iivI ~v 1978 Docket Nos. +~~0-401, 50-402 and 50-403 Mr. J. A. Jones ExecutiveVice President - Engineeri Construction and Operations Carolina Power 8 Light Company 336 Fayetteville Street

Raleigh, North Carolina 27602

Dear Mr. Jones:

"Distribution NRC PDR Local PDR Docket Fi LWR ¹3 File R.

Boyd D. Vassallo F. Williams

0. Parr S. Miner.

M. Rushbrook R. Mattson ng D.

Ross J.

Knight R. Tedesco R.

DeYoung V. Moore R. Vollmer M. Ernst w/encl.osure R.'enise ELD IE (3)

(w/extra copies)

BCC:

NSIC TIC ACRS (16)

SUBJECT:

SHEARON HARRIS NUCLEAR POWER PLANT UNITS 1, 2, 3 AND 4 -

REQUEST FOR,ADDITIONAL INFORMATION ON SITE GEOLOGY By letter dated October 17 1978, you provided a report on the geologic feature at station 2+50 of the divhrsion conduct excavation.

tie have reviewed the report and.find that we require additional information.

The specific information required is lisked in the gnclosure.

Please inform us of -the date when this;r>equested additional information will be available for our review.

Please contact us if you desire any discussion or clarification of the information requested.

Enclosure:

As stated Sincqrely, 0~g'j~R] Sigllclib$ >

lan PRE2 lan D. Parr, Chief Light Water Reactors Branch No.

3 Division of Project Management cc w/enclosure:

See next page ORCICC~

ODRMAMCW DATd~

LWR ¹3.:q'ra

'SMi ner:

I'1'/Qj

/78" g@

¹3:BC OParr 11/~

/78

~

~

~

0 ~ I

~ ~

~ ~

~

NRC EORM 518 (9.76) NRCM 0240 4 V,S. OOVCRNMCNT I'RINTINO ONPICC I I ~ t ~

SSS 1 ~ S

4e.

4t

~

Wg kg

Mr. J.

A. Jones cc:

George F. Trowbridge, Esq.

Shaw, Pittman, Potts, Trowbridge 5 Madden 1800 M Street, N.

W.

Washington, D.

C.

20036 Richard E. Jones, Esq.

Carolina Power E Light Company 336 Fayetteville Street

Raleigh, North Carolina 27602 Thomas S. Erwin, Esq 115 W. Morgan Street
Raleigh, North Carolina 27602 Jesse C. Brake, Esq.

Associate Attorney General State of North Carolina P. 0.

Box 629

Raleigh, North Carolina 27602 Alan S. Rosenthal, Esq.,

Chairman Atomic Safety and Licensing Appeal Board U. S. Nuclear Regulatory Commission Washington, D.'C.

20555 Michael C. Farrar, Esq.

Atomic Safety and Licensing Appeal Board U. S. Nuclear Regulatory Commission Washington, D. C.

20555 Dr. John H. Buck Atomic Safety and Licensing Appeal Board U. S. Nuclear Regulatory Commission Washington, D.

C.

20555

ENCLOSURE 00 0

0>>

0 0

0 SHEARON HARRIS NUCLEAR POWER PLANT UNITS 1

2, 3 AND 4 DOCKET NOS.

50-400

. 50-401, 50-402 AND 50-403

Geosciences Branch - Geolo We agree that the evidence supports your conclusion that the schistose zone at station 2+50 of the diversion conduit excava-tion resulted from deformation which occurred over 225 million years ago.

However, sufficient data have not been provided to support your further conclusion that these zones cannot be described as capable faults.

In particular, the schistone zone-granite contact at station 2+55. is mapped as a planar contact'hich strongly suggests a fault contact due to possible reacti-vated movement along this zone.

In order to better identify and date the planar feature provide information which demonstrates that no movement has occurred along this contact or if offset has occurred, demonstrate its age of last movement.

At a minimum, provide data such as a thin-section study across the planar contact which identifies key minerals, their time of deposition, and their last period of deformation.

In addi tion, a'fold analysis across the planar contact would be extremely useful in making such a demonstration.

4,