, and deterministic models of the plant response to events and accidents. Second, the deterministic DBAs are se-lected based on prescriptive rules and analyzed using conservative assumptions. Finally, the 19

LBE selection includes a review to ensure that the LBE selection and the results of the LBE eval-uations meet a set of criteria to ensure the adequacy of defense-in-depth. Commented [RW19]: 1.It is then stated in Section 5.6.1 that: However, there do not exist any well-de-These evaluations often lead to changes to the plant design and programmatic controls that are fined regulatory acceptance criteria for deciding the sufficiency of the defense-in-depth (DiD) for nuclear reflected in changes to the PRA and, hence, changes to the selection of LBEs and SSC safety power plant licensing or operation. To support the classification. In addition to these elements, peer reviews and regulatory reviews of the PRA design and licensing of advanced non-LWRs within will provide an opportunity to challenge the completeness and treatment of uncertainties in the this framework, a set of DiD adequacy guidelines has been provided. These guidelines are then provided PRA to ensure that the deterministic DBAs and the conservative assumptions that are used in in Table 5.2 of the draft guidance document. In light Chapter 15 are sufficient to meet the applicable regulatory requirements. of the statement in Section 5.6.1, the statement in Section 3.3 seems misleading. If the reader searches for criteria in Chapter 5 he will not find 3.3.1. Use of PRA in LBE Selection Process Summary them.

In the course of developing a reactor design-specific PRA model, a comprehensive set of initiat-ing events and event sequence families are systematically identified, building on the engineering and systems analyses that are performed to support the design development. These events and event sequences are considered in the selection of the LBEs, and the quantitative estimates of the event sequence frequencies and consequences provide a basis for evaluating their risk signifi-cance. Deterministic evaluations of prescriptively derived DBAs benefit from the identification and evaluation of LBE uncertainties that result from the PRA process.

SSC safety classification requires an assessment of the risk significance of SSCs and the LBEs that describe the safety functions of the SSCs in the prevention and mitigation of accidents. In-formation from the PRA is used as input to the selection of reliability targets and performance requirements for SSCs that set the stage for the selection of special treatment requirements.

The PRA process, in the course of addressing the three questions of the risk triplet: What can go wrong?; How likely is it?; and What are the consequences?; exposes many sources of un-certainty in the definition of event sequences, the estimation of their frequencies, and the quanti-fication of the consequences. This information on uncertainties is an important input to the selec-tion of protective strategies and in the evaluation of defense-in-depth adequacy. Additional roles of the PRA in the DID evaluation include information on the LBE risk margins against the F-C Target and the Cumulative Risk Targets, and evaluation of quantitative DID evaluation criteria.

The above uses of the PRA complement the use of deterministic methods traditionally employed in the development of the design and licensing bases as part of risk-informed, rather than risk-based framework 3.3.2. Non-LWR PRA Scope for LBE Selection Prior to the first use of the PRA, it is necessary to develop an understanding of the potential fail-ure modes of the reactor concept, how the reactor plant would respond to such failure modes, and how protective strategies are incorporated into formulating the safety design approach. The in-corporation of safety analysis methods appropriate to early stages of design, such as failure modes and effects analysis (FMEA), HAZOPs, and other process hazard analysis (PHA) meth-ods, provide industry-standardized and established practices to ensure that early stage evalua-tions are systematic, reproducible and as complete as the current stage of design permits.

20

Since the non-LWRs are expected to make greater use of inherent and passive capabilities to achieve safety, the PRA model used for applications described in this document should address the full spectrum of internal events and external hazards that pose challenges to the capabilities of the plant.

The PRA in use at the time of license application development should address the PRA require-ments described in ASME/ANS RA-S-1.4: Probabilistic Risk Assessment Standard for Ad-vanced Non-LWR Nuclear Power Plants. The size, complexity, and potential risk of a given de-sign should influence the level of detail required to support this process. Reactor designs with small radionuclide inventories, few SSC, and inherently safe responses to upsets may employ simple, yet fit for purpose, PRAs.

Quantification of the frequencies and radiological consequences of each of the significant event sequences modelled is an important outcome of the PRA. This quantification includes mean point estimates and an appropriate quantification of uncertainty in the form of uncertainty proba-bility distributions. These distributions should account for quantifiable sources of parameter and model uncertainty in the accident frequencies, mechanistic source terms, and offsite radiological consequences. The analysis performed in support of the RIPB applications covered in this guideline should include an appropriate set of sensitivity analyses to provide adequate assurance that major contributors to risk and performance uncertainties are identified and addressed.

Plants comprised of multiple reactor modules require consideration of event sequences that im-pact reactor modules independently as well as those that impact two or more reactor modules concurrently.

3.3.3. PRA Scope Adequacy For non-LWRs, the guidance in the ASME/ANS RA-S-1.4 provides an acceptable means to es-tablish the scope and technical adequacy of the PRA The scope and level of detail of the PRA models aligns with the state of definition of the design, the safety design approach, and systems design concepts. As the design matures and more de-sign information becomes available for different types of risk evaluations, the scope of the PRA can broadened to address other plant conditions and progressively confirm the plant capability to meet safety objectives.

3.3.4. PRA Safety Functions The term PRA safety function, is any function by any SSC modelled in the PRA that is respon-sible for preventing or mitigating a release of radioactive material from any radioactive material source within the plant. Some of these safety functions should be further classified as required safety functions if they are necessary in the DBAs to meet the acceptance criteria for the Chap-ter 15 safety analysis, or supportive safety functions if they are not necessary to meet the Chapter 15 safety analysis criteria but still play a role in accident prevention and mitigation and 21

part of the plant capabilities for DID. Following the development of the initial PRA, while se-lecting the LBEs that will be analyzed as DBAs, those SSCs that perform required safety func-tions are classified as safety-related and special treatment requirements will be developed to ensure they have the necessary and sufficient capability and reliability to assure acceptance crite-ria are satisfied.

Safety functions are defined starting with generic fundamental reactor functions of controlling heat generation, controlling heat removal, and retaining radionuclides. These are refined as nec-essary into reactor technology-specific safety functions that reflect the reactor concept and unique characteristics of the reactors. This provides the foundation for reactor technology spe-cific SSCs selected to perform each function.

3.3.5. Selection of Risk Metrics for PRA Model Development 3.3.5.1.Overall Plant Risk Metrics The PRA model can be structured differently than the model for an LWR PRA, given that plant damage states may not involve an equivalent metric to the core damage state in a LWR PRA model. Frequencies of event sequences can be individually and grouped into accident families having the same or similar plant response and offsite radiological consequences may be defined in terms of release categories, i.e., plant response, mechanistic source term, and offsite radionu-clide consequences. Consequences are quantified in terms of offsite early and latent health ef-fects and/or site boundary doses.

Some acceptable TI risk metrics include: Commented [NRC20]: How would risk metrics change for designs choosing to use the PAG reference level as the F-C target

  • Integrated risks of a given consequence metric, e.g., site boundary dose, number of early or latent health effects, etc. calculated by summing the product of the frequency and conse- In general, if not using the PAG as a criteria, would protec-quence of each LBE over the full set of LBEs. tive actions (including evacuations) be assumed or credited in evaluating risks and comparisons to metrics such as latent
  • Integrated risks of individual fatalities as needed for comparison to the Cumulative Risk Tar- health effects?

gets for evaluating LBEs including the QHOs.

  • Cumulative frequency of exceeding consequences such as large release, early or latent health effects, or a specific site boundary dose.

In addition to the above TI metrics, reactor specific risk metrics defined by the user may be used to define the parameters of the PRA model. Requirements for the definition and use of these re-actor specific metrics are given in the advanced non-LWR PRA standard.

The selection of PRA risk metrics should address accident sequences that may involve two more reactor modules or radionuclide sources. This is addressed using the following approaches:

  • The IEs and event sequences in the PRA delineate events involving each reactor and radionu-clide source separately as well as events involving two or more reactors or sources.
  • Dependencies associated with shared systems and structures are explicitly modeled in an in-tegrated fashion to support an integrated risk assessment of the entire plant where the plant may be comprised of two or more reactor modules and non-core radionuclide sources.

22

  • Treatment of human actions considers the unique performance shaping factors associated with multi-reactor and multi-source event sequences.
  • Treatment of common cause failures delineates those that may impact multiple reactor mod-ules.
  • The frequency basis of the event sequence quantification is events per (multi-module/multi-source) plant-year.

A summary of the technical issues that need to be addressed for PRAs involving multiple reactor modules or radionuclide sources is found in Reference X.

3.3.5.2.Risk Significance Evaluations There are two types of risk significance evaluations that are performed for the selection and eval-uation of LBEs. The first type is an evaluation of the frequencies and consequence of each LBE, expressed in the form of mean values and uncertainty (at the 5th and 95th percentiles), against the Frequency-Consequence (F-C) Target shown in Figure XError! Reference source not found..

In this evaluation, the frequencies and consequences of individual LBEs are compared against an F-C Target derived from top level regulatory requirements and NRC safety goal policy. The ob-jective is to keep the LBE frequencies and consequences within the F-C targets. An evaluation of the margins between the LBE risks and the F-C target is one aspect of the RIPB evaluation of plant capability and defense-in-depth adequacy. The development of the F-C target is explained more fully in X.

23

Figure 31. Use of the F-C Target to Define Risk Significant LBEs Each LBE in this evaluation is defined as a family of event sequences modelled in the PRA that groups the individual modeled PRA event sequences according to the similarity of the following elements of the event sequence:

  • Plant operating state.
  • Plant response to the IE and any independent or consequential failures represented in the event sequence including the nature of the challenge to the barriers and SSCs supporting each safety function.
  • Event sequence end state.
  • Number or combination of reactor modules and radionuclide sources affected by the se-quence.
  • Mechanistic source term for sequences involving a release. Commented [NRC21]: May be appropriate to include somewhere a bit more (possibly even in glossary) a discus-sion of mechanistic source term The event sequence frequencies are expressed in terms of events/plant-year where a plant may be comprised of two or more reactor modules and sources of radioactive material.

24

In addition to evaluation of each individual LBE, an integrated risk evaluation of the entire plant is performed against the below criteria. For this evaluation, the integrated risk of the entire plant is evaluated against three Cumulative Risk Targets:

  • The total frequency of exceeding a site boundary dose of 100 mrem shall not exceed 1/plant-year to ensure that the annual exposure limits in 10 CFR 20 are not exceeded. Commented [NRC22]: See previously suggested wording
  • The average individual risk of early fatality within 1 mile of the EAB shall not exceed 5x10 7

/plant-year to ensure that the NRC Safety Goal QHO for early fatality risk is met.

  • The average individual risk of latent cancer fatalities within 10 miles of the EAB shall not exceed 2x10-6/plant-year to ensure that the NRC safety goal QHO for latent cancer fatality risk is met.

Risk significant LBEs are those with frequencies and consequences within 1% of the F-C target with site boundary doses exceeding 2.5 mrem. To consider the effects of uncertainties, the upper 95%tile estimates of both frequency and dose should be used for this purpose. The use of the 1%

metric is consistent with the approach to defining risk significant accident sequences in the PRA standards. The 2.5 mrem cut-off is selected as this is approximately 10% of the dose that an av-erage person at the site boundary would receive in 30 days due to background radiation.

To provide input to the selection of emergency planning zones, the frequency of exceeding the Environmental Protection Agency protective action guideline dose limits would be included in the calculated risk metrics. Commented [NRC23]: Is this a different proposal from using PAG as F-C target ?

3.3.6. Contributors to Risk and Risk Importance Measures To derive useful risk insights from the results of a PRA, it is necessary to understand the princi-pal contributors to each evaluated risk metric. This can be achieved by rank ordering the PRA event sequences and sequence minimal cut-sets to identify their relative and absolute contribu-tion to each risk metric and to calculate the risk importance measures that evaluate contributions to basic events that may be common to two or more sequences or cut-sets. For any of the inte-grated risk metrics, such as the QHOs, the relative risk significance of any LBE can be calculated as a percentage of the LBE risk (product of the LBE frequency and LBE consequence) to the ag-gregated risk of all the LBEs.

In order to evaluate the risk contributions from basic events that may appear in two or more event sequences or cut-sets, risk importance measures can be used. The most commonly used risk importance measures in PRA are listed in Table X-XError! Reference source not found.,

which is developed from Reference XError! Reference source not found.. In this table, the term R represents the total risk, R(base), which is the risk with each basic event probability set to its base value, and the term xi represents the probability of a basic event i, which may be, for ex-ample, the event that a specific valve fails to perform its function.

25

Table 32. Risk Importance Measures The associated Table 3-1 risk importance measures definitions can be used with any of the tech-nology-inclusive risk metrics selected for the PRA using this process. These include:

  • Frequency of a specific LBE
  • Total risk (sum of the product of frequency and site boundary dose) of all the PRA modeled sequences, or individual risk of fatality in the plant vicinity
  • Frequency of exceeding a specified site boundary dose
  • Individual risk of prompt or latent fatality for comparison to NRC safety goal QHOs.

The historical approach to evaluating risk importance produced only the relative importance of each basic event because the formulas are normalized against the total calculated risk for the plant, R(base). For advanced non-LWR plants, the frequencies of accidents involving a release of radioactive material may be very small and those accidents with releases may involve very small source terms compared with releases from an LWR core damage accident. Hence, it is ap-propriate to evaluate risk significance not only on a relative but also on an absolute basis.

For this purpose, the risks can be compared against the risk goals rather than the baseline risks.

One example of the use of absolute risk metrics is the approach to defining risk significance LBEs as illustrated in XError! Reference source not found.. Another means is establishing the risk significance of SSCs. For this metric, SSCs are risk significant if any of the following crite-ria are met:

  • A prevention or mitigation function of the SSC is necessary to meet the design objective of keeping all LBEs within the F-C target. This is determined by assuming failure of the SSC in performing a prevention or mitigation function and checking on how the resulting LBE risks compare with the F-C target. The LBE is considered within the F-C target 26

when a point defined by the upper 95%-tile uncertainty of the LBE frequency and dose estimates are within the F-C target.

  • The SSC makes a significant contribution to one of the cumulative risk metrics used for evaluating the risk significance of LBEs. A significant contribution to each cumulative risk metric limit is satisfied when total frequency of all LBEs with failure of the SSC ex-ceeds 1% of the cumulative risk metric limit 1. The cumulative risk metrics and limits in-clude:

o The total frequency of exceeding of a site boundary dose of 100 mrem < 1/plant-year (10 CFR 20) o The average individual risk of early fatality within 1 mile of the Exclusion Area Boundary (EAB) < 5x10 -7/ plant-year (QHO) o The average individual risk of latent cancer fatalities within 10 miles of the EAB shall not exceed 2x10-6/plant-year (QHO)

April 5-6 Workshop Discussion Topics:

PRA Technical adequacy. Discuss how much the ASME/ANS non-PWR standard can be relied upon and what technical / licensing aspects need specific discussion in the Guidance Document for understanding and durable agreement between NRC and industry.

1 This evaluation of SSC risk significance requires the aggregation of all the LBEs in which any basic event in the PRA model associated with the SSC is failed. There are normally different basic events for different SSC failure modes (e.g. failure to start, failure to run, etc.), unavailability for test or maintenance, or a common cause basic event involving that SSC. When the total frequency of LBEs with all the basic events associated with the SSC exceeds the 1% criterion, the SSC is regarded as risk significant according to these criteria.

27

4. SAFETY CLASSIFICATION AND PERFORMANCE CRITERIA FOR STRUCTURES, SYSTEMS, AND COMPONENTS The purpose of this section is to define the approach to SSC safety classification and to identify potential technical concerns related to SSC safety classification and the derivation of require-ments necessary to support SSC performance of safety functions in the prevention and mitigation of LBEs. Such requirements include those to provide the necessary capabilities to perform their mitigation functions and those to meet their reliability requirements to prevent LBEs with more severe consequences. Use is made of relevant aspects of risk-informed SSC classification ap-proaches that have been developed for existing and advanced LWRs and small modular reactors, including those defined for implementation of 10 CFR 50.69. [xx]

Safety classification categories are defined as follows:

  • Safety-Related (SR):
  • SSCs selected by the designer from the SSCs that are available to perform the re-quired safety functions to mitigate the consequences of DBEs to within the LBE FC target, and to mitigate DBAs that only rely on the SR SSCs to meet the dose limits of 10 CFR 50.34 using conservative assumptions
  • SSCs selected by the designer and relied on to perform required safety functions to prevent the frequency of BDBE with consequences greater than the 10 CFR 50.34 dose limits from increasing into the DBE region and beyond the F-C target
  • Non-Safety-Related with Special Treatment (NSRST):
  • Non-safety-related SSCs relied on to perform risk significant functions. Risk signifi-cant SSCs are those that perform functions that prevent or mitigate any LBE from ex-ceeding the F-C target, or make significant contributions to the cumulative risk met-rics selected for evaluating the total risk from all analyzed LBEs.
  • Non-safety-related SSCs relied on to perform functions requiring special treatment for DID adequacy
  • Non-Safety-Related with No Special Treatment (NST):
  • All other SSCs (with no special treatment required) Commented [NRC24]: Is it clear that those SSCs whose failure could adversely affect a safety significant SSC would be classified appropriately and/or special treatment would be Safety significant SSCs include all those SSCs classified as SR or NSRST. None of the NST identified related to such failures?

SSCs are classified as safety significant.

The RIPB SSC performance and special treatment requirements identified in this document for SR and NSRST SSCs are appropriate. The purpose of these requirements is to provide reasona-ble confidence in the SSC capabilities and reliabilities in performing functions identified in the LBEs consistent with the F-C target and the regulatory dose limits for DBAs.

28

4.1. SSC Safety Classification Approach for Advanced Non-LWRs The SSC safety classification 2 process is described in Figure 41. This process is designed to be used with the process for selecting and evaluating LBEs. The information needed to support the SSC safety classification is available when Step 10 of the LBE selection and evaluation process is completed in each phase of the design process.

2 The SSC safety classification process classifies SSCs on the basis of the SSC safety functions reflected in the LBEs. Although the SSCs are classified, the resulting performance and special treatment requirements are for the specific functions identified in the LBEs.

29

Figure 41. SSC Function Safety Classification Process 30

31 The SSC safety classification process is implemented in the six tasks that are described below.

This process is described as an SSC function classification process rather than a SSC classifica-tion process because only those SSC functions that prevent or mitigate accidents represented in the LBEs are of concern. A given SSC may perform other functions that are not relevant to LBE prevention or mitigation or functions with a different safety classification.

Task 1: Identify SSC Functions in the Prevention and Mitigation of LBEs The purpose of this task is to review each of the LBEs, including those in the AOO, DBE, and BDBE regions to determine the function of each SSC in the prevention and mitigation of the LBE. Each LBE is comprised of an initiating event, a sequence of conditioning events, and end state. The initiating events may be associated with an internal event such as an SSC failure or human error, an internal plant hazard such as a fire or flood, or an external event such as seismic event or external flood.

For those internal events caused by an equipment failure, the initiating event frequency is related to the unreliability of the SSC, i.e., SSCs with higher reliability serve to prevent the initiating event. Thus, higher levels of reliability result in a lower frequency of initiating events. For SSCs that successfully mitigate the consequences of the initiating event, their capabilities and safety margins to respond to the initiating event are the focus of the safety classification process and resulting special treatment. For those SSCs that fail to respond along the LBE, their reliabil-ities, which serve to prevent the LBE by reducing its frequency, are the focus of the reliability requirements derived from classification and treatment process. The output of this task is the identification of the SSC prevention and mitigation functions for all the LBEs.

Task 2: Identify and evaluate SSC capabilities and programs to support defense-in-depth The purpose of this task is to provide a feedback loop from the evaluation of defense-in-depth (DID) adequacy, which is the topic of a separate LMP white paper Error! Reference source not found.. This evaluation includes an examination of the plant LBEs, identification of the SSCs responsible for the prevention and mitigation of accidents, and a set of criteria to evaluate the ad-equacy of DID. A result of this evaluation is the identification of SSC functions, and the associ-ated SSC reliabilities and capabilities that are deemed to be necessary for DID adequacy. Such SSCs and their associated functions are regarded as safety significant and this information is used to inform the SSC safety classification in subsequent steps.

Task 3: Determine the Required and Safety-Significant Functions The purpose of this task is to define the safety functions that are required to meet the 10 CFR 50.34 dose requirements for all the DBEs and the high consequence BDBEs as well as other safety functions regarded as safety significant. Safety significant SSCs include those that per-form risk significant functions and those that perform functions that are necessary to meet de-fense-in-depth criteria. The scope of the PRA includes all the plant SSCs that are responsible for preventing or mitigating the release of radioactive material. Hence the LBEs derived from the PRA include all the relevant SSC prevention and mitigation functions.

As explained previously, there are some safety functions classified as required safety functions that must be fulfilled to meet the F-C target for the DBEs using realistic assumptions and dose requirements for the DBAs using conservative assumptions. In addition to these required safety functions, there are additional functions that are classified as safety significant when certain risk 32

significance and defense-in-depth criteria are met as explained below. In most cases, there are several combinations of SSCs that can perform these required safety functions. How individual SSC safety functions are classified relative to these function categories is resolved in Tasks 4 and

5. The concepts used to classify SSC safety functions as risk significant and safety significant are illustrated in Figure 42 Figure 42. Definition of Risk Significant and Safety Significant SSCs Tasks 4 and 5: Evaluate and Classify SSC Functions The purpose of Tasks 4 and 5 is to classify the SSC functions modeled in the PRA into one of three safety categories: SR, NSRST, and NST.

Tasks 4A and 5A In Task 4A, each of the DBEs and any high consequence BDBEs (i.e., those with doses above 10 CFR 50.34 limits) are examined to determine which SSCs are available to perform the re-quired safety functions. The designer then selects one specific combination of available SSCs to perform each required safety function that covers all the DBEs and high consequence BDBEs.

These specific SSCs are classified as SR in Task 5A and are the only ones credited in the Chap-ter 15 safety analysis of the DBAs. All the remaining SSCs are processed further in Steps 4B and 4C.

Tasks 4B and 5B Because each SR classified SSC identified in Task 4A is necessary to keep one or more LBEs inside the F-C target, all SR SSCs are regarded in the framework as risk significant. However, it 33

is also possible that some non-SR SSCs will meet the criteria for risk significance. In this task, each non-safety-related SSC is evaluated for its risk significance. A risk significant SSC func-tion is one that is necessary to keep one or more LBEs within the F-C target or is significant in relation to one of the LBE cumulative evaluation risk metric limits. Examples of the former cat-egory are SSCs needed to keep the consequences below the AOO limits in the F-C target, and DBEs where the reliability of the SSCs must be controlled to prevent an increase of frequency into the AOO region with consequences greater than the F-C target. If the SSC is classified as risk significant and is not an SR SSC, it is classified as NSRST in Task 5B. SSC functions that are neither safety-related nor risk significant are evaluated further in Task 4C.

Tasks 4C and 5C In this task, a determination is made as to whether any of the remaining non-safety-related and non-risk significant SSC functions should be classified as requiring special treatment in order to meet criteria for defense-in-depth adequacy. Those that meet these criteria are classified as NSRST in Task 5B and those remaining as NST in Task 5C.

At the end of this task, all SSC functions reflected in the LBEs will be placed in one of the three SSC function safety classes illustrated in Figure 4-3 Figure 43.

34

Figure 43. SSC Safety Categories Note that all SSC functions classified as either SR or NSRST are regarded as safety signifi-cant. All non-safety significant SSC functions are classified in NST.

This guidance documents approach makes use of the concept of SSC safety significance that is associated with the 10 CFR 50.69 approach and also addresses the possibility that an SSC that is not safety-related nor risk significant may be classified as safety significant based on defense-in-depth considerations. This approach to assigning risk significance uses the concept of evaluating the impact of the SSC function on the ability to meet the F-C target, as in the previous ap-proaches, but also includes criteria based on risk significance metrics for the cumulative risk im-pacts of SSC functions across all the LBEs. Hence this approach is in better alignment with the risk-informed safety classification process that is being implemented for 10 CFR 50.69.

Task 6: SSC Reliability and Capability Requirements Commented [NRC25]: Will the reliability requirements be incorporated into reliability assurance programs, the mainte-For each of the SSC functions that have been classified in Task 4, the purpose of this task is to nance rule, or other programs This may be an area warrant-define the requirements for reliabilities and capabilities for SSCs modeled in the PRA. For SSCs ing additional guidance - but goal is to ensure that the ap-classified as SR or NSRST, which together represent the safety significant SSCs, these require- proach for non-LWRs improves upon how process addresses life cycle of plant - from design, construction, and into oper-ments are used to develop regulatory design and special treatment requirements in Task 7. For ations.

those SSCs classified as NST, the reliability and capability requirements are part of the non-reg-ulatory user design requirements.

35

For SSCs classified as SR, Functional Design Criteria (FDC) and lower level design criteria are defined to capture design-specific criteria that may supplement or may not be captured by the ap-plicable GDC or Advanced Reactor Design Criteria. These criteria are used to frame specific de-sign requirements as well as special treatment requirements for SR SSCs. NSRST SSCs are not directly associated with FDC but are subject to special treatment as determined by the integrated decision making process for evaluation of defense-in-depth. The FDC, design requirements, and special treatment requirements define key aspects of the descriptions of SSCs that will be in-cluded in safety analysis reports. Guidance on the development of FDC, design requirements, Commented [NRC26]: Another example of connecting and special treatment requirements is found elsewhere in this guidance document. guidance to requirements of content of application. Also a good example of a part of guidance that can be developed to define the logic for content and level of detail in FSARs.

Task 7: Determine SSC Specific Design Criteria and Special Treatment Requirements The purpose of this task is to establish the specific design requirements for SSCs which include FDC for SR classified SSCs, regulatory design and special treatment requirements for each of the safety significant SSCs classified as SR or NSRST, and user design requirements for NST classified SSCs. The specific SSC requirements are tied to the SSC functions reflected in the LBEs and are determined utilizing the same integrated decision making process used for evaluat-ing the adequacy of defense-in-depth.

The term special treatment is used in a manner consistent with NRC regulations and Nuclear Energy Institute (NEI) guidelines in the implementation of 10 CFR 50.69. In Regulatory Guide 1.201, [xx] the following definition of special treatment is provided:

special treatment refers to those requirements that provide increased assurance beyond normal industrial practices that structures, systems, and components (SSCs) perform their design-basis functions.

In RIEP-NEI-16, [xx] a distinction is made between special treatment as applied to safety-related SSCs and alternative special treatment afforded by 10 CFR 50.69. Alternative treatment require-ments are differentiated from special treatment requirements in the use of reasonable confi-dence versus reasonable assurance. More details on the development of specific SSC design and performance requirements are provided in Section 3 of this guidance document.

April 5-6 Workshop Discussion Topic:

What content is needed in the Guidance Document regarding comparison /

contrast with 10 CFR 50.69 and related processes? Please see ML17290A463 for a detailed discussion of this topic in the SSC white paper.

36

4.2. Definition of Safety Significant and Risk-Significant SSCs 4.2.1. Safety Significant SSCs The meaning of safety significant SSC in this framework is the same as that used in NRC regula-tions. The NRC glossary provides the following definition:

When used to qualify an object, such as a system, structure, component, or accident sequence, this term identifies that object as having an impact on safety, whether de-termined through risk analysis or other means, that exceeds a predetermined signifi-cance criterion.

4.2.2. Risk Significant SSCs In this framework, an SSC is classified as risk significant if any of the following risk significance criteria are met for any SSC function included within the LBEs:

  • A prevention or mitigation function of the SSC is necessary to meet the design objective of keeping all LBEs within the F-C target. An LBE is considered within the FC target when a point defined by the upper 95th percentile uncertainty on both the LBE frequency and dose are within the F-C target. Note that all the SR SSCs meet this criterion and hence all SR SSCs are regarded as risk significant. In addition, some non-SR SSCs perform functions that may be required to keep AOOs or high consequence DBEs within the F-C target; these non-SR SSCs are also regarded as risk significant and classified as NSRST.
  • The SSC makes a significant contribution to one of the cumulative risk metrics used for evaluating the risk significance of LBEs. A significant contribution to each cumulative risk metric limit is satisfied when total frequency of all LBEs with failure of the SSC exceeds 1% of the cumulative risk metric limit. This SSC risk significance criterion may be satis-fied by an SSC whether or not it performs functions necessary to keep one or more LBEs within the F-C target. The cumulative risk metrics and limits include:
  • The total frequency of exceeding of a site boundary dose of 100 mrem shall not ex-ceed 1/plant-year to ensure that the annual exposure limits in 10 CFR 20 are not ex-ceeded. An SSC makes a significant contribution to this cumulative risk metric if the total frequency of exceeding a site boundary dose of 100 mrem associated with LBEs with the SSC failed is greater than 10-2/plant-year.
  • The average individual risk of early fatality within 1 mile of the EAB shall not exceed 5x10-7/plant-year to ensure that the NRC Safety Goal QHO for early fatality risk is met. An SSC makes a significant contribution to this cumulative metric if the indi-vidual risk of early fatalities associated with the LBEs with the SSC failed is greater than 5x10-9/plant-year.
  • The average individual risk of latent cancer fatalities within 10 miles of the EAB shall not exceed 2x10-6/plant-year to ensure that the NRC Safety Goal QHO for latent can-cer fatality risk is met. An SSC makes a significant contribution to this cumulative 37

risk metric if the individual risk of latent cancer fatalities associated with the LBEs with the SSC failed is greater than 2x10-8/plant-year.

The cumulative risk limit criteria in this SSC classification approach are provided to address the situation where an SSC may contribute to two or more LBEs which collectively may be risk sig-nificant even though the individual LBEs may not be significant. All LBEs within the scope of the supporting PRA should be included when evaluating these cumulative risk limits. In such cases, the reliability and availability of such SSCs may need to be controlled to manage the total integrated risks over all the LBEs.

4.3. SSCs Required for Defense-in-Depth Adequacy In this framework, an integrated decision-making process is used to evaluate the design and risk-informed decision to ensure adequacy of design and DID. Any SSCs that do not meet the risk-significance criteria will be classified as safety significant only if the integrated decision making process determines that some form of special treatment is necessary to establish the adequacy of DID. This makes sense because the DID evaluation, which will incorporate traditional engineer-ing judgments made via an integrated decision panel, will consider additional sources of uncer-tainty that are fully resolved in the PRA, including measures to enforce assumptions made in the PRA, and measures necessary to address considerations beyond the PRA. If a non-risk signifi-cant SSC is classified as safety significant, it simply means that some type of special treatment is needed to address the adequacy of DID.

As a result, the universe of safety significant SSCs in this framework includes both risk signifi-cant SSCs as well as SSCs that perform functions where some form of special treatment is deter-mined to be needed to meet DID adequacy criteria. All safety significant SSCs are classified as SR or NSRST. All NST SSCs are not safety significant. This provides a nexus between the SSC safety classification approach and the special treatment requirements for SR and NSRST SSCs as discussed in Section 4.

April 5-6 Workshop Discussion Topic:

What content is needed in the Guidance Document regarding conformity of SSC Classification approach with RIPB principles? Please see ML17290A463 for a detailed discussion of this topic in the SSC Classification white paper.

4.4. Development of SSC Design and Performance Requirements This section describes the approach for defining the design requirements for each of the three SSC safety categories: SR; NSRST; and NST. These design requirements begin with the identi-fication of the SSC functions that are required to meet user requirements for energy production, investment protection, worker and public safety, and licensing. SSC functions associated with the prevention and mitigation of release of radioactive material from the plant are modeled in the PRA and represented in the LBEs. The first priority in establishing the design requirements for all the SSCs associated with the prevention and mitigation of release of radioactive material is to 38

ensure that the capability and reliability of each SSC is sufficient for all the SSC functions repre-sented in the LBEs, including the AOOs, DBEs, BDBEs, and DBAs. A related priority is to pro-vide reasonable confidence that the reliability and capability of the SSCs are achieved and main-tained throughout the lifetime of the plant.

Those SSCs that are classified as safety-related are expected to meet applicable regulatory re-quirements as well as reactor-specific functional design criteria (FDC).

4.4.1. Functional Design Criteria for Safety-Related SSCs As noted in the previous section, SSCs classified as SR perform one or more safety functions that are required to perform either of the following:

1.Mitigate DBEs within the F-C target and DBAs within 10 CFR 50.34 dose limits 2.Prevent any high consequence BDBEs (those with doses exceeding 10 CFR 50.34 dose limits) from exceeding 1x10-4/plant-year in frequency and thereby migrate into the DBE region of the F-C evaluation These required safety functions are used within this framework to define a set of reactor-specific FDCs from which SSC regulatory design requirements may be derived. Because the FDCs are derived from a specific reactor technology and design, supported by a design specific PRA, and related to a set of design specific required safety functions, each non-LWR design would need to develop its own FDCs. A key purpose of the FDCs is to form a bridge between the safety classi-fication of SSCs and the derivation of SSC performance and special treatment requirements.

The process for identifying the required safety functions for a given reactor starts with a review of the safety functions modeled in the PRA for the prevention and mitigation of LBEs and identi-fying which of those safety functions, if not fulfilled, would likely increase the consequences of any of the DBEs beyond the F-C target. This normally involves the performance of sensitivity analyses 3 in which the performance of each safety function that mitigates the consequences of each DBE is removed and consequences re-evaluated. From the required safety functions, a top-down logical development is used to define the functional requirements that must be fulfilled for the reactor design to meet each required safety function. The FDCs may be viewed as criteria that are defined in the context of the specific reactor design features that are necessary and suffi-cient to meet the required safety function.

3 This is just one example of the use of sensitivity analyses in this framework. Sensitivity analyses are also performed in the de-velopment of the PRA and in the risk-informed and performance-based evaluation of defense-in-depth as part of the ap-proach to addressing uncertainties in the estimation of LBE frequencies and consequences. Requirements for performing these analyses are covered in ASME/ANS-RA-S-1.4. Guidance for performing uncertainty analysis in the PRA is available in NUREG-1855. Insights from the uncertainty analysis are also an important input to the risk-informed and performance-based evaluation of defense-in-depth.

39

4.4.2. Regulatory Design Requirements for Safety-Related SSCs For each of the FDCs, each designer will need to identify a set of regulatory design requirements that will be assigned to the safety-related systems assigned to perform the required safety func-tions.

The design requirements are performance-based and keyed to required safety functions, derived from the LBEs, and used to systematically select the safety-related SSCs.

4.4.3. Evaluation of SSC Performance Against Design Requirements Although the safety-related SSCs are derived from an evaluation of the required safety functions to mitigate the DBEs and DBAs, the safety-related and non-safety-related SSCs are evaluated against the full set of LBEs including the AOOs, and BDBEs, as well as normal plant operation, at the plant level to ensure that the F-C target is met. This leads to design requirements for both the safety-related and non-safety-related SSCs across the full set of LBEs, including the DBAs.

4.4.4. Barrier Design Requirements SSCs that provide functions that support the retention of radioactive material within barriers have associated regulatory design requirements that are derived from the evaluation of the LBE against the F-C target and the FDCs. These functions include barrier functions in which the SSC serves as a physical or functional barrier to the transport of radionuclides and indirect func-tions in which performance of an SSC function serves to protect one or more other SSCs that may be classified as barriers. However, a more complete perspective on the role of barriers and the SSCs that protect each barrier needs to consider the barrier response to each of the LBEs de-rived from the PRA. The LBEs delineate the barrier failure modes, the challenges to barrier in-tegrity, and the interactions between SSCs that influence the effectiveness of each barrier, and the extent of barrier independence. The evaluation of mechanistic source terms that help deter-mine the offsite doses provides another performance metric for evaluating the effectiveness of each barrier.

When viewed across all the LBEs, each barrier plays a specific role in the retention of radionu-clides; however, those roles are different on different LBEs. A full picture of the synergistic roles that each of the SSCs that comprise these barriers needs to consider the ways in which the SSCs mutually support the fundamental function of radionuclide retention.

It is noted that some non-LWRs employ functional barriers that are different than the physical barriers frequently employed in the past. As noted previously, in this framework, the term bar-rier is used to denote any plant feature that is responsible to either full or partial reduction of the quantity of radionuclide material that may be released during an accident. It includes features such as physical barriers or any feature that is responsible for mitigating the quantity of material including time delays that permit radionuclide decay.

In summary, the definition of requirements for barriers cannot be fully developed simply by ex-amining the capability of discrete physical barriers to retain radionuclides. The fact that barriers are not independent for any reactor concept precludes such a simplistic approach. A systematic 40

development of SSC design requirements needs to consider a full spectrum of barrier challenges, barrier interactions, and barrier dependencies. A full examination of the barrier challenges, inter-actions and dependencies requires the performance of a technically sound PRA. Hence it is criti-cal that the approach to formulating requirements for barriers and other SSCs be linked to a sys-tematic identification and evaluation of LBEs supported by a PRA.

4.4.5. Special Treatment Requirements for SSCs 4.4.5.1.Purpose of Special Treatment The purpose of special treatment is reflected in the Regulatory Guide 1.201 [xx] definition of this term:

special treatment refers to those requirements that provide increased assurance beyond normal industrial practices that structures, systems, and components (SSCs) perform their design-basis functions.

In the context of this framework, this definition of special treatment is realized by those measures taken to provide reasonable confidence that SSCs will perform their functions re-flected in the LBEs. The applicable functions include those that are necessary to prevent initiat-ing events and accidents and other functions needed to mitigate the impacts of initiating events on the performance of plant safety functions. Assurance is first accomplished by achieving and monitoring the levels of reliability and availability that are assessed in the PRA and that are de-termined to be necessary to meet the LBE risk evaluation criteria. These measures are focused on the prevention functions of the SSCs. Assurance is further accomplished by achieving and monitoring the capabilities of the SSCs in the performance of their mitigation functions with ade-quate margins to address uncertainties. The relationships between SSC reliability and capability in the performance of functions to that are needed to prevent and mitigate accidents are defined further in the next section.

4.4.5.2.Relationship Between SSC Capability, Reliability, Mitigation, and Prevention The safety classification of SSCs is made in the context of how the SSCs perform specific safety functions for each LBE in which they appear. The reliability of the SSC serves to prevent the oc-currence of the LBE by lowering its frequency of occurrence. If the SSC function is successful along the event sequence, the SSC helps to mitigate the consequences of the LBE.

The safety classification process and the corresponding special treatments serve to control the frequencies and consequences of the LBEs within the F-C target and to ensure that the cumula-tive risk targets are not exceeded. The LBE frequencies are a function of the frequencies of initi-ating events from internal events, internal and external hazards, and the reliabilities and capabili-ties of the SSCs (including the operator) to prevent and mitigate LBE. The SSC capabilities in-clude the ability to prevent an initiating event from progressing to an accident, to mitigate the consequences of an accident, or both. In some cases, the initiating events are failures of SSCs themselves, in which case the reliability of the SSC in question serves to limit the initiating event frequency. In other cases, the initiating events represent challenges to the SSC in question, in which case the reliability of the SSC to perform a safety function in response to the initiating 41

event needs to be considered. Finally, there are other cases in which the challenge to the SSC in question is defined by the combination of an initiating event and combinations of successes and failures of other SSCs in response to the initiating event. All of these cases are included in the PRA and represent the set of challenges presented to a specific SSC.

4.4.5.3.Role of SSC Safety Margins SSC safety margins play an important role in the development of SSC design requirements for reliability and performance capability. Acceptance limits on SSC performance are set with safety margins between the level of performance that is deemed acceptable in the safety analysis and the level of performance that would lead to damage or adverse consequences for all the LBEs in which the SSC performs a prevention or mitigation function. The magnitude of the safety margins in performance are set considering the uncertainties in performance, the nature of the associated LBEs, and criteria for adequate defense-in-depth. The ability to achieve the ac-ceptance criteria in turn reflects the design margins that are part of the SSC capability to mitigate the challenges reflected in the LBEs.

A second example of the use of margins is in the selection of reliability performance targets.

The reliability targets are set to ensure that the underlying LBE frequencies and consequences meet the LBE evaluation criteria with sufficient margins. These safety margins are also evalu-ated in the defense-in-depth evaluation.

A third example of safety margins is the evaluation of margins between the frequencies and con-sequences of the LBEs and the F-C Target and the margins between the cumulative risk metrics and the cumulative risk targets used for LBE evaluation. These risk margins are evaluated as part of the RIPB evaluation of defense-in-depth.

4.4.6. Specific Special Treatment Requirements for SR and NSRST SSCs A summary of special treatment requirements for SSCs is provided in Table 41.

42

Table 41. Summary of Special Treatment Requirements for SR and NSRST SSCs Applicability1 Special Treatment Category SR NSRST NST Available Guidance4 SSC SSC SSC Requirements Associated with SSC Safety Classification Document basis for SSC categorization by Essentially the same as 10 CFR 50.69(c), [xx] Guidance in RG 1.201, Integrated Decision Making Panel5 NEI0004 for all SSCs Essentially the same as 10 CFR 50.69(d), Guidance in RG 1.201, [xx]

Document evaluation of adequacy of spe- NEI0004 for RISC-1 SSCs cial treatment to support SSC categoriza-tion Essentially the same as 10 CFR 50.69(d), Guidance in RG 1.201, NEI0004 for RISC-2 SSCs 43

Applicability1 Special Treatment Category SR NSRST NST Available Guidance4 SSC SSC SSC Change control process to monitor perfor-Essentially the same as 10 CFR 50.69(e), Guidance in RG 1.201,[xx] NEI0004 mance and manage SSC categorization for RISC-1 and RISC-2 SSCs changes Basic Requirements for all Safety Significant SSCs Reliability Assurance Program including re- Essentially same as Reliability Assurance Program in SRP 17.4 for safety sig-liability and availability targets for SSCs in nificant SSCs, Guidance in SRP Chapter 19.1, ASME Section XI Reliability performance of LBE safety functions and Integrity Management Programs Design Requirements for SSC capability to Guidance in this guidance document, MHTGR PSID mitigate challenges reflected in LBEs Maintenance Program that assures targets for SSC availability and effectiveness of Essentially same as 10 CFR 50.65 Maintenance Rule; link to MR consistent maintenance to meet SSC reliability tar- with 10 CFR 50.69 for RISC-1 (SR) and RISC-2 (NSRST) SSCs gets Essentially same as 10 CFR 50.69(f), Guidance in RG 1.201, NEI-00-04 for Licensee Event Reports RISC-1 and RISC-2 SSCs Additional Special Treatment Requirements Functional design criteria Guidance in this guidance document, INL/EXT-14-31179 2

Technical Specifications 10 CFR 50.36, SRP, MHTGR PSID 3 3 Essentially the same as for existing reactors for safety-related SSCs 10 CFR Seismic design basis 100 Appendix A Essentially the same as for existing reactors for safety-related SSCs, Seismic qualification testing 10 CFR 100 Appendix A, RG 1.100 Protection against design basis external Essentially the same as for existing reactors for safety-related SSCs, Guid-events ance in 10 CFR 100 Appendix A, SRP 3 44

Applicability1 Special Treatment Category SR NSRST NST Available Guidance4 SSC SSC SSC Essentially the same as for existing reactors for safety-related SSCs, Equipment qualification testing 10 CFR 50.49 Materials surveillance testing ASME Section XI Reliability and Integrity Management Programs [xx]

Pre-service and In-service inspection via 2 (note that the RIM program is not yet an endorsed standard, and so either Reliability Integrity Management an acknowledgment or refer to other available guidance (e.g., existing guidance for LWRs) 2 In-service testing needs to be integrated with Reliability Assurance Pro-Pre-service and in-service testing gram 1

The applicability of any category of special treatment to any SSC must be evaluated on a case-by-case basis and in the context of the SSC functions in the prevention and mitigation of applicable LBEs. This is determined via an integrated decision making process.

2 The need for this special treatment for any NSRST is determined on a case-by-case basis and when applicable is applied to the specific functions to prevent and mitigate the applicable LBEs. This is determined via an integrated decision making process.

3 SR classified SSCs are required to perform their safety functions following a Safe Shutdown Earthquake; NSRST SSCs are required to perform their safety functions following an Operational Basis Earthquake; NSRST and NST SSCs required to meet Seismic II/I requirements (required not to inter-fere with the performance of SR SSC safety functions following an Safe Shutdown Earthquake.

4 The references in this column are mostly applicable to LWRs and hence they are offered as providing useful guidance. In this column, the term essentially is used to mean that non-LWR guidance under this framework will need to be developed because the referenced documents were de-veloped specifically for LWRs in which risk insights have been back-fit.

5 Integrated decision panel is discussed more fully in this guidance document on defense-in-depth and is similar to that described in NEI-00-04 45

The applicability of special treatment to the SSC safety categories that is identified in Table 41 is provided for general guidance only, and it is not prescriptive. The applicability of any special treatment to any SSC must be evaluated on a case-by-case basis and in the context of the SSC functions in the prevention and mitigation of applicable LBEs.

The purpose of any special treatment requirement is to provide adequate assurance that the SSC will perform its functions in the prevention and mitigation of LBEs. Each requirement is in-tended to assure that the SSC has adequate reliability and capability to perform these functions.

4.4.6.1.Reliability Assurance for SSCs All safety significant SSCs, including those in the SR and NSRST categories, should be included in a Reliability Assurance Program (RAP) similar to that described in SRP 17.4. [xx] The relia-bility and availability targets established in RAP are used to focus the selection of special treat-ments that are necessary and sufficient to achieve these targets and to assure they will be main-tained for the life of the plant.

4.4.6.2.Capability Requirements for SSCs All safety significant SSCs, including those in the SR and NSRST categories, should have the capability to perform the safety functions to mitigate the challenges reflected in the LBEs re-sponsible for the safety classification. SR SSCs must be capable of mitigating the DBAs within the 10 CFR 50.34 dose limits. These SR SSCs shall include appropriate functional design crite-ria for such functions. Additional special treatment requirements for SR SSCs should be devel-oped to provide assurance that the capability to perform their designated safety functions is maintained during the operating lifetime of the plant. The guiding principle is that the require-ments should be performance-based and yield high confidence that the SSC functions will be performed during the identified LBEs. Specific capability requirements for other non-LWR con-cepts and design will necessarily be reactor technology and design specific.

46

5. EVALUATION OF DEFENSE-IN-DEPTH ADEQUACY The philosophy of defense-in-depth, multiple independent but complimentary methods for pro-tecting the public from potential harm from nuclear reactor operation, has been applied since the dawn of the industry. While the term has been defined primarily as a general philosophy by the NRC, a formal definition that permits an objective assessment of DID adequacy has not been re-alized. This framework provides an approach that permits the establishment of DID in design, construction, maintenance, and operation of nuclear facilities. This is accomplished by the reac-tor designer and operator with the objective of assuring that adequate DID has been achieved.

Achievement of DID occurs when all stakeholders (designers, license applicants, regulators, etc.)

make clear and consistent decisions regarding DID adequacy as an integral part of the overall de-sign process.

Establishing DID adequacy involves incorporating DID design features, operating and emer-gency procedures and other programmatic elements. DID adequacy is evaluated by using a se-ries of RIPB decisions regarding design, plant risk assessment, selection and evaluation of li-censing basis events, safety classification of SSCs, specification of performance requirements for SSCs, and programs to ensure these performance requirements are maintained throughout the life of the plant.

The RIPB evaluation of DID adequacy is complete when the recurring evaluation of plant capa-bility and programmatic capability associated with design and PRA update cycles no longer identifies risk-significant vulnerabilities where potential compensatory actions can make a practi-cal, significant improvement to the LBE risk profiles or risk significant reductions in the level of uncertainty in characterizing the LBE risk.

5.1. Defense-in-Depth Philosophy According to the NRC glossary,[xx] defense-in-depth is:

...an approach to designing and operating nuclear facilities that prevents and miti-gates accidents that release radiation or hazardous materials. The key is creating multiple independent and redundant layers of defense to compensate for potential hu-man and mechanical failures so that no single layer, no matter how robust, is exclu-sively relied upon. Defense in depth includes the use of access controls, physical bar-riers, redundant and diverse key safety functions, and emergency response measures.

Figure 51 illustrates the concept of layers of defense embodied in this philosophy taken from NUREG/KM-0009.[xx] This framework is consistent with the levels of defense concept ad-vanced by the International Atomic Energy Agency (IAEA) in Reference [xx].

47

Figure 51. U.S. Nuclear Regulatory Commissions Defense-in-Depth Concept [xx]

This framework for establishing DID adequacy embraces this layers of defense concept and uses these layers to identify and evaluate DID attributes for establishing DID adequacy.

5.2. Framework for Establishing DID Adequacy This framework for evaluation of DID adequacy is outlined in Figure 52. The elements of the framework are described below.

48

Figure 52. Framework for Establishing DID Adequacy Plant Capability Defense-in-Depth This element is used by the designer to select functions, SSCs and their bounding design capabil-ities to assure safety adequacy. Additionally, excess capability, reflected in the design margins of individual SSC and the use of redundancy and diversity, is important to the analysis of beyond design basis conditions that could arise. This reserve capacity to perform in severe events is con-sistent with the DID philosophy for conservative design capabilities that enable successful out-comes for unforeseen or unexpected events should they occur. Plant capability DID is divided into the following categories:

  • Plant Functional Capability DIDThis capability is introduced through systems and fea-tures designed to prevent occurrence of undesired LBE or mitigate the consequences of such events.
  • Plant Physical Capability DIDThis capability is introduced through SSC robustness and physical barriers to limit the consequences of a hazard.

These capabilities when combined create Layers of Defense response to plant challenges.

Programmatic Defense-in-Depth Programmatic DID is used to address uncertainties when evaluating plant capability DID as well as where programmatic protective strategies are defined. It is used to incorporate special treat-ment 4 during design, manufacturing, constructing, operating, maintaining, testing, and inspecting 4

According to Regulatory Guide 1.201,[xx] special treatment refers to those requirements that provide increased assurance beyond normal industrial practices that structures, systems, and components (SSCs) perform their design-basis functions.

49

of the plant and the associated processes to ensure there is reasonable assurance that the pre-dicted performance can be achieved throughout the lifetime of the plant. The use of perfor-mance-based measures, where practical, to monitor plant parameters and equipment performance that have a direct connection to risk management and equipment and human reliability are con-sidered essential.

Risk-Informed Evaluation of Defense-in-Depth This element provides a systematic and comprehensive process for examining the DID adequacy achieved by the combination of plant capability and programmatic elements. This evaluation is performed by a risk-informed integrated decision-making (RIDM) process to assess and establish whether DID is sufficient and to enable consideration of different alternatives for achieving com-mensurate safety levels at reduced burdens. The outcome of the RIDM process also establishes a DID baseline for managing risk throughout the plant lifecycle.

This process for using the layers of defense for performing the RIPB evaluation of plant capabili-ties and programs, which has been adapted from the IAEA levels of defense approach is shown in Figure 53. This process is used to evaluate each LBE and to identify the DID attributes that have been incorporated into the design to prevent and mitigate accident sequences and to ensure that they reflect adequate SSC reliability and capability. Those LBEs with the highest levels of risk significance are given greater attention in the evaluation process.

Figure 53. Process for Evaluating LBEs Using Layers of Defense Concept Adapted from IAEA [xx]

50

As explained more fully in the sections on PRA development, LBE selection and evaluation, and SSC safety classification, the PRA is used together with traditional deterministic safety ap-proaches to affect a risk-informed process, as shown in the center of Figure 52. The PRA is not employed simply to calculate numerical risk metrics, but rather to develop risk insights into the design and to identify sources of uncertainty in the PRA models and supporting data that com-plement the deterministic elements of the framework. The DID evaluation includes the identifi-cation of compensating protective measures to address the risk significant sources of uncertainty so identified.

5.3. Integrated Framework for Incorporation and Evaluation of DID DID is to be considered and incorporated into all phases of defining the design requirements, de-veloping the design, evaluating the design from both deterministic and probabilistic perspectives, and defining the programs to ensure adequate public protection. The reactor designer is respon-sible for ensuring that DID is achieved through the incorporation of DID features and programs in the design phases and in turn, conducting the evaluation that arrives at the decision of whether adequate DID has been achieved. The reactor designer implements these responsibilities through the formation of an Integrated Decision Panel (IDP) which guides the overall design effort (in-cluding development of plant capability and programmatic DID features), conducts the DID ade-quacy evaluation of that resulting design, and documents the DID baseline.

The incorporation of DID in each component of this framework is illustrated in Figure 54, and the key elements of each box in this figure are summarized below. The color coding in this fig-ure identifies elements of the process that are probabilistic, deterministic, and risk-informed meaning having both probabilistic and deterministic aspects. It is emphasized that the imple-mentation of the framework is not a series of discrete tasks but rather an iterative process. The sequence of boxes reflects more an information logic than a step-by-step procedure. The execu-tion of the DID elements is accomplished in the context of an integrated decision-making process throughout the plant design and operation lifecycle.

51

Figure 54. Integrated Process for Incorporation and Evaluation of Defense-in-Depth 52

Under this framework, an IDP will be responsible for evaluating the adequacy of DID; similar to the processes used by currently operating plants to guide risk-informed changes to the licensing basis, such as risk-informed safety classification under 10 CFR 50.69. The NEI has developed procedures and guidelines for the makeup and responsibilities of such panels. [xx] For advanced non-LWRs that are currently in various stages of design development, the IDP is comprised of a team that is responsible for implementing the integrated process steps for evaluating DID shown in Figure 54. This team includes those responsible for the design, operations, and maintenance program development and for performing the necessary deterministic and probabilistic evalua-tions identified in this figure.

Box 1. Establish Initial Design Capabilities The process begins in Box 1 with available design information. Top level requirements are for-mulated with input from all stakeholders, including user requirements for such things as energy production, capital costs, operating and maintenance costs, safety, availability, investment pro-tection, siting, and commercialization requirements. DID adequacy is given high priority in the early phase of design.

Even though many of these requirements are not directly associated with meeting licensing re-quirements, they often contribute to DID. User requirements for plant availability and reliability contribute to protecting the first layer of defense of DID in Figure 54 by controlling plant dis-turbances and preventing Initiating Events (IEs) and AOOs.

The selection of the inherent reactor characteristics for the design are determined by the early fundamental design decisions to address user requirements, operating experience, studies of tech-nology maturity, system engineering requirements and safety objectives. Examples of the kinds of decisions that are made in this step include power level, selection of the materials for the reac-tor, moderator, and coolant, neutron energy spectrum, thermodynamic cycle, parameters of the cycle and energy balance, and evaluation of options such as fuel type, indirect versus direct cy-cle, passive versus active safety systems, working fluids for secondary cycles, selection of design codes for major SSCs, Operations and Maintenance (O&M) philosophy, and other high level de-sign decisions driven by the top level requirements and results of the design trade studies. The decision whether to use inherent characteristics and passive SSCs as the primary means of assur-ing safety functions, supplemented by active systems that provide additional layers of defense to the prevention and mitigation of events is of particular relevance to any design.

At an early stage of design, a comprehensive set of plant level and system level functional re-quirements are developed. Examples of plant level requirements include requirements for pas-sive and active fulfillment of functions, man-machine interface requirements, plant cost, plant availability, plant investment protection requirements, construction schedule, load following ver-sus base load, barrier protections against external events, etc. This step includes the identifica-tion of systems and components and their functions, including energy production functions, maintenance functions, auxiliary functions, and safety functions and an identification of hazards associated with these SSCs. This is a purely deterministic step that produces a definition of the design in sufficient detail to begin the PRA.

53

The selection of inherent reactor characteristics, primary heat transport system design parame-ters, and materials selection for SSCs dictate the safe stable operating states for the reactor. Con-siderations of the need for periodic inspections and maintenance, O&M procedures, methods for starting up, shutting down, load following, and mode transitions are used to make decisions about the modes and states that need to be considered to complete the functional design and to perform the subsequent evaluations.

As part of the pre-conceptual design phase, a great deal of the DID capability is naturally estab-lished by addressing the fundamental top-level requirements of any design for operability, avail-ability, maintainability, and investment protection features for the design, using conventional practices and industry codes and standards etc. It is noted that additional plant capabilities as well as programs and compensating measures may be added as a result of maturing probabilistic and deterministic evaluations of plant safety and DID in subsequent steps.

Initially, the designer makes decisions on both the design and selection of codes and standards that influence design and some baseline level of special treatment. For example, the designer may select certain parts of the American Society of Mechanical Engineers (ASME) design codes for certain SSCs which may be linked to ASME requirements for in-service inspection. Provi-sions must then be made in the design and the definition of modes and states to perform the re-quired inspections. Final decisions on the frequency and extent of inspections will be made later in Box 14 of the figure. The full extent of special treatment is defined later following the evalua-tion of LBEs and the selection of SSC safety classes for each SSC. Hence, selection of codes and standards supports both the plant capabilities for DID and the activities that contribute to the programmatic DID.

As noted previously, the process of establishing DID capabilities in the plant design is an itera-tive process. Some portions of the design advance earlier than others, normally from the nuclear island to the power conversion and site support portions. As a result, some of the activities in Figure 54 are updated in parallel. Thus, the IDP process recurs more often than the serial picture as more and more of the design is completed and integrated evaluations of performance and DID become more robust.

Box 2. Establish F-C Target Based on TLRC and QHOs The F-C target derived from TLRC is an important risk-informed element of this framework as discussed previously. The evaluation of DID adequacy in Boxes 12 and 17 of Figure 54 focuses on the LBEs and associated SSCs with the highest levels of risk significance.

Box 3. Define SSC Safety Functions for PRA Modeling The plant designer defines the reactor specific safety functions as represented in Box 3. All reac-tors are designed to meet certain fundamental safety functions 5 such as retention of radioactive material, decay heat removal, and reactivity control. However, application of the reactor specific safety design approach leads to a set of reactor specific safety functions that achieve the funda-mental safety functions. During this process, the designer confirms the allocation of these safety 5

The term fundamental safety function is used extensively in IAEA publications such as IAEA SSR-2/1 (Rev. 1). [xx] The functions listed are the ones regarded as fundamental and are applicable to all reactor technologies.

54

functions to both passive and active SSCs. In Box 3, the top-level design criteria are also con-firmed for all the SSCs selected to perform the reactor specific safety functions. As Box 3 is completed the plant capabilities that support DID are largely determined. Adjustments may be made to address the results of subsequent evaluations or design iterations that may expose weak-nesses in design or operating assumptions, or expose margin or other uncertainties that are rele-vant to demonstrate adequate levels of safety and sufficient DID.

Box 4. Define Scope of PRA for Current Design Phase In the initial stages of the design, an evaluation is made to decide which hazards, IEs, and event sequences to consider within the design basis and for designing specific measures to prevent and to mitigate off normal events and accidents.

Box 5. Perform PRA The performance of the current phase of the PRA is covered in this box consistent with the framework described elsewhere in this guidance document. Information from the PRA is used together with deterministic inputs to establish DID adequacy as part of the risk-informed and performance-based evaluation of DID depicted in Boxes 12 and 17. The PRA is used together with traditional deterministic safety approaches to affect a risk-informed process. The PRA is not employed simply to calculate numerical risk metrics, but rather to develop risk insights into the design and to identify sources of uncertainty in the PRA models and supporting data that complement the deterministic elements of the framework. The DID evaluation includes the iden-tification of compensating protective measures to address the risk significant sources of uncer-tainty so identified.

Box 6. Identify and Categorize LBEs as AOOs, DBEs, or BDBEs The process for identifying and categorizing the LBEs in terms of AOOs, DBEs, and BDBEs was discussed in detail in the LBE section above. [xx]

Box 7. Evaluate LBE Risks vs. F-C Target An important input to evaluating DID adequacy is to establish adequate margins between the risks of each LBE and the F-C target. Such margins also help demonstrate conformance to the NRCs advanced reactor policy objectives of achieving higher margins of safety. In this process, the most risk significant LBEs are identified. These provide a systematic means to better focus attention on those events that contribute the most to the design risk profile.

Box 8. Evaluate Plant Risks vs. Cumulative Risk Targets In addition to establishing adequate margins between the risks of individual LBEs and the F-C targets, the evaluation of the margins against the cumulative risk metrics identified previously is also necessary to establish DID adequacy Box 9. Identify DID Layers Challenged by Each LBE The layers of defense framework in Figure 53 are used in this box to evaluate each LBE with more attention paid to risk significant LBEs to identify and evaluate the DID attributes to support the capabilities in each layer and to minimize dependencies among the layers.

55

Box 10. Select Safety-Related SSCs and Define DBAs The selection of SR SSCs is accomplished by examining each of the DBEs and high conse-quence BDBEs and performing sensitivity analyses to determine which of the safety functions modeled in these LBEs are required to perform their prevention or mitigation functions to keep the DBEs and high consequence BDBEs inside the F-C target. Those safety functions are classi-fied as required safety functions. In general, there may be two or more different sets of SSCs that could provide these required safety functions. Those functions specified by the design team (represented on the IDP) select which of the available SSCs that can support the required safety functions for all the DBEs and high consequence BDBEs are designated as safety-related. DBAs are then constructed starting with each DBE and then assuming only the safety-related SSCs per-form their prevention or mitigation function. DID considerations are taken into account in the selection of safety-related SSCs by selecting those that yield high confidence in performing their functions with sufficient reliability and to minimize uncertainties.

Box 11. Perform Safety Analysis of DBAs Conservative deterministic safety analyses of the DBAs are performed in a manner that is analo-gous to that for current generation light water reactors in this step of the process. The conserva-tive assumptions used in these analyses make use of insights from the PRA which includes an analysis of the uncertainties in the plant response to events, mechanistic source terms, and radio-logical consequences. Programmatic DID considerations are taken into account in the formula-tion of the conservative assumptions for these analyses which need to show that the site bound-ary doses meet 10 CFR 50.34 acceptance limits.

Box 12. Confirm Plant Capability DID Adequacy At this step, there is sufficient information, even during conceptual engineering phase, to evalu-ate the adequacy of the plant capabilities for DID using information from the previous steps and guidelines for establishing the adequacy of DID. This step is supported by the results of the sys-tematic evaluation of LBEs using the layers of defense process outlined in Figure 53 in Box 9.

As part of the DID adequacy evaluation, each LBE is evaluated to confirm that risk targets are met without exclusive reliance on a single element of design, single program, or single DID at-tribute.

Box 13. Identify Non-Safety-Related with Special Treatment (NSRST) SSCs All the SSCs that participate in a layer of defense are generally not classified as SR. However, these SSCs are evaluated against criteria for establishing SSC risk significance and additional criteria for whether the SSC provides a function required for DID adequacy. Criteria for classi-fying SSCs as safety significant based on DID considerations is presented in Section 4. SSCs not classified as SR or NSRST are classified as NST. None of the NST SSCs are regarded as safety significant even though they may contribute to the plant capability for DID. This is true because SSCs that perform a function that prevents and/or mitigates a release of radioactive ma-terial are modeled in the PRA and are candidates for SSC classification. All of the safety signifi-cant SSCs are classified as either SR or NSRST.

56

Box 14. Define and Evaluate Functional Design Criteria for SR SSCs FDC provide a bridge between the DBAs and the formulation of principle design criteria for the SR SSCs. DID attributes such as redundancy, diversity, and independence, and the use of pas-sive and inherent means of fulfilling safety functions are used in the formulation of FDCs.

Box 15. Evaluate Uncertainties and Margins One of the primary motivations of employing DID attributes is to address uncertainties, includ-ing those that are reflected in the PRA estimates of frequency and consequence as well as other uncertainties which are not sufficiently characterized for uncertainty quantification nor amenable to sensitivity analyses. The plant capability DID include design margins that protect against un-certainties. The layers of defense within a design, including layer 5, off-site response, are used to compensate for residual unknowns. The approach to identifying and evaluating uncertainties that are quantified in the PRA and used to establish protective measures reflected in the plant ca-pability and programmatic elements of DID is described previously.

Box 16. Specify Special Treatment Requirements for SR and NSRST SSCs All safety significant SSCs that are distributed between SR and NSRST are subject to special treatment requirements. These requirements always include specific performance requirements to provide adequate assurance that the SSCs will be capable of performing their functions with significant margins and with a high degree of reliability. These include numerical targets for SSC reliability and availability, design margins for performance of essential safety functions, and monitoring of performance against these targets with appropriate corrective actions when targets are not fully realized. Another consideration in the setting of SSC performance requirements is the need to assure that the results of the plant capability DID evaluation in Box 12 are achieved not just in the design, but in the as-built and as-operated and maintained plant following manu-facturing and construction, and maintained during the life of the plant. The SSC performance targets are set by the design IDP that is responsible for establishing the adequacy of DID. In ad-dition to these performance targets, additional special treatments may be identified.

Box 17. Confirm Programmatic DID Adequacy The adequacy of the programmatic measures for DID is driven by the selection of performance requirements for the safety significant SSCs in Box 16. The programmatic measures are evalu-ated relative to the risk significance of the SSCs; roles of SSCs in different layers of defense and the effectiveness of special treatments in providing additional confidence that the risk significant SSCs will perform as intended.

Box 18. DID Adequacy Established; Document/Update DID Baseline Evaluation The RIPB evaluation of DID adequacy continues until the recurring evaluation of plant and pro-grammatic DID associated with design and PRA update cycles no longer identifies risk-signifi-cant vulnerabilities where potential compensatory actions may be needed. At this point, a DID baseline can be finalized to support the final design and operations the plant.

The successful outcomes of Boxes 12 and 17 establish DID adequacy. This determination is made by the IDP and documented initially in a DID integrated baseline evaluation report which is subsequently revised as the iterations through the design cycles and design evaluation evolve.

57

5.4. How Major Elements of the TI-RIPB Framework are Employed to Establish DID Adequacy As seen in this table, there are important DID roles in each major element of the framework.

Table 51. Role of Major Elements of TI-RIPB Framework in Establishing DID Adequacy Elements of TI-RIPB Role in Establishing DID Adequacy Framework Selection of inherent, active, and passive design features Selection of approach to radionuclide functional and physical barriers Designer De-Definition of safety functions to prevent and mitigate accidents for inclusion into the PRA velopment of Safety Design Selection of passive and active SSCs to perform safety functions with consideration of the Com-Approach missions Advanced Reactor Safety Policy to simplify designs and rely more on inherent and passive means to fulfill safety functions Initial selection of DID attributes for plant capability and programmatic DID Identification of challenges to each layer of DID and evaluation of the plant responses to them Identification of challenges to physical and functional barriers within layers of defense Characterization of the plant responses to initiating events and identification of end states in-volving successful mitigation and associated success criteria, and unsuccessful mitigation with release of radioactive material from one or more reactor modules or radionuclide sources Assessment of the effectiveness of barriers in retaining fission products via mechanistic source term development and assessment offsite radiological consequences Assessment of the initiating event frequencies, reliabilities, and availabilities of SSCs required to Reactor Spe- respond to those initiating events cific PRA Identification of dependencies and interactions among SSCs; evaluation of the layers of defense against common cause failures and functional independence Grouping of the event sequences into LBEs based on similarity of initiating event challenge, plant response, and end state Information for the evaluation of risk significance Identification of key sources of uncertainty in modeling event sequences and estimation of fre-quencies and consequences Quantification of the impact of uncertainties via uncertainty and sensitivity analyses Identification and documentation of scope, assumptions, and limitations of the PRA 58

Identification of safety margins in comparing LBE risks against F-C targets and cumulative risk cri-teria Selection and Evaluation of the risk significance of LBEs Evaluation of Confirmation of the required safety functions LBEs Input to the selection of safety-related SSCs Input to the formulation of conservative assumptions for the deterministic safety analysis of DBAs Classification of NSRST and NST SSCs SSC Safety Selection of SSC Functional Design Criteria Classification Selection of design requirements for safety-related SSCs and Perfor-mance Re- Selection of performance-based reliability, availability, and capability targets for safety signifi-quirements cant SSCs Selection of Special Treatment Requirements for safety significant SSCs Evaluation of DID attributes for DID Input to identification of safety significant SSCs Input to the selection of safety-related SSCs Evaluation of roles of SSCs in the prevention and mitigation of LBEs Evaluation of the LBEs to assure adequate functional independence of each layer of defense.

Risk-Informed Evaluation of single features that have a high level of risk importance to assure no overdepend-Evaluation of ence on that feature and appropriate special treatment to provide greater assurance of perfor-DID Adequacy mance Input to SSC performance requirements for reliability and capability of risk significant prevention and mitigation functions Input to SSC performance and special treatment requirements Integrated evaluation of the plant capability DID Integrated evaluation of programmatic measures for DID The IDP uses information and insights in each of these elements to support a risk-informed and performance-based evaluation of DID adequacy. As indicated in Figure 52, RIPB decisions that are made in this evaluation feedback any necessary changes to the DID attributes reflected in the plant capability and programmatic elements of DID.

5.5. RIPB Compensatory Action Selection and Sufficiency Because the design, safety analyses, and PRA will be developed in phases and in an iterative fashion, the DID adequacy evaluation and baseline are updated as the design matures. The DID evaluation can be depicted as the more detailed DID framework shown in Figure 52 using infor-mation as it is developed in the design process to adjust the plant capability features or program-matic actions as the state of DID knowledge improves with the design evolution.

59

5.6. Establishing the Adequacy of Plant Capability DID The RIPB evaluation of DID adequacy is complete when the recurring evaluation of plant capa-bility and programmatic capability associated with design and PRA update cycles no longer identifies risk-significant vulnerabilities where potential compensatory actions can make a practi-cal, significant improvement to the LBE risk profiles or risk significant reductions in the level of uncertainty in characterizing the LBE risk. The IDP is responsible for making the deliberate, af-firmative decision that DID adequacy has been achieved. This decision should be clearly rec-orded, including the bases for this decision, in a configuration-controlled document. At this point, the DID baseline should be finalized to support the operational phase of the plant.

5.6.1. Guidelines for Plant Capability DID Adequacy The approach to establishing plant capability DID begins in the development of the safety design approach and is accomplished in the course of the iterative process steps leading up the selection and evaluation of the licensing basis events and is also impacted by this framework to SSC safety classification. Box 7e in represents the step in the LBE evaluation where the plant capability for DID is assessed. As discussed in the NRC documents that describe the DID philosophy, layers and DID attributes play a significant role in the approach to DID capability. However, there do not exist any well-defined regulatory acceptance criteria for deciding the sufficiency of the DID for nuclear power plant licensing or operation. To support the design and licensing of advanced non-LWRs within this framework, a set of DID adequacy guidelines has been provided. The guidelines can be used as a basis for initially evaluating the adequacy of plant capability DID but must be confirmed with regulators as appropriate and sufficient. These guidelines are presented in Table 52.

60

Table 52. Guidelines for Establishing the Adequacy of Overall Plant Capability Defense-in-Depth Layer Guideline Overall Guidelines Layer[a]

Quantitative Qualitative Quantitative Qualitative

1) Prevent off-normal opera- Maintain frequency of plant transients within designed cycles; meet user tion and AOOs requirements for plant reliability and availability[b]
2) Control abnormal opera-Maintain frequency of all DBEs Minimize frequency of challenges to tion, detect failures, and

< 102/ plant-year safety-related SSCs prevent DBEs No single design

3) Control DBEs within the Meet F-C target or operational No single design or operational fea-analyzed design basis Maintain frequency of all BDBEs for all LBEs and feature,[c] no ture[c] relied upon to meet quantita-conditions and prevent < 10-4/ plant-year cumulative risk matter how ro-tive objective for all DBEs BDBEs metric targets bust, is exclu-with sufficient[d] sively relied upon margins to satisfy the five
4) Control severe plant con- layers of defense ditions, mitigate conse-quences of BDBEs No single barrier[c] or plant feature Maintain individual risks from all relied upon to limit releases in LBEs < QHOs with sufficient[d] mar-
5) Deploy adequate offsite achieving quantitative objectives for gins protective actions and all BDBEs prevent adverse impact on public health and safety tes:

The plant design and operational features and protective strategies employed to support each layer should be functionally independent Non-regulatory user requirements for plant reliability and availability and design targets for transient cycles should limit the frequency of initiating events and transients and thereby contribute to the protective strategies for this layer of DID. Quantitative and qualitative targets for these pa-rameters are design specific.

This criterion implies no excessive reliance on programmatic activities or human actions and that at least two independent means are provided to meet this objective.

The level of margins between the LBE risks and the QHOs provides objective evidence of the plant capabilities for DID. Sufficiency will be decided by the IDP.

61

5.6.2. DID Guidelines for Defining Safety Significant SSCs As shown in Boxes 2 and 3 of this SSC Safety Classification process, SSCs are classified as safety significant if they perform one or more functions that are classified as risk significant, or necessary for adequacy of DID. The plant capability DID adequacy guidelines in Table 52 re-quire that two or more independent plant design or operational features be provided to meet the guidelines for each LBE. Any SSCs required to meet this guideline, as determined by the IDP, would be regarded as performing a safety function necessary for adequacy of plant capability DID. Such SSCs, if classified as risk significant, would already be classified as safety signifi-cant. If one of the plant features used to meet the need for multiple DID measures in Table 52 involves the use of SSCs that are neither safety-related nor risk significant, the IDP would clas-sify the SSC as safety significant and NSRST because it performs a function required for DID adequacy according to the guidelines in Table 52.

SSCs that are regarded as safety significant but are not SR are classified as NSRST. Special treatment requirements for NSRST SSCs include the setting of performance requirements for SSC reliability, availability, and capability and any other treatments deemed necessary by the IDP responsible for guiding the integrated design process in Figure 54 and evaluating the ade-quacy of DID.

5.6.3. DID Attributes to Achieve Plant Capability DID Adequacy The evaluation of plant capability DID adequacy focuses on the completeness, resiliency, and robustness of the plant design with respect to addressing all hazards, responding to identified IEs, the availability of independent levels of protection in the design for preventing and mitigating the progression of IEs, and the use of redundant and diverse means to achieve the needed levels of protection sufficient to address different threats to public health and safety. Additionally, the plant capability DID adequacy evaluation examines whether any single feature is excessively re-lied on to achieve public safety objectives, and if so identifies options to reduce or eliminate such dependency. The completion of the plant capability DID adequacy evaluation supports making an appropriate safety case and ultimate finding that a plant poses no undue risk to public health and safety.

Table 53 lists the plant capability DID attributes and principal evaluation focus included in this DID evaluation scope. The evaluation of plant capability involves the systematic evaluation of hazards that exist for a given technology and specific design over the spectrum of all modes and states including anticipated transients and potential accidents within and beyond the design basis.

Table 53. Plant Capability Defense-In-Depth Attributes Attribute Evaluation Focus PRA Documentation of Initiating Event Selection and Event Sequence Modeling Initiating Event and Accident Sequence Completeness Insights from reactor operating experience, system engineering evaluations, ex-pert judgment 62

Multiple Layers of Defense Extent of Layer Functional Independence Layers of Defense Functional Barriers Physical Barriers Inherent Reactor Features that contribute to performing safety functions Functional Reliability Passive and Active SSCs performing safety functions Redundant Functional Capabilities Diverse Functional Capabilities SSCs performing prevention functions Prevention and Mitigation SSCs performing mitigation functions Balance No Single Layer /Feature Exclusively Relied Upon 5.7. Evaluation of LBEs Against Layers of Defense A key element of the RIPB evaluation of DID is a systematic review of the LBEs against the lay-ers of defense. This review by the IDP is necessary to evaluate the plant capabilities for DID and to identify any programmatic DID measures that may be necessary for establishing DID ade-quacy. This review has the following objectives:

  • Confirm that plant capabilities for DID are deployed to prevent and mitigate each LBE at each layer of defense challenged by the LBE
  • Confirm that a balance between accident prevention and mitigation reflected in the layers of defense for risk significant LBEs
  • Identify the reliability/availability missions of SSCs that perform prevention and mitigation functions along each LBE and confirm that these missions can be accomplished. A relia-bility/availability mission is the set of requirements related to the performance, reliability, and availability of an SSC function that adequately ensures the accomplishment of its task, as defined by the PRA or deterministic analysis
  • Confirm that adequate technical bases for classifying SSCs as safety-related or non-safety-related and risk-significant exists and their capabilities to execute the required safety func-tions are defined
  • Confirm that the effectiveness of physical and functional barriers to retain radionuclides in preventing or limiting release is established 63
  • Review the technical bases for important characteristics of the LBEs with focus on the most risk significant LBEs, and LBEs with relatively higher consequences.6 The technical bases for relatively high frequency LBEs that are found to have little or no release or radio-logical consequences is also a focus of the review.
  • Confirm that risk significant sources of uncertainty that need to be addressed via program-matic and plant capability DID measures have been adequately addressed An important consideration in the safety classification of SSCs and in the formulation of SSC performance requirements is the understanding of the roles of SSCs modeled in the PRA in the prevention and mitigation of accidents. This understanding is the basis for the formulation of the SSC capability requirements for mitigation of the challenges represented in the LBEs as well as the reliability requirements to prevent LBEs with more severe consequences. This understanding is also key to recognizing how the plant capabilities for DID achieve an appropriate balance be-tween accident prevention and mitigation across different layers of defense, which permits an ex-amination of the evaluation of the plant capabilities in the context of the layers of defense that were delineated in Figure 53.

A generalized model for describing an event sequence in terms of the design features that sup-port prevention and mitigation reflecting the above insights is provided in Table 54. This table provides an important feedback mechanism between risk-informed and performance-based eval-uation of DID and plant capability DID. The event sequence framework is part of the risk-in-formed evaluation of DID, and the roles of SSCs in the prevention and mitigation of accidents are the result of the plant capability DID. The reliabilities and capabilities of the SSCs that pre-vent and mitigate events are influenced by both the plant capability and programmatic DID ele-ments. Programmatic DID reduces the uncertainty in the reliability and capability performance of the SSCs responsible for prevention and mitigation.

Table 54. Event Sequence Model Framework for Evaluating Plant Capabilities for Prevention and Miti-gation of LBEs Standard Elements of Ac- Design Features Contributing to Design Features Contributing to Mitigation cident Sequence Prevention Reliability of SSCs supporting Capabilities of normally operating systems to Initiating Event Occur- power generation reduces the IE continue operating during disturbances to pre-rence frequencies; successful operation vent initiating events serve to mitigate events of the SSCs prevents the sequence. and faults that may challenge these functions.

6 LBEs with site boundary doses exceeding 1 rem (total effective dose equivalent), the lower EPA Protective Action Guideline dose, are regarded as having relatively high consequences for this purpose.

64

Response of Active SSCs Reliability and availability of active Capabilities of active successful SSCs including Supporting Safety Func- SSCs reduce sequence frequency; design margins reduce the impacts of the initi-tions: Successful and successful operation of these SSCs ating events and reduce the challenges to bar-Failed SSCs prevents the sequence. rier integrity.

Response of Passive Fea- Reliability and availability of pas- Capabilities of passive successful SSCs including tures Supporting Safety sive SSCs reduce sequence fre- design margins reduce the impacts of the initi-Functions: Successful and quency; successful operation of ating events and reduce the challenges to bar-Failed SSCs these SSCs prevents the sequence. rier integrity.

Inherent and passive capabilities of the fuel in-Fraction of Source Term None cluding design margins given successful active Released from Fuel or passive SSCs limit the release from the fuel.

Inherent and passive capabilities of the pressure Fraction of Source Term boundary including design margins given suc-Released from the Cool- None cessful active or passive SSCs and the capabili-ant Pressure Boundary ties of the fuel limit the release from the pres-sure boundary.

Inherent and passive capabilities of the reactor building barrier including design margins condi-Fraction of Source Term tioned on the successful response of any active Released from Reactor None or passive SSCs along the sequence and the ca-Building Barrier pabilities of the fuel and coolant pressure boundary limit the release from the reactor building barrier.

Inherent and passive features and capabilities of the fuel, coolant pressure boundary, and re-Time to Implement Emer-actor building barrier including design margins gency Plan Protective Ac- None conditioned on the successful response of any tions active or passive SSC along the sequence dictate the time available for emergency response.

The accident sequence framework for evaluating accident prevention and mitigation in Table 54 is used to define a simple model for estimating the risk of a release of radionuclides associated with a specific accident sequence, or LBE:

(1) 65

Rj = Expected quantity of radioactive material released per year from sequence j Q = Quantity of radionuclides (for a given isotope) in the reactor core inventory FIE,j = Frequency of the initiating event associated with sequence j PASSC,j = Probability of active SSCs successes and failures along sequence j PPSSC,j = Probability of passive SSCs successes and failures along sequence j rfuel, j= Release fraction from the fuel barrier, given system and structure response for se-quence j rPB,j = Release fraction from the coolant pressure boundary for sequence j rcont,j = Release fraction from the reactor building barrier for sequence j 5.7.1. Evaluation of LBE and Plant Risk Margins The purpose of this section is to explain how margins are established between the frequencies and consequences of individual LBEs and the F-C target used to evaluate the risk significance of LBEs. These margins are established for the LBEs having the highest risk significance within each of the three LBE categories (AOOs, DBEs, and BDBEs Margins are developed in two forms. The margins to the F-C target are measured based on mean values of the LBE frequencies and doses. In each case, margin is expressed as a ratio of the events mean value (frequency and dose) to the corresponding F-C target value (frequency and dose). These are the best measure of the margins because traditionally in the PRA community, mean values are compared to targets such as design objectives for core damage frequency and large early release frequency and the NRC safety goal QHOs.

A more conservative evaluation of margins is similar to above in which the 95th percentile upper bound values for both LBE frequency and dose are used to calculate the margins.

This process is repeated for each individual LBE, grouped by LBE category as part of the DID evaluation during the design development.

5.7.2. Integrated Decision Panel Focus in LBE Review The evaluation of LBEs by the IDP will focus on the following questions:

66

  • Is the selection of initiating events and event sequences reflected in the LBEs sufficiently complete? Are the uncertainties in the estimation of LBE frequency, plant response to events, mechanistic source terms, and dose well characterized? Are there sources of uncer-tainty not adequately addressed?
  • Have all risk significant LBEs and SSCs been identified?
  • Has the PRA evaluation provided an adequate assessment of cliff edge effects?
  • Is the technical basis for identifying the required safety functions adequate?
  • Is the selection of the SR SSCs to perform the require safety functions appropriate?
  • Have protective measures to manage the risks of multi-module and multi-radiological source accidents been adequately defined?
  • Have protective measures to manage the risks of all risk significant LBEs been identified, especially those with relatively high consequences?
  • Have protective measures to manage the risks for all risk significant common cause initiat-ing events such as support system faults, internal plant hazards such as fires and floods, and external hazards been identified?
  • Is the risk benefit of all assigned protective measures well characterized, e.g., via sensitiv-ity analyses?

If the evaluation identifies unacceptable answers to any of these questions, additional compensa-tory action would be considered, depending on the risk significance of the LBE. With reference to Figure 54, which identifies feedback loops in the framework at each evaluation step of the process, the compensatory action can take on different forms including changes to design and operation, refinements to the PRA, revisions to the selection of LBEs and safety classification of SSCs, as well as enhancements to the programmatic elements of DID.

5.8. Establishing the Adequacy of Programmatic DID 5.8.1. Guidelines for Programmatic DID Adequacy The adequacy of programmatic DID is based on meeting the following objectives:

  • Assuring adequate margins exist between the assessed LBE risks relative to the F-C target including quantified uncertainties
  • Assuring adequate margins exist between the assessed total plant risks relative to the Cu-mulative Risk Targets
  • Assuring appropriate targets for SSC reliability and performance capability are reflected in design and operational programs for each LBE
  • Providing adequate assurance that the risk, reliability, and performance targets will be met and maintained throughout the life of the plant with adequate consideration of sources of significant uncertainties 67

Unlike the plant capabilities for DID which can be described in physical terms and are amenable to quantitative evaluation, the programmatic DID adequacy must be established using engineer-ing judgment by determining what package of DID attributes are sufficient to meet the above ob-jectives. These judgments are made by the IDP using the programmatic DID attributes and eval-uation considerations in Table 55.

Table 55. Programmatic DID Attributes Attribute Evaluation Focus Performance targets for SSC reliability and capability Quality / Reliability Design, manufacturing, construction, O&M features, or special treat-ment sufficient to meet performance targets Compensation for human errors Compensation for Uncer- Compensation for mechanical errors tainties Compensation for unknowns (performance variability)

Compensation for unknowns (knowledge uncertainty)

Off-Site Response Emergency response capability The attributes of programmatic DID complement each other and provide overlapping assurance that the design plant capability is achieved in design, manufacturing, construction, and opera-tions lifecycle phases. The evaluation focus items in Table 55 should be answered for each pro-grammatic DID attribute for risk significant LBEs in order to determine that the programmatic DID provides sufficient confidence that there is reasonable assurance of adequate protection of public health and safety based on the design plant capability. The net result establishing and evaluating programmatic DID is the selection of special treatment programs for all safety signifi-cant SSCs, which include those classified as SR or NSRST.

5.8.2. Application of Programmatic DID Guidelines In the evaluation of programmatic DID using the attributes in Table 55 and the questions raised in Table 56, the considerations discussed below will be used by the IDP.

68

Table 56. Evaluation Considerations for Evaluating Programmatic DID Attributes Evaluation Fo- Implementation Strat-Attribute Evaluation Considerations cus egies

1. Is there appropriate bias to prevention of AOOs progressing to postulated accidents?
2. Has appropriate conservatism been applied in bounding deterministic safety analysis of more risk Conservatism with significant LBEs?

Bias to Preven- 3. Is there reasonable agreement between the deterministic safety analysis of DBAs and the upper Design tion bound consequences of risk-informed DBA included in the LBE set?

Testing Equipment Codes 4. Have the most limiting design conditions for SSCs in plant safety and risk analysis been used for se-Quality / Manufactur-and Standards lection of safety-related SSC design criteria?

Reliability ing Equipment Qualifi- 5. Is the reliability of functions within systems relied on for safety overly dependent on a single inher-Construction cation ent or passive feature for risk significant LBEs?

O&M Performance Test- 6. Is the reliability of active functions relied upon in risk significant LBEs achieved with appropriate ing redundancy or diversity within a layer of defense?

7. Have the identified safety-related SSCs been properly classified for special treatment consistent with their risk significance?

Operational Com- 1. Have the insights from the Human Factors Engineering program been included in the PRA appropri-mand and Con- ately?

trol Practices 2. Have plant system control designs minimized the reliance on human performance as part of risk-Training and Quali- significant LBE scenarios?

Compensa- Compensa-fication 3. Have plant protection functions been automated with highly reliable systems for all DBAs?

tion for tion for Plant Simulators 4. Are there adequate indications of plant state and transient performance for operators to effec-Uncertain- Human Er-Independent Over- tively monitor all risk-significant LBEs?

ties rors sight and Inspec- 5. Are the risk-significant LBEs all properly modeled on the plant reference simulator and adequately tion Programs confirmed by deterministic safety analysis?

Reactor Oversight 6. Are all LBEs for all modes and states capable of being demonstrated on the plant reference simula-Program tor for training purposes?

69

Evaluation Fo- Implementation Strat-Attribute Evaluation Considerations cus egies Operational Tech-nical Specifica-

1. Are all risk-significant LBE limiting condition for operation reflected in plant Operating Technical Compensa- tions Specifications?

tion for Allowable Outage

2. Are Allowable Outage Times in Technical Specifications consistent with assumed functional reliabil-Mechani- Times ity levels for risk-significant LBEs?

cal Errors Part 21 Reporting

3. Are all risk-significant SSCs properly included in the Maintenance Program?

Maintenance Rule Scope Compensa-Operational Tech-tion for 1. Are the Technical Specification for risk-significant SSCs consistent with achieving the necessary nical Specifica-Unknowns safety function outcomes for the risk significant LBEs?

tions (Perfor- 2. Are the in-service monitoring programs aligned with the risk-significant SSC identified through the In-Service Moni-mance RIPB SSC Classification process?

toring Programs Variability)

1. Have the uncertainties identified in PIRT or similar evaluation processes been satisfactorily ad-dressed with respect to their impact on plant capability and associated safety analyses?

Compensa- Site Selection 2. Has physical testing been done to confirm risk significant SSC performance within the assumed tion for PIRT/ Technical bounds of the risk and safety assessments?

Unknowns Readiness Levels 3. Have plant siting requirements been conservatively established based on the risk from severe acci-(Knowledg Integral Systems dents identified in the PRA?

e Uncer- Tests / Separate 4. Has the PRA been peer reviewed in accordance with applicable industry standards and regulatory tainty) Effects Tests guidance?

5. Are hazards not included in the PRA low risk to the public based on bounding deterministic analy-sis?
1. Are functional response features appropriately considered in the design and emergency opera-Layers of Response tional response capabilities for severe events as a means of providing additional DID for undefined Strategies Emergency event conditions?

Off-Site Re- EPZ location Response 2. Is the Emergency Planning Zone appropriate for the full set of DBEs and BDBEs identified in the LBE sponse EP Programs Capability selection process?

Public Notification

3. Is the time sufficient to execute EP protective actions for risk significant LBEs consistent with the Capability event timelines in the LBEs?

70

71 Quality and Reliability The initial quality of the design is developed through the application of proven practices and ap-plication of industry codes and standards. In cases where no approved codes and standards are available, conservative adaptation of existing practices from other industries or first principles derivations of repeatable practices may be required. Conservatism should be applied in cases where common practices and codes are not available. The use of new practices should be vali-dated to the degree practical against physical tests or other operating experiences if risk signifi-cant SSCs are involved. The PRA should consider the uncertainties of unproven methods or standards for specific risk significant functions. This question should be examined by the IDP.

The primary focus on reliability in the evaluation of DID is on the establishment of the func-tional reliability targets for SSCs that prevent or mitigate risk significant LBEs as part of a layer of defense and associated monitoring of reliability performance against the targets. The reliabil-ity can be achieved by some combination of inherent, passive, or active SSC capabilities. The appropriate use of redundancy and diversity to achieve the reliability targets set by the IDP to-gether with the plant technical specifications should be evaluated.

Margin Adequacy At the plant level, performance margins to established design goals and regulatory limits are evaluated as part of DID adequacy. At the individual SSC level, properly designing SSCs to proven codes and standards provides an appropriate level of design margin in the level of assur-ance that the SSC will perform reliably at its design conditions and normally include reserve margin for more demanding conditions. The DID evaluation should include a determination that the appropriate codes were applied to safety significant SSCs (included in SR and NSRST safety categories) and that the most demanding normal operation, AOO, DBE, or DBA parameters for that component, conservatively estimated, have been used for the design point. For SSCs that play a role in risk-significant BDBEs, the DID evaluation should evaluate the inherent perfor-mance margins in SSCs against the potentially more severe conditions of BDBEs in the PRA.

Treatment of Uncertainty in Programmatic DID In judging DID adequacy, at each stage of design and operations, designers, managers, owners, and operations Staff must continually keep in mind that errors are possible, equipment can fail and real events do not always mimic analytical events. For that reason, the risk triplet ques-tions: What can go wrong? How likely is it? What are the consequences? must become an institutionalized set of questions as a part of deciding the how to deal with residual risk and un-certainty. The primary means to address these residual risks is through effective Severe Acci-dent Management Programs and effective Emergency Planning. Siting and Emergency Planning Zone size considerations take into account the known risks of a plant, siting in less populated ar-eas, and having proactive Emergency Planning programs that take precautionary actions well be-fore a serious threat to public health can arise.

Compensation for Unknowns The layers of defense approach utilized in the DID evaluation framework includes the need to define protective measures to address unknowns. Feedback from actual operating and mainte-nance experience to the PRA provides performance-based outcomes that are part of plant moni-72

toring. Periodic PRA updates should incorporate that information into reliability (system or hu-man) estimates to determine whether significant LBE risks have changed or new events emerged.

All nuclear industry sources of information should be utilized for known, risk-significant LBEs.

Operator and management training programs should contain appropriate requirements for dealing with each identified risk significant BDBEs, and include provision for event management of po-tential accidents undefined in the PRA due to truncation or other limitations in modeling or scope for this phase of the design/PRA development. The evaluation of programmatic DID should determine whether risk-significant LBEs are included in the routine training of operators and management.

Programmatic DID in Design Programmatic activities developed during design and licensing phases that are integral to design process include design-sensitive programs such as:

  • Development of risk-informed plant technical specifications
  • Tier 1 and inspections, tests, analyses, and acceptance criteria
  • Maintenance programs for safety significant SSCs (SR and NSRST)
  • In-service inspection and in-service testing programs The early consideration of the use of RIPB practices to establish the scope of these types of pro-grammatic actions supports the more efficient implementation of physical design features that minimize the scope of compliance activities and related burdens in the operational phase of the plant lifecycle.

Examples of special treatment programs are listed in Table 57. The actual special treatments are established by the IDP. Each of these programs and treatments are programmatic DID protective measures that should benefit from RIPB insights early in their development cycles in optimizing their value as part of an integrated risk management approach.

Table 57. Examples of Special Treatments Considered for Programmatic DID Programs Elements Special treatment specifications Engineering Assurance Independent design reviews Programs Physical testing and validation including integrated and separate effects tests Plant simulation and human factors engineering Organizational and Hu-Training and qualification of personnel man Factors Programs Emergency operating procedures 73

Accident management guidelines Limiting conditions for operation Technical Specifications Surveillance testing requirements Allowable outage (completion) times Equipment fabrication oversight Construction oversight Plant Construction and Start-Up Programs Factory testing and qualification Start-up testing Operation In-service testing Maintenance and Mon-In-service inspection itoring of SSC Perfor-mance Programs Maintenance of SSCs Monitoring of performance against reliability and capability performance indicators Inspections and audits Procurement QA Program Independent reviews Software verification and validation Event trending Corrective Action Pro-Cause analysis grams Closure effectiveness Independent Oversight and Monitoring Pro-grams Seismic qualification Equipment Qualifica-Adverse environment qualification tion Physical protection 74

Emergency Planning There are other programmatic activities spread across a broader portion of the industry that pro-vide additional levels of programmatic DID and contribute to assurance of public protection.

The NRC, Institute of Nuclear Power Operations, American Nuclear Insurers, ASME, and IAEA all play an important part of assuring public safety through their independent oversight and mon-itoring of the different phases of plant development and operations. Included in some of these oversight activities are self-reporting requirements that notify NRC and other external agencies of unexpected or inappropriate performance of SSCs or human activities.

5.9. Risk-Informed and Performance-Based Evaluation of DID Adequacy 5.9.1. Purpose and Scope of Integrated Decision Panel Activities Under this framework, an IDP will be responsible for evaluating the adequacy of DID. For cur-rently operating plants that are employing risk-informed changes to the licensing basis, such as risk-informed safety classification under 10 CFR 50.69, [xx] such panels are employed to guide the risk-informed decision-making process. The NEI has developed procedures and guidelines for the makeup and responsibilities of such panels. [xx] Specifically, NEI 00-04 Sections 9 and 11 provide valuable guidance on the composition of a panel (referred to as the Integrated Deci-sion-Making Panel within NEI 00-04) and the associated output documentation. The decisions of the IDP should be documented and retained as a quality record; this function is critical to fu-ture decision making regarding plant changes which have the potential to affect DID.

For advanced non-LWRs that are currently in various stages of design development, the IDP is comprised of a team that is responsible for implementing the integrated process steps for evaluat-ing DID shown in Figure 54. This team includes those responsible for the design, operations, and maintenance program development and for performing the necessary deterministic and prob-abilistic evaluations identified in this figure.

5.9.2. Risk-Informed and Performance-Based Decision Process The IDP will use a risk-informed and performance-based integrated decision-making (RIPB-DM) process. Risk-informed decision-making is the structured, repeatable process by which de-cisions are made on significant nuclear safety matters including consideration of deterministic and probabilistic inputs. The process is also performance-based because it employs measurable and quantifiable performance metrics to guide the decision that DID is adequate. RIPB-DM plays a key role in designing and evaluating the DID layers of defense and establishing measures associated with each plant capability and programmatic DID attribute.

Table 58 provides a listing of the integrated decision-making attributes and principal evaluation focus included in the RIPB DID evaluation scope to be executed by the IDP. The RIDM process is expected to be applied at each phase of the design processes in conjunction with other inte-grated review processes executed during design development as described in Figure 54. Meeting 75

the applicable portions of ASME/ANS PRA Standard for Advanced non-LWRs, [xx] which in-cludes the requirement for and completion of the appropriate PRA peer review process, is re-quired for use of the PRA in RIPB-DM processes.

Table 58. Risk-Informed and Performance-Based Decision-Making Attributes Attribute Evaluation Focus What can go wrong?

Use of Risk Triplet Beyond PRA How likely is it?

What are the consequences?

Plant Simulation and Modeling of LBEs Knowledge Level State of Knowledge Margin to PB Limits Uncertainty Management Magnitude and Sources of Uncertainties Implementation Practicality and Effectiveness Action Refinement Cost/Risk/Benefit Considerations The RIPB-DM process should include the following steps regardless of the phase of design:

  • Identification of the DID issue to be decided
  • Identification of the combination of defined DID attributes important to address current is-sues
  • Comprehensive consideration of each of the defined attributes individually, incorporating insights from deterministic analyses, probabilistic insights, operating experience, engineer-ing judgment, etc.
  • Knowledgeable, responsible individuals make a collaborative decision based on the defined attribute evaluation requirements
  • If compensatory actions are needed, identification of potential plant capability and /or pro-grammatic choices
  • Implementation closure of DID open actions and documentation of the results of the RIPB-DM process A key concept in DID adequacy evaluation RIPB-DM is that a graded approach to RIPB-DM is prudently applied such that the decisions on LBEs with the greatest potential risk significance receive corresponding escalated cross-functional and managerial attention, while routine deci-sions are made at lower levels of the organization consistent with their design control program.

76

Completing the evaluation of the DID adequacy of a design is not a one-time activity. The De-signer is expected to employ the RIPB-DM process as often as required to minimize the potential for revisions late in the design process due to DID considerations. Integrated DID adequacy evaluations would be expected to occur in concert with completion of each major phase of de-signconceptual, preliminary, detailed, and finaland would additionally occur in response to any significant design changes or new risk significant information at any phase of design or li-censing.

5.9.3. IDP Actions to Establish DID Adequacy Adequacy of DID is confirmed when the following actions and decisions by the IDP are com-pleted.

  • Plant capability DID is deemed to be adequate.
  • Plant capability DID guidelines in Table 52 are satisfied.
  • Review of LBEs is completed with satisfactory results.

Risk margins against F-C target are sufficient.

Risk margins against Cumulative Risk Targets are met.

Role of SSCs in the prevention and mitigation at each layer of defense chal-lenged by each LBE is understood.

Prevention/mitigation balance is sufficient.

Classification of SSCs into SR, NSRST, and NST is appropriate.

Risk significance classification of LBEs and SSCs are appropriate.

Independence among design features at each layer of defense is sufficient.

Design margins in plant capabilities are adequate to address uncertainties iden-tified in the PRA.

  • Programmatic DID is deemed to be adequate.
  • Performance targets for SSC reliability and capability are established.
  • Source of uncertainty in selection and evaluation of LBE risks are identified.

Completeness in selection of initiating events and event sequences is sufficient.

Uncertainties in the estimation of LBE frequencies are evaluated.

Uncertainties in the plant response to events are evaluated.

Uncertainties in the estimation of mechanistic source terms are evaluated.

Design margins in plant capabilities are adequate to address residual uncertain-ties.

  • Special treatment for all SR and NSRST SSCs is sufficient.

77

5.9.4. IDP Considerations in the Evaluation of DID Adequacy Risk Triplet Examination The evaluation of DID adequacy requires recurring examination of the design as it matures.

Thus, there needs to a recurring consideration of the three basic questions in the risk triplet:

What can go wrong?, How likely is it?, and What are the consequences? This should be done at the natural design phase review points as specific engineering information is baselined for the next design phase. In the reviews, hazards analysis updates, PRA updates, DBA safety analysis and plant level risk profiles (e.g. LBEs identified, changes in margins or uncertainties, or layers of defense features, human performance assumptions, etc.) should be an explicit com-ponent of the review and decision to continue to the next engineering phase.

State of Knowledge The level of knowledge during a design process matures from functional capabilities at plant and system level to physical characteristics that implement the functional design. During the period of early design evolution, trade studies that explore alternative configurations, alternate materi-als, inherent, passive and active system capabilities, etc. to most effectively achieve top level project criteria should be considered in light of DID objectives. Different PRA and non-PRA tools, commensurate with the availability of design information, should be utilized to provide risk insights to the designer as an integral part of the design development process. The scope and level of detail of the PRA will evolve as the level of design and site information matures. Rela-tive risk and reliability analyses should be developed in advance of the full PRA as they provide very valuable inputs to design functionality requirements as well early means to resolve opera-tional challenges. It is during this period of the design development, basic decisions on layers of defense that comprise a portion of the DID strategy are best formulated and documented and evaluated in appropriate design descriptions at plant and system level.

Margin Adequacy Once the initial PRA is developed, LBEs are available for examination. The margins between mean performance predictions and any insights into uncertainties around that performance should be evaluated as part of establishing an early DID baseline. Other sources of uncertainty caused by PRA scope boundaries, model incompleteness, methods or input data accuracy should be examined as well. The focus and level of scrutiny between no/low consequence LBEs and higher consequence LBEs should vary according to the risk significance.

Sources of Uncertainties The greatest number of uncertainties exist in the beginning of the design cycle and systematically are resolved through the iterative design process. Those are state-of-knowledge uncertainties that are transient in nature, they are unverified assumptions that are worked out over the design process and sometimes beyond. During design phase reviews, the DID evaluation should exam-ine significant assumptions or features that could materially alter plant or individual LBE risk profiles or whether there are single features that are risk significant that would benefit from addi-tional compensatory actions to improve performance capability or performance assurance.

Permanent uncertainties are typically broken down into two groups, those that are caused by var-iability or randomness, such as plant performance, and those that are as a result of gaps in 78

knowledge. DID adequacy evaluations should include both types of permanent uncertainties in reaching a final design adequacy conclusion. Attention in the evaluation of DID adequacy is paid to hazards excluded from the PRA that could either pose an on-site risk to plant or person-nel performance; and, those that could be a risk to the public due to significant non-radiological consequences.

Magnitude of Uncertainties DID adequacy evaluations will examine the nominal performance of the plant against various risk objectives. Evaluations will also include quantified uncertainties for PRA-derived LBEs in two ways, frequency uncertainty and consequence uncertainty. These are described more fully in the PRA and LBE guidelines.

Compensatory Action Adequacy DID adequacy evaluations should include the necessity, scope and sufficiency of existing design and operational programs being applied to a design or portion of a design. Specific consideration should be given to the RIPB capabilities of each program type to provide meaningful contribu-tions to risk reduction or performance assurance based on the risk significance of SSCs associ-ated with each LBE. Particular attention should be paid to the number of layers of defense that are associated with initiating events that can progressively cascade to the point of challenging public safety objectives. Initiating events that cannot cascade to a point of threating public health should be found acceptable with fewer layers of defense than events that have the poten-tial to release large amounts of radiation.

For risk significant BDBE, the evaluation should take into account both the magnitude of the consequences and the time frame for actions in determining the need for or choice of compensa-tory actions. Where dose predictions fall below regulatory limits, the availability of program-matic actions to mitigate those events should be considered over more sweeping changes to plant design to eliminate the BDBE which could be impractical to implement or excessively burden-some. Small changes to the design that improve the likelihood of successful actions should be consider in the light of the stage of design development attained. For any BDBE that exceeds regulatory siting limits, if practical, design changes should be considered over reliance on EP DID alone.

5.9.5. Baseline Evaluation of Defense-in-Depth As illustrated in Figure 54, there will be a number of iterations through the integrated design pro-cess to reflect different design development phases and the feedback loops indicated in Figure 52 where the DID evaluation leads to changes in the plant design to enhance the plant capability DID or changes to the protective measures reflected in the programmatic DID. Like many other licensing basis topics, changes in physical, functional, operational, or programmatic features re-quire consideration of the potential for reduction of DID before proceeding. This requires that a current baseline for DID be available as a reference for change evaluation. These changes in turn require revisions to the PRA and all the subsequent steps in the integrated design process.

The first complete pass through the integrated design process will require a baseline DID evalua-tion which completes the actions of the IDP. The baseline DID evaluation will be documented in sufficient detail so it can be efficiently updated in future design development iterations. The 79

checklists in Table 59 and Table 510 will serve as a reminder as to the scope of the evaluation which will be documented in a controlled document.

Table 59. Evaluation Summary - Qualitative Evaluation of Plant Capability DID Functional Physical LBE IE Series Name Multiple Pro- Prevention and No Single Margin Ade- Functional tective Mitigation Bal- Feature Re-quacy Reliability Measures ance lied Upon Normal Operation AOOs DBEs BDBEs DBAs Table 510. Evaluation Summary - Qualitative Evaluation of Programmatic DID Compensation for Uncertainties Quality/Reliability:

Offsite Response:

Design, Manufactur-LBE IE Series Name Human Er- Mechanical Emergency Re-ing, Construction, Unknowns rors Failures sponse Capability O&M Normal Operation AOOs DBEs BDBEs DBAs 5.9.6. Considerations in Documenting Evaluation of Plant Capability and Programmatic DID Simplify Change Evaluation Commented [NRC27]: This raises the topic of longer term The documentation of the DID baseline shall be derived from the design records, primarily those controls - into plant operation and maintaining elements of that verified the attributes described in previously were adequate. The development of the base- this process that is different from the operating fleet. This is likely the case, and we need to decide whether to introduce line should support and complement existing change control requirements such as 10 CFR 50.59 subject and refer to a future guidance document.

80

where the impact on DID is considered. The threshold for evaluating a change to the DID base-line should be informed by the risk significance of changes in LBE performance in the PRA. Commented [NRC28]: We need to discuss possible impli-This involves the following considerations as part of the RIDM process for plant changes: cations of changes in baseline due to changes in PRA due to operating experience and maintenance of PRA, DiD, etc.

over the lifetime of the plant. See previous notes on how we

  • Does the change introduce a new LBE for the plant? connect design, construction, and operations for improved integrated process
  • Does the change increase the risk of LBEs previously considered to be of no/low risk sig-nificance to the point that it will be considered risk-significant after the change is made?
  • Does the change reduce number of layers of defense for any impacted LBEs or materially alter the effectiveness of an existing layer of defense?
  • Does the change significantly increase the dependency on a single feature relied on in risk-significant LBEs?

If the answer to any of the above questions is yes, a complete evaluation of all of the DID attrib-utes is performed. As a result of the more comprehensive evaluation of DID changes, the IDP will reject the change or recommend additional compensatory actions to plant capability or pro-grammatic capability if practical to return a baseline LBE performance to within the current DID baseline. If the compensatory actions are not effective, the change may require NRC notification in accordance with current license and regulatory requirements.

The evaluation of DID adequacy should be documented in two parts; quantitative and qualitative, covering the DID attributes established above. The summary the DID baseline includes:

Quantification of LBE Margins Against F-C Target The purpose is to explain how margins are established between the frequencies and conse-quences of individual LBEs and the F-C target used to evaluate the risk significance of LBEs.

These margins are established for the LBEs having the highest risk significance within each of the three LBE categories: AOOs, DBEs, and BDBEs.

Summary Evaluation of DID Adequacy Baseline Additionally, qualitative evaluation of DID adequacy is performed for each LBE. Adequate qualitative DID is provided when a qualitative evaluation determines observable attributes of the design demonstrate the conservative principles supporting DID are, in combination, sufficient.

The conclusion is reached through an integrated decision-making process to verify the following are in place commensurate with the identified event risks.

5.9.7. Evaluation of Changes to Defense-in-Depth For each iteration of the design evaluation life cycle in Figure 54, the DID evaluation from the baseline will be re-evaluated based on a review to determine which programmatic or plant capa-bility attributes have been affected for each layer of defense. Obviously changes that impact the definition and evaluation of LBEs, safety classification of SSCs, or risk significance of LBEs or SSCs will need to have the DID adequacy re-evaluated and the baseline updated as appropriate.

81

6. REFERENCES Editorial placeholder; references to be added in future draft.

82