IVlr. Leon R. Eliason Chief Nuclear Officer & President-Nuclear Business Unit Public Service Electric and Gas Company Post Office Box 236 Hancocks Bridge, NJ 08038 October 5.95
SUBJECT:
NON-EMERGENCY EVENT NOTIFICATION, 10 CFR 50.72, SALEM NUCLEAR GENERATING STATION, UNITS 1 AND 2, AND HOPE CREEK GENERATING STATION
{TAC NOS. M93350, M93351 AND M93352)
Dear Mr. Eliason:
In a letter dated August 25, 1995, you requested relief from the 4-hour notification requirements of 10 CFR 50.72(b)(2)(vi). Specifically, you requested relief from reporting minor exceedances of the New Jersey opacity standards for diesel generators and auxiliary boiler, and minor exceedances of the New Jersey Pollutant Discharge Elimination System permit effluent limitations for conventional, non-toxic pollutants, such as residual chlorine, suspended solids, temperature and sewage limits.
The request is similar to your September 2, 1992, letter regarding minor non-radioactive chemical spills.
In our October 19, 1992, letter we determined that such spills need not be reported under Section 50.72(b)(2)(vi),
consistent with guidance in a draft of NUREG-1022.
Therefore, consistent with the advice which we previously provided in 1992, our interim position on your most recent request is that until a final revision to NUREG-1022 has been issued, these two exceedances of State limits need not be reported to the NRC under Section 50.72(b)(2)(vi).
However, as stated in our October 19, 1992 letter, when the final revision to NUREG-1022 is published, you must verify the*staff's final position, and determine whether a request for relief is appropriate at that time.
Our interim advice on this matter does not constitute a staff position for purposes of the Backfit Rule, 10 CFR 50.109.
Docket Nos. 50-272, 50-311 and 50-354 cc:
See next page
- See previous concurrence Sincerely,
/SI Leonard Olshan, Senior Project Manager Project Directorate I-2 Division of Reactor Projects - I/II Office of Nuclear Reactor Regulation DISTRIBUTION; Docket File PUBLIC PDI-2 Reading SVarga JZwolinski MO' Brien LOl sh an OGC ACRS(4)
JWhite, RGN-I DJaffe
/ll?tJ f).e; I=
OFFICE DI-2/PM OGC*
PDI-2/
DATE OFFICIAL RECORD COPY DOCUMENT NAME:
SAM9335.LTR 9510100032 951005 PDR ADOCK 05000272 P
PDR 9/19/95 10 I ~/95
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 October 5, 1995
SUBJECT:
NON-EMERGENCY EVENT NOTIFICATION, 10 CFR 50.72, SALEM NUCLEAR GENERATING STATION, UNITS 1 AND 2, AND HOPE CREEK GENERATING STATION (TAC NOS. M93350, M93351 AND M93352}
Dear Mr. Eliason:
In a letter dated August 25, 1995, you requested relief from the 4-hour notification requirements of 10 CFR 50.72(b}(2}(vi}.
Specifically~ you requested relief from reporting minor exceedances of the New Jersey opacity standards for diesel generators and auxiliary boiler, and minor exceedances of the New Jersey Pollutant Discharge Elimination System permit effluent limitations for conventional, non-toxic pollutants, such as residual chlorine, suspended solids, temperature and sewage limits.
The request is similar to your September 2, 1992, letter regarding minor non-radioactive chemical spills.
In our October 19, 1992, letter we determined that such spills need not be reported under Section 50.72(b}(2}(vi},
consistent with guidance in a draft of NUREG-1022.
Therefore, consistent with the advice which we previously provided in 1992, our interim position on your most recent request is that until a final revision to NUREG-1022 has been issued, these two exceedances of State limits need not be reported to the NRC under Section 50.72(b}(2}(vi}.
However, as stated in our October 19, 1992 letter, when the final revision to NUREG-1022 is published, you must verify the staff's final position, and determine whether a request for relief is appropriate at that time.
Our interim advice on this matter does not constitute a staff position for purposes of the Backfit Rule, 10 CFR 50.109.
Docket Nos. 50-272, 50-311 and 50-354 cc:
See next page Sincerely, f.Dad~
Leonard Olshan, Senior Project Manager Project Directorate I-2 Division of Reactor Projects - I/II Office of Nuclear Reactor Regulation
Mr. Leon R. Eliason Public Service Electric & Gas Company cc:
Mark J. Wetterhahn, Esquire Winston & Strawn 1400 L Street NW Washington, DC 20005-3502 Richard Fryling, Jr., Esquire Law Department - Tower SE 80 Park Place Newark, NJ 07101 Mr. John Summers General Manager - Salem Operations Salem Generating Station P.O. Box 236 Hancocks Bridge, NJ 08038 Mr. J. Hagan Vice President - Nuclear Operations Nuclear Department P.O. Box 236 Hancocks Bridge, New Jersey 08038 Mr. Charles S. Marschall, Senior Resident Inspector Salem Generating Station U.S. Nuclear Regulatory Commission Drawer 0509 Hancocks Bridge, NJ 08038 Dr. Jill Lipoti, Asst. Director Radiation Protection Programs NJ Department of Environmental Protection and Energy CN 415 Trenton, NJ 08625-0415 Maryland Office of People's Counsel 6 St. Paul Street, 21st Fl oar Suite 2102 Baltimore, Maryland 21202 Ms. R. A. Kankus Joint Owner Affairs PECO Energy Company 965 Chesterbrook Bl~d., 63C-5 Wayne, PA 19087 Salem Nuclear Generating Station, Units I and 2, and Hope Creek Generating Station Richard Hartung Electric Service Evaluation Board of Regulatory Commissioners 2 Gateway Center, Tenth Floor Newark, NJ 07102 Regional Administrator, Region I U. S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Lower Alloways Creek Township c/o Mary 0. Henderson, Clerk Municipal Building, P.O. Box 157 Hancocks Bridge, NJ 08038 Mr. Frank X. Thomson, Jr., Manager Licensing and Regulation Nuclear Department P.O. Box 236 Hancocks Bridge, NJ 08038 Mr. David Wersan Assistant Consumer Advocate Office of Consumer Advocate
- 1425 Strawberry Square Harrisburg, PA 17120 Ms. P. J. Curham MGR. Joint Generation Department Atlantic Electric Company P.O. Box 1500 6801 Black Horse Pike Pleasantville, NJ 08232 Carl D. Schaefer External Operations - Nuclear Delmarva Power & Light Company P.O. Box 231 Wilmington, DE 19899 Public Service Commission of Maryland Engineering Division Chief Engineer 6 St. Paul Centre Baltimore, MD 21202-6806
[
I Mr. Leon R. Eliason Public Service Electric & Gas Company Hope Creek Resident Inspector U.S. Nuclear Regulatory Commission Drawer 0509 Hancocks Bridge, New Jersey 08038 Mr. M. Reddemann General Manager - Hope Creek Operations Hope Creek Generating Station P.O. Box 236 Hancocks Bridge, New Jersey 08038
- Salem Nuclear Generating Station, Unit 1 and 2, and Hope Creek Generating Station Mr. S. LaBruna Vice President - Nuclear Engineering Nuclear Department P.O. Box 236 Hancocks Bridge, New Jersey 08038