ML18114A721

From kanterella
Jump to navigation Jump to search
Forwards IE Insp Rept 50-281/79-14 on 790306-09 & Notice of Violation
ML18114A721
Person / Time
Site: Surry Dominion icon.png
Issue date: 03/30/1979
From: Murphy C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Proffitt W
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
Shared Package
ML18114A722 List:
References
NUDOCS 7906250137
Download: ML18114A721 (7)


See also: IR 05000281/1979014

Text

. **

(

(

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTASTREET,N.W.

ATLANTA, GEORGIA 30303

MAR 3 0 1979

In Reply Refer To:

l

RII :JDW

S0-1281/79-14

'

Virginia Electric and Power Company

Attn:

Mr. W. L. Proffitt

Senior Vice President, Power Operations

Post Office Box 26666

Richmond, Virginia

23261

Gentlemen:

This refers to the inspection conducted by Mr. J. D. Wilcox, Jr. of this

office on March 6-9, 1979 of activities authorized by NRC Operating

License No. DPR-37 for the Surry Power Station facility, Unit No. 2, and

to the discussion of our findings held with Mr. W. L. Stewart at the

conclusion of the inspection.

Areas examined during the inspection and our findings are discussed in

the enclosed inspection report.

Within these areas, the inspection

consisted of selective examinations of procedures and representative

records, interviews with personnel, and observations by the inspector.

We have examined actions you have taken with regard to previously reported

unresolved items.

The status of these items is discussed in the enclosed

report.

During the inspection, it was found that certain activities under your

license appear to be in noncompliance with NRC requirements.

This item

and references to pertinent requirements are listed in the Notice of

Violation enclosed herewith as Appendix A.

This notice is sent to you

pursuant to the provisions of Section 2.201 of the NRC's "Rules of

Practice", Part 2, Title 10, Code of Federal Regulations.

Section 2.201

requires you to submit to this office, within *20-days of your receipt of

this notice, a written statement or explanation in reply including:

(1)

corrective steps which have been taken by you, and the results achieved;

(2) corrective steps which will be taken to avoid further noncompliance;

and (3) the date when full compliance will be achieved.

In accordance with Section 2.790 of the NRC's "Rules of Practice,"

Part 2, Title 10, Code of Federal Regulations, a copy of this letter and

the enclosed inspection report will be placed in the NRC's Public Documf'nt

Room.

If this report contains any information that you (or your contractor)

believe to be proprietary, it is necessary that you make a written

application within 20 days to this office.to withhold such information

from public disclosure.

Any such application must include a full statemenl::S:p

of the reasons on the basis of which it is claimed that the information

(.

Virginia Electric and

Power Company

-2-

(

MAR 3 0 1979

is proprietary, and should be prepared so that proprietary information

identified in the application is contained in a separate part 1of the

I document.

If we do not hear from you in this regard within ~tt= specified

1 period, the report will be placed in the Public Docwnent Rooin.J

.

Should you have any questions concerning this letter, we will be glad to

discuss them with you.

Enclosures:

Sincerely,

cc/:/;;,.J-,1

Charles E. ~~y, Cp{ef

Reactor Construction and

Engineering Support Section

1.

Appendix A, Notice of Violation

2.

Inspection Report No. 50-281/79-14

cc w/enclosures:

Mr. W. 1: Stewart

Station Manager

Surry Power Station

Post Office Box 315

Surry, Virginia 23883

(

APPENDIX A

NOTICE OF VIOLATION

Virginia Electric and Power Co.

C

f Surry Nuclear Plant, Unit 2

Based on the NRC inspection March 6-9, 1979, certain of your activities

were apparently not conducted in full compliance with NRC requirements as

indicated below.

These items have been categorized as described* in corre-

spondence to you dated December 31, 1974.

As required by 10 CFR, Part 50, Appendix B, Criterion XVII, as imple-

mented by VEPCO's licensing submittal (Steam Generator Project, Surry

Power Station Units Nos. 1 and 2 - Revision 9). "Sufficient records

shall be maintained to furnish evidence of activities affecting quality

Inspection and test records shall, as a minimum, identify the

inspector or data recorder, the type of observation, the results; the

acceptability, and the action taken in connection with any dificiencies

noted.

Records sha11 be identifiable and retrievable".

Westinghouse

Process Specifications NPT-91 and 94 require that the monitoring

schedules for nitrogen pressure gage readings of primary and secondary

sides to the steam generator lower assemblies shall be documented.

Contrary to the above, on March 8, 1979, the S. G. Lower assemblies

identified as f/2927, #2973 and #2981 had no official records for

nitrogen pressure gage readings.

This is a deficiency.

(

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTA STREET, N.W.

ATLANTA, GEORGIA 30303

f Report No. 50-281/79-14

I

Licensee: Virginia Electric and Power Company

P. 0. Box 26666

Richmond, Virginia 23261

Facility Name:

Surry Power Station, Unit 2

Docket No. 50-281

License No. DPR-37 *

Inspection at Surry Site near Williamsburg, Virginia

'JD * **') C7

Inspector~ d'-;__,.. ~' ~

J. D. Wi cox, Jr.

~s

I

'

App roved by :

1

...,.'* .:!::>f-:=...e:~

1

..::l.~l__..i---=(=-j_, ~-1'-l""'=~~-===-=--:::----,------

A.

RC&ES Branch

SUMMARY

Inspection on March 6-9i 1979

Areas Inspected

Dat7e Si'gned

This routine, unannounced inspection involved 28 inspector-hours onsite in

the areas of construction status pertaining to the steam generator replacement

(SGRP) for Surry Power Station storage of new steam generator lower units,

follow-up on previous identified unresolved item, QA Audit Revie .... * ,. and

observation of safety-related work activities.

Results

Of the five areas inspected, no apparent items of noncompliance or deviations

were identified in four areas.

One apparent i tern of noncompliance ...-as

.found in one area (deficiency - Inadequate records - Nitrogen Purge S. G. Lo~er

Assembly - paragraph 6) .

! :

(

(

\\... ....

DETAILS

!.

Persons Contacted

Licensee Employees

A.

  • J.
'
J.

'i':T.

  • R.

L. Parrish, III, Project Manager SGRP

W. Patrick, VEPCO

L. Wilson, Station Operations Superintendent

A. Peebles, Technical Services Superintendent

M. Smith, H. P. Supervisor

  • R.
  • E.

L. Baldwin, VEPCO, Supervisor, Administrative Services

P. DeWandel, Administrative Assistant

  • F. L. Rentz, Resident QC Engineer
  • P. P. Nottingham, H. P. Coordinator, SGRP
  • C. W. Rhodes, Resident Engineer Construction SGRP

.,':y.

  • R.

P. Mangum, Jr., Resident Engineer Project Control SGRP

E. Titone, Engineering Technician

,',M. D. Tower, VEPCO (Corporate QA)

~*:s. Sarver, VEPCO (Corporate HP)

Other licensee employees contacted during this inspection included 4

construction craftsmen, 4 technicians, l security force member, and 3

office personnel.

NRC Resident Inspector

  • D. J. Burke

'l':Attended exit interview.

2.

Exit Interview

The inspection scope and findings were summarized on

with those persons indicated in Paragraph 1 above.

sununarized the scope of the inspection as follows:

status, QA Audit Review, Review of Previous Identified

ind Observation of safety-related work activities.

3.

Licensee Action on Previous Inspection Findings

March 9, 1979

The inspector

Construction

Unresolved Item

(Closed) Unresolved Item (280-281/79-04-0l) "ASME Code Requirements"

Per concurring telcon conversation from D. Neighbors (NRR) to J. D. ~ilcox.

Jr.

(IE:RII), the intent of Paragraph 2.3 of the Safety Evaluation

Report (SER) under "ASHE Code and Regulatory Guide Implementation is

  • the following: All piping weld end preps, welding, and nondestructive

examination will be in accordance with the 1974 Edition of the ASME

I

~

I

4.

(

\\.. .....

(

-2-

Code, including addenda through Winter 1976.

Therefore, the S.E.R.

agrees with VEPCO's submittal (Steam Generator Project,1Surry Power

Station Units Nos. 1 and 2, Revision 9) to NRR dated Au!:st 1977 for

the Surry Steam Generator Replacement (SGRP) pertaining to the ASME

Code Requirements. This item is closed.

Unresolved Items

Unresolved items were not identified during this inspection.

5.

Independent Inspection Effort

a.

Construction Status

b.

The biological shield walls are being removed from around the

steam generators of the Unit 2 Reactor Building. Installation of

Crane Wall jib cranes and monorail transport system are being

accomplished.

Containment floor and crane wall modifications are

also in progress.

The new steam generator lower assemblies are

being stored near the unloading dock on the James River in VEPCO's

construction security area.

Quality Assurance Audit

The inspector examined the following QA audit conducted by the

site VEPCO's QA unit for completeness, deficiencies found, correc-

tive action taken, timeliness and implementation taken.

Audit Number

Subject

SGRP 78-1

Tesi and Measuring Equipment

The audit reviewed was found to be conducted and documented in a

thorough, timely and objective manner.

No items of noncompliance or deviations were identified in the

above area. inspected.

c.

Observation of Safety-Related Work Activities

The following safety-related work was observed by the inspector

during the course of the inspection:

(1)

Preparation for installation of Crane wall jib cranes

(2)

Preparation for modification of Crane wall

I

6.

(3)

(4)

( ___ _

(__ __

-3-

Preparation for removal of instrumentation, feedwater and

mainsteam piping from Steam Generators "A", "B'f and "C".

Preparation for cutting reactor coolant pipiJg for Steam

Generator "C"

No items of noncompliance or deviations were ident:i.fied in the

above areas inspected.

Storage of Steam Generator Lower Assemblies

The inspector observed the storage of four (4) steam generator lower

assemblies.

The lower assemblies are located near a unloading dock on

the James River in VEPCO' s construction security area.

The lower

assemblies were checked to ensure proper nitrogen purges were being

maintained as required by Westinghouse Process Specification NPT 91,

"Protective measures for long term storage of steam generator lower

assemblies" and NPT 94, "Protective measures for short term storage of

steam generator lower assemblies".

Paragraph 4. 0 of these process

specifications contain the following requirements:

The following

monitoring schedules for nitrogen pressure gage readings of primary

and secondary sides of the steam generator lower assemblies shall be

documented. The monitoring of the site storage will be to take pressure

gage readings daily for the first three days at the plant site. Also

take readings daily for the first three days after any handling of the

generator at the plant site. Thereafter, take pressure gage readings

every two weeks until the nitrogen charge is intentionally released

for installation into the nuclear steam supply system.

On March 8,

1979, the inspector observed that inadequate records were being main-

tained for monitoring pressure gage reading of primary and secondary

sides of three (3) lower assemblies (identified as #2972, #2973, and

  1. 2981). It should be noted that the primary side of lower assembly

identified as #t971 is presently having nozzles re endprepped; therefore,

a.purge is not being maintained on the primary side of this generator

assembly.

This is in noncompliance with 10 CFR 50, Appendix B*, Cri-

terion XVII as implemented by the VEPCO's licensing submittal (Steam

Generator Project, Surry Power Station Units Nos. 1 and 2 - Revision 9)

to the Steam Generator Project.

This is identified as deficiency

  • 281/79-14-01 "Inadequate Records - Nitrogen Purge S. G. Lower Assembly".

No other items of noncompliance or deviations were identified.