ML18116A149
| ML18116A149 | |
| Person / Time | |
|---|---|
| Site: | Surry |
| Issue date: | 05/10/1979 |
| From: | Sutherland J NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | Proffitt W VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.) |
| Shared Package | |
| ML18116A147 | List: |
| References | |
| NUDOCS 7907180679 | |
| Download: ML18116A149 (2) | |
See also: IR 05000280/1979018
Text
-
- , #_
'......J.....=:~ ....... , .. _ ***-** .. -.
- -~~-*--~*~**--'-~--* *---*~-. "-***-**
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION II
101 MARIETTASTREET,N.W.
ATLANTA, GEORGIA 30303
MAY 10 1979
In Reply Refer To:
RII:CMH
50-280/79-18
50-281/79-26
Virginia Electric and Power Company
ATTN:
W. L. Proffitt
Senior Vice President, Power
P. 0. Box 26666
Richmond, VA 23261
Gentlemen:
This refers to the inspection conducted by C. M. Hosey of this office on
April 9-13, 1979, of activities authorized by NRC Operating License Nos.
DPR-32 and DPR-37 for the Surry Power Station, Unit 1 and 2 facilities, and
to the discussion of our findings held with J. L. Wilson at the conclusion
of the inspection.
Areas examined during the inspection and our findings are discussed in the
enclosed inspection report.
Within these areas, the inspection consisted
of selective examinations of procedures and representative records, interviews
with personnel, and observations by the inspect?r.
One new unresolved item resulted from this inspection and is discussed in
the enclosed report. This i tern will be examined during subsequent inspections.
During the inspection, it was found that certain activities under your
license appear to be in noncompliance with NRC requirements.
These items
and references to pertinent requirements are listed in the Notice of Violation
enclosed herewith as Appendix A.
This notice is sent to you pursuant to
the provisions of Section 2.201 of the NRC's "Rules of Practice," Part 2,
Title 10, Code of Federal Regulations.
Section 2. 201 requires you to
submit to this office, within 20 days of your receipt of this notice, a
written statement or explanation in reply including:
(1) corrective steps
which have been taken by you and the results achieved; (2) corrective steps
which will be taken to avoid further noncompliance; and (3) the date when
full compliance will be achieved.
In accordance with Section 2.790 of the NRC's "Rules of Practice," Part 2,
Title 10, Code of Federal Regulations, a copy of this letter and the enclosed~ I:"')
inspection report will be placed in the NRC' s Public Document Room.
If ~-...,
this report contains any information that you (or your contractor) believe
to be proprietary, it is necessary that you make a written application
~
. ~s.-------------.. -~- -- .... ---------~-
.. --.--.. -------..- -~---*-*-* -.'\\*---~------- *-**
~ ---~-----;-~--------:----------------
.'
- .'*
.
- ---0 *. -,..: * ..:. ___ ~.--..( .* ,-----*
..... ~---*--____,_.._..**"--*'** S'>"'--
- ~ ..... *-*.,:.~,.._.,*., -~~ ,.,._,,.._* . ..._,.
- **** .. -
-
- .,
.. *
\\ .
(
MAY 1 0 1979
Virginia Electric and Power Co.
-2-
within 20 days to this office to withhold such information from public
disclosure.
Any such application must include a full statement of the
reasons on the basis of which it is claimed that the information is proprie-
tary, and should be prepared so that proprietary information identified in
the application is contained in a separate part of the document. If we do
not hear from you in this regard within the specified period, the report
will be placed in the Public Document Room.
Should you have any questions concerning this letter, we will be glad to
discuss them with you.
Enclosures:
Sincerely,
dV:~h~
~- *T. Sutherland, Chief
Fuel Facility and Materials
Safety Branch
1.
Appendix A, Notice of Violation
2.
Inspection Report Nos. 50-280/79-18
and 50-281/79-26
cc w/encl:
W. L. Stewart, Manager
P. 0. Box 315
Surry, VA
23883
"' *---.. -* *-*-**-- ---.....-------