ML18100A541
| ML18100A541 | |
| Person / Time | |
|---|---|
| Site: | Salem |
| Issue date: | 08/11/1993 |
| From: | Hodges M NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
| To: | Miltenberger S Public Service Enterprise Group |
| References | |
| NUDOCS 9308170146 | |
| Download: ML18100A541 (56) | |
See also: IR 05000272/1993081
Text
'
Docket Nos. 50-272
50-311
Mr. Steven E. Miltenberger
Vice President and Chief Nuclear Officer
Public Service Electric and Gas Company
P.O. Box 236
Hancocks Bridge, NJ 08038
Dear Mr. Miltenberger:
AUG 11 1993
SUBJECT:
SALEM MANAGEMENT MEETING
On July 18, 1993, a management meeting was held with you and other representatives of
Public Service Electric and Gas and the staff of the NRC. The topic discussed at the
meeting was the numerous rod control system failures which occurred during May and
June 1993, and were the subject of an Augmented Team Inspection. Enclosed is a list of the
meeting attendees [Enclosure 1]. Also enclosed are the handouts you provided at the meeting
[Enclosure 2].
During the meeting, your presentation included: 1) a technical assessment of the rod control
system malfunctions and their causes, 2) a safety assessment of the malfunctions, 3) the
assessment provided by your Significant Event Response Team, and 4) corrective actions
taken as a result of these malfunctions.
The NRC Augmented Inspection Team performed an independent review of the rod control
system problems and the results of this inspection are documented in NRC Combined
Inspection Report 50-272/93-81; 50-311/93-81.
In accordance with 10 CFR 2.790 of the NRC's "Rules of Practice," its enclosures will be
placed in the NRC Public Document Room. No reply to this letter is required .
9308170146
- PDR
ADOCK
G
930811
05000272
OFFICIAL RECORD COPY
A:SALEMMTG.618
Mr. Steven E. Miltenberger
2
AUG 11 1993
Your cooperation with us is appreciated.
Enclosures:
Sincerely,
Original Signed By.
Marvin W. Hodges
Marvin W. Hodges, Director
Division of Reactor Safety
1. PS&EG Management Meeting List of Attendees, July 18, 1993
2. PSE&G Meeting Handouts
cc w/encls:
J. J. Hagan, Vice President, Nuclear Operations
C. Schaefer, External Operations - Nuclear, Delmarva Power & Light Co.
C. Vondra, General Manager - Salem Operations
R. Hovey, General Manager - Hope Creek Operations
F. Thomson, Manager, Licensing and Regulation
R. Swanson, General Manager - QA and Nuclear Safety Review
J. Robb, Director, Joint Owner Affairs
A. Tapert, Program Administrator
R. Fryling, Jr., Esquire
M. Wetterhahn, Esquire
J. Isabella, Director, Generation Projects Department,
Atlantic Electric Company
Consumer Advocate, Office of Consumer Advocate
William Conklin, Public Safety Consultant, Lower Alloways Creek Township
K. Abraham, PAO (2)
Public Document Room (PDR)
Local Public Document Room (LPDR)
Nuclear Safety Information Center (NSIC)
NRC Resident Inspector
State of New Jersey
OFFICIAL RECORD COPY
A:SALEMMTG.618
/
Mr. Steven E. Miltenberger
bee w/encls:
Region I Docket Room (with concurrences)
DRS Files (2)
bee w/o encls: (Via E-Mail)
R. Cooper, DRP
J. Durr, DRS
C. Miller, DRS
E. Wenzinger, DRP
J. White, DRP
J. Stone, NRR
D. Wheeler, OEDO
M. Boyle, PDI-2, NRR
T. Martin, RA
W. Kane, DRA
RI:DRS
Sc~gcb
RI: DRS
3
1;y193
~ ~/fc,/93
AUG 111993
-RI:DRS
H~~
tf///93
OFFICIAL RECORD COPY
A:SALEMMTG.618
PSE&G:
S. Miltenberger
S. La Bruna
J. Hagan
C. Vondra
F. Thomson
W. Stewart
L. Miller
L. Rajkowski
E. Robinson
T. Ross
D. Best
H. Onorato
NRC:
T. Martin
W. Kane
R. Cooper
E. Imbro
E. Wenzinger
J. White
B. McDermott
W. Maier
T. Johnson
S.Barr
H.Garg
D. Screnci
J. Stone
P. Patniak
R. Skokowski
W. Ruland
L. Scholl
M. La7.arowitz
J. Calvo
ENCWSURE1
LIST OF ATTENDEFS
Vice President and Chief Nuclear Officer
Vice President - Nuclear Engineering
Vice President - Nuclear Operations
General Manager - Salem
Manager - Licensing and Regulation
Media Relations Representative
General Manager - Nuclear Operations Support
Supervising Engineer - Instrumentation and Controls
Principal Training Supervisor
Senior Staff Engineer
Systems Engineer
Licensing Engineer
Regional Administrator
Deputy Regional Administrator
Director, Division of Radiation Safety and Safeguards
Deputy Director, Division of Reactor Safety
Chief, Projects Branch 2, DRP
Chief, Reactor Projects Section 2A, DRP
Reactor Engineer, DRP
Operations Engineer, DRS
Senior Resident Inspector, DRP
Resident Inspector, DRP
Senior Electrical Engineer, NRR
Public Affairs Officer, ORA
Salem Project Manager, NRR
Reactor Inspector, DRS
Reactor Engineer, DRS
Chief, Electrical Section, DRS
Reactor Engineer, DRP
Reactor Engineer, DRS
Assistant Director for Region I Reactors, NRR
Enclosure 1
Other Organizations
R. Oakes
P. Duca
T. Robb
M. Beaumont
P. Milford
2
Salem Site Representative - Atlantic Electric
Salem Site Representative - Delmarva Power
Director - Joint Owners Affairs
Manager - Rockville Licensing (Westinghouse)
Reporter - Wilmington News Journal
-
ENCLOSURE2
-ps~G
Public service
8
Electric and Gas
Company
SALEM UNIT 2
ROD CONTROL SYSTEM
JUNE 18, 1993
SALEM
GENERA TING STATION
-
D
e
I * * I
111 II *
II 111 I
fl_.
..
SALEM UNIT 2
ROD CONTROL SYSTEM
AGENDA
INTRODUCTION
S. E. MILTENBERGER
MEETING OBJECTIVES
S. E. MILTENBERGER
CURRENT PLANT STATUS
S. E. MILTENBERGER
SYSTEM OVERVIEW
D.BEST
CHRONOLOGICAL SUMMARY
C.A.VONDRA
TECHNICAL ASSESSMENT OF
L. J. RAJKOWSKI
MALFUNCTIONS
SAFETY ASSESSMENT
F. X. THOMSON
SERT ASSESSMENT
L. K. MILLER
CORRECTIVE MEASURES
C.A.VONDRA
CONCLUSIONS
S. E. MILTENBERGER
e tf
SALEM UNIT 2
ROD CONTROL SYSTEM
MEETING OBJECTIVES
e PROVIDE THE RESULTS OF PSE&G'S ASSESSMENT OF THE
ROD CONTROL SYSTEM MALFUNCTIONS
e IDENTIFY CORRECTIVE MEASURES
e PROVIDE ASSURANCE FOR CONTINUED SAFE OPERATION
OF UNIT 2
e OBTAIN CONCURRENCE FOR ACTIONS NEEDED TO CLOSE
OUT CONFIRMATORY ACTION LETTER
e *.
SALEM UNIT 2
ROD CONTROL SYSTEM
CURRENT PLANT STATUS
SALEM UNIT 1
- MODE 3
e NORMAL OPERATING TEMPERATURE AND PRESSURE
e RCS - DIODE SUPPRESSION DCP INSTALLED FOR ALL
GROUP COUNTERS
SALEM UNIT 2
- MODE3
- NORMAL OPERATING TEMPERATURE AND PRESSURE
e UNIT ON HOLD FOR STARTUP PENDING:
- RCS LOGIC CABINET CARD REPLACEMENT
e COMPLETION OF SHORT TERM CORRECTIVE ACTIONS
.r
SALEM UNIT 2
ROD CONTROL SYSTEM
SYSTEM OVERVIEW
- PURPOSE
- POSITION CONTROL RODS IN.RESPONSE TO DEMANDS
FOR MOTION FROM EITHER THE REACTOR OPERATOR
OR THE ROD CONTROL SYSTEM
e INTERFACES
- CONTROL BOARD
- PROCESS CONTROL
e BLOCK DIAGRAM
- LOGIC CABINET
- POWER CABINET
- DC HOLD CABINET
- ROD GROUP ARRANGEMENT
e LOGIC CABINET BLOCK DIAGRAM
- SYSTEM OPERATION
- CROM
e CURRENT TRACES
..*
~
-
- *
..
SYSTEM INTERFACE BLOCK DIAGRAM
Panel
-
-
\\~ \\
Co~trol /
/
\\
Board
~ 0
~
Soeed-
Direction
RIL
Alarm
~ '
TH
---
Alanna
-
--
Logic
Cabinet
0
'
Group
Step a
Current
Commands
Group
Select
Bank
Steps
Alarms
4-
~ ,
Plant Computer *
Tc
- ' ' '
Proceaa
Pimp ...
Rack
Control
Bank Steps
NIS-
j *
a*nana.002
--
..
--
Power Cabinet
( 1 of 5)
D
' '
j l
I
I
-
Hold
Cabinet
CROM
Litt
Current
Movable
..::..
Current -
Stationary
Current
I
- - - - -
Control
P-A
Converter ~ Bank
i-.----
voe
..
..
BASIC SYSTEM BLOCK DIAGRAM
'~* .
480VAC =:
60HZ
f1c
Speed
and
Direction
228l23111.001
Motor
BKRS
Logic
Cabinet
D
Motor
Generator
( 1 of 2)
Gen
BKRS
Main 120VAC
Current Commands
Group Select
260 VAC
Reactor
Trip Bkrs
Power Cabinet
( 1 of 5)
D
CROM
Reactor
Protection
Trip Signals
Lift
Current
Movable
Current
I..____.._ ____________ ~ ' '
Auxiliary
120VAC
260VAC 3/J
Hold
Cabinet
- - -
Control
P-A
L--~~~---t~ Converter
Bank Steps
- - -
125 voe
or
10 voe
Stationary
Current
Control
Bank voe
"l . *
~
ROD CONTRO*L SYSTEM
Bl°'* Qlaaram
Current
Power Cabinet
1AC
Bank Selector r---1
Logic
Cabinet
I
Command
Group
I I
- Gr 1, CA (2)(4)
~ar 1, cc t*>
---*Gr 1, SA (4)
Rod Out
--
siO.,
Current
Command
Swhch
- Out
.-----. ~= :
I
- I I
I
In .
I
~= I
I 0Ho1c11
I Auto...
I I -
I
L..-. *--' ~.na---t,~ ... --....
L---.J
I Current
Command
I
-
Control Bo*rd
Auto In
a..;.;A*u-lo;,,.;Ouiiiiiiiimiiit __ R-1:1!
Speed
Stoo
I
I
.. -..
. . -
... _.,... __ ,...
I **--
Speed
- -
Current
Command
Current
.......... -- Command
~ I
Individual
Bank
Select
u 1 Bank Selector Switch
---
Proce** Rack
- MAN, CA, CB, CC, or CD Position
Select
PowerCab~et2AC *
Group
Select
I
I I
-.ar 2, CA (2)(4)
- Gr 2, CC (4)
---*Gr 2 1 SA (4)
Power Cabinet 180
Group
I I
-.ar 1. ce (4)(2)
Select
- Gr I, CD(*)
I
_ __.__.--Gr I, SB (4)
Power Cabinet 280
I
Oroup
Select
- Or 2. CB (4)(2)
I I
,..Gr 2. co (5)
~Or 2, SB (4)
---
Power Cabinet SCD
I
Group
Select
I I
.. sc (4)
ROD CONTROL SYSTEM
LOGIC CABINET BLOCK DIAGRAM
M81ftAC'"-
1120 VAC _, HZI
Awl .....
AC'"-
,,..,._,---~~L!!!!!!.!~~--1-~
-llllll
, ............ ~......::.:.:~==:w:.:=====-~--1:::=~ ..... ,.,....~~-1
1* t002-t211. t/T23'71.024
.....
c.-r
IA.U
..................
OOIAC
OOllO
-
}*~OI
a;;.;.;;:;..;;;.;=~ ao.d
Tof'IMI
~
JoPIA
eon....
10280
p-
CllblMI
CONTROL ROD DRIVE MECHANISM
(~
\\ ""' ~
Rod Trave1~m
Housing
~;;
- ~
.
I
Disconnect
Button
Pressure Vessel
Housing Assembly
Stationary Gripper--..
Coil Stack
- - ..
. ..._."
I
I
. _ ___,
~
~
Electrical
Lead Tube
Movable Gripper
Latch Assembly
Stationary Gripper
Latch Assembly
--Connection to
RCCA Spider
Assembly
LATCHING
1
.
- '*'{~
MECHANISM
~.:
Lift Coil
Movable
Coll
Flux Ring
Stationary
Coll
Drive Rod
' 'f IWlll9fW* I
Guide Tube
Lift Pole
Flux Ring
Lift Armature
Movable Gripper
Movable Gripper
Armature
(Shown Open)
Stationary
Pole
Stationary
Gripper
Armature
Stationary Gripper
- *
..
, Normal Oscillograph Trace
Lill Pole
Closed
I
MG Pole Closed & --11-...
MG Laich In
Lo*d Transfer
SG Pole Open &
SQ l*lch Out
Lill Pole Open
SG Pole Closed &
SG Latch In
MG Pole Open &
MG Laich Oul
Lill Pole
Closed
g
>
3 1 i
~
r
C>
>
>
3
3
1
-0 ..
...
...
I
II
--Hold-
MG Pole Closed &
MG Latch In
Load Transler
SG Pole Closed &
SG Laich Oul
Lill Pole Closed
SG Pole Closed &
SG Latch In
MG Pole Open &
MG Laich Out
Lill Pole Open
-MG Pole Closed &
MG Laich in
V>
0 c
- r a.
(/)
C>
>
3
u
CD ...
CD
Cl>
r ::
>
3
~
...
Cl
""
-Holdl
~
- r
a.
.,
DI
~
CJ)
Ci
'O
SALEM UNIT 2
ROD CONTROL SYSTEM
CHRONOLOGICAL SUMMARY
SEVENTH REFUELING OUTAGE MAINTENANCE AND TESTING
e WESTINGHOUSE CARD TESTING SERVICES CONTRACTED
BY PSE&G
- RELIABILITY IMPROVEMENTS
-
VISUAL INSPECTION AND LOGIC CARD TESTING
- REPAIR/REPLACEMENT CRITERIA
- LOGIC SYSTEM DYNAMIC TESTING
e MAY 24, 1993
- MG SET BALANCING AND DYNAMIC TESTING
- IRPI CALIBRATIONS
A CONTROL BANK A GROUP 2 FAILS TO MOVE -
URGENT FAILURE ALARM
-
A CONTROL BANK B STEP COUNTERS FAILURE
- REPAIRED CARDS AND REPLACED 2 STEP COUNTEh&'
- PERFORMED POST MAINTENANCE FUNCTIONAL TESTS
- IRPI CALS AND ROD DROPS COMPLETED ..
SATISFACTORY
- ROD CONTROL SYSTEM READY FOR PLANT STARTUP
SALEM UNIT 2
ROD CONTROL SYSTEM
CHRONOLOGICAL SUMMARY
STARTUP OF MAY 25, 1993
e OPERATIONS PERFORMED SURVEILLANCE TEST
e COMMENCED STARTUP
e CONTROL BANK C GROUP 1 STOPS ADVANCING AT 31
STEPS
e REINSERTED RODS IN REVERSE ORDER
e MALFUNCTIONS FOUND THAT WERE NOT RELATED TO
BANK C GROUP 1 COUNTER
e INITIATED TROUBLESHOOTING VIA CARD REPLACEMENT
e DISCOVERED SHORTED DIODES ON A CARD TESTED
SATISFACTORY
e ATTRIBUTED OTHER FAILURES TO CARD WITH SHORTED
DIODES
e REPAIRED OR REPLACED AFFECTED CARDS
e PERFORMED FUNCTIONAL RETEST OF LOGIC AND
COUNTERS
- - "
SALEM UNIT 2
ROD CONTROL SYSTEM
CHRONOLOGICAL SUMMARY
STARTUP OF MAY 27, 1993
e COMMENCED STARTUP
e SHUTDOWN BANK A WITHDRAWN TO 20 STEPS - NO
INDICATION ON IRPI
- DURING INSERTION OF SHUTDOWN BANK A - 1 SA3
INDICATES WITHDRAWAL TO 15 STEPS
- l&C CONFIRMS IRPI FOR 1 SA3 AT 15 STEPS
- STATIONARY GRIPPER FUSES PULLED TO INSERT
1SA3
- LOGIC CABINET TROUBLESHOOTING IDENTIFIED 2
FAILED CARDS
e PERFORMED CURRENT ORDER TRACES AND CAPTURED
INVALID CURRENT TRACES
e REPLACED FAILED CARDS
- ATTRIBUTED APPARENT FAILURE TO SELF-INDUCED
PROBLEMS DUE TO TROUBLESHOOTING OF MAY 26
e SEGREGATED CARD FOR FURTHER ROOT CAUSE
'\\NALYSIS
t:.
SALEM UNIT 2
ROD CONTROL SYSTEM
CHRONOLOGICAL SUMMARY
STARTUP OF MAY 27, 1993 (CONTINUED)
e CONSULTATION WITH VENDOR REGARDING 1SA3 ROD
MOTION
- VENDOR INDICATED ROD RESPONSE NOT TOTALLY
UNEXPECTED FOR THIS CONDITION
- VENDOR INDICATED CROM WAS NOT DAMAGED BY
THIS OCCURRENCE
e STATUS MEETING BETWEEN OPERATIONS,
MAINTENANCE, SYSTEM ENGINEERING, E&PB AND
VENDOR
~
SALEM UNIT 2
ROD CONTROL SYSTEM
CHRONOLOGICAL SUMMARY
STARTUP OF MAY 28, 1993
e COMMENCED NORMAL STARTUP WITH ROD CONTROL
SYSTEM
e SHUTDOWN BANKS AND CONTROL BANKS
WITHDRAWN - BORON DILUTION TO CRITICALITY IN
PROGRESS
- CONTROL BANK C GROUP 1 RODS DROPPED
- MANUAL REACTOR TRIP INITIATED
- SERT CONVENED AND CHARTERED TO INVESTIGATE
PROBLEMS WITH ROD CONTROL SYSTEM AND
STARTUP DECISION PROCESS
e TROUBLESHOOTING IDENTIFIES BAD CARD IN THE
POWER CABINET
e DECISION TO PERFORM ADDITIONAL CARD TESTING
- 100 VOLT POWER SUPPLY FUSES.BLOW
e FIND PROBLEMS IN ADDITIONAL LOGIC CARDS
SALEM UNIT 2
ROD CONTROL SYSTEM
CHRONOLOGICAL SUMMARY
STARTUP OF MAY 28, 1993 (CONTINUED)
e LINE MANAGEMENT PERFORMS EVENT ANALYSIS
- DETERMINES BLOWN POWER SUPPLY FUSES WERE
APPARENTLY SELF-INDUCED
e WESTINGHOUSE PROVIDES ADDITIONAL TECHNICAL
SUPPORT
e REPAIRED NUMEROUS CARDS AND REPLACED 15 VOLT
POWER SUPPLY AUCTIONEERING DIODE
e FULL CABINET TESTING TO VERIFY COUNTERS AND
CURRENT TRACES
- CONNECTED CURRENT TRACE MONITORS FOR EACH
BANK
e PERFORMED PRE-STARTUP FUNCTIONAL TESTING
- EACH ROD BANK PULLED TO 30 STEPS, INSERTED TO
-" -
- 20 STEPS, MAINTAINED AT 20 STEPS FOR ONE HOUR
THEN INSERTED
SALEM UNIT 2
ROD CONTROL SYSTEM
CHRONOLOGICAL SUMMARY
STARTUP OF MAY 28, 1993 (CONTINUED)
e PSE&G SENIOR MANAGEMENT CONTACTED
WESTINGHOUSE SENIOR MANAGEMENT TO SOLICIT ANY
OTHER TESTING OR CHANGE OUTS THAT SHOULD BE
DONE
- FOLLOWING REVIEW WITH ITS TEAM, WESTINGHOUSE
DETERMINED NO ADDITIONAL ACTIONS SHOULD BE
TAKEN
e DECISION TO RESTART PLANT, BASED ON SORC REVIEW *.
SERT FINDINGS, CONSULTATION WITH VENDOR AND
SENIOR MANAGEMENT REVIEW
I
I
SALEM UNIT 2
ROD CONTROL SYSTEM
CHRONOLOGICAL SUMMARY
STARTUP OF JUNE 2, 1993
e OPERATIONS SURVEILLANCE PERFORMED -
SATISFACTORY
e COMMENCED STARTUP .
e ROD CONTROL SYSTEM OPERATES SATISFACTORILY -
ALL SHUTDOWN AND CONTROL BANKS WITHDRAWN
e IDENTIFY P/A CONVERTER PROBLEM
e DECISION TO SHUTDOWN UNIT 2 TO MAKE REPAIR
- TROUBLESHOOTING IDENTIFIES FAUL TY DATA LOGGING
CARD
e ATTRIBUTED TO TROUBLESHOOTING
e OPERATIONS FUNCTIONAL RETEST PERFORMED -
SATISFACTORY
e SUCCESSFUL OPERATION OF ROD CONTROL SYSTEM
DURING STARTUP AND SHUTDOWN PROVIDED
ASSURANCE OF SYSTEM RELIABILITY
SALEM UNIT 2
ROD CONTROL SYSTEM
CHRONOLOGICAL SUMMARY
STARTUP OF JUNE 3, 1993
e COMMENCED STARTUP
e ROD CONTROL SYSTEM PERFORMS SATISFACTORILY -
REACTOR CRITICAL
e NRC REGIONAL INSPECTOR ARRIVES ON SITE
SALEM UNIT 2
ROD CONTROL SYSTEM
CHRONOLOGICAL SUMMARY
JUNE 4, 1993
e REACTOR PHYSICS TESTING IN PROGRESS
e SINGLE FAILURE HYPOTHESIS PRESENTED
e WESTINGHOUSE INITIAL REACTION a NOT PLAUSIBLE (3:00
PM)
e WESTINGHOUSE ADMITS SINGLE FAILURE THEORY IS
PLAUSIBLE (4:30 PM)
e PSE&G DECISION TO PLACE UNIT IN MODE 3
e ALL CONTROL AND SHUTDOWN BANKS INSERTED
e ONE HOUR REPORT IN ACCORDANCE WITH 10CFR50.72
e ROD CONTROL SYSTEM DE-ENERGIZED
e TECHNICAL RESPONSE TEAM FORMED
JUNE 5, 1993
e AIT ARRIVES ON SITE
- - "
......
SALEM UNIT 2
ROD CONTROL SYSTEM
TECHNICAL ASSESSMENT
e FORMED ROOT CAUSE ASSESSMENT TEAM
- TECHNICAL FACT FINDING
- ENGINEERING ANALYSIS
- REPLICATION TESTING
- COMPONENT EXAMINATION BY MANUFACTURERS
- DETERMINE FAILURE MECHANISMS/ROOT CAUSE
- PROVIDE TECHNICAL INPUT TO SERT
SALEM UNIT 2
ROD CONTROL SYSTEM
TECHNICAL ASSESSMENT
TECHNICAL FACT FINDING
e DEVELOPED TROUBLE SHOOTING CHRONOLOGY. (3/17 -
6/4)
e DEVELOPED COMPONENT FAILURE LIST ( * 30)
e REVIEWED REFUELING OUT AGE DESIGN CHANGES
- EQUIVALENT COUNTER REPLACEMENT
- POWER CABINET POWER SUPPLY MODIFICATIONS
e
SALEM UNIT 2
ROD CONTROL SYSTEM
TECHNICAL ASSESSMENT
ENGINEERING ANALYSIS
e EVALUATED SINGLE FAILURE
- DUPLICATED CURRENT TRACES THROUGH
ENGINEERING ANALYSIS
- INVESTIGATED SHUTDOWN BANK A CROM
RESPONSE
e ASSESSMENT OF FAILURES
-
ANALYZED COMPONENT FAILURES AND REPAIRS
- EVALUATED SYSTEM POWER SUPPLIES
- EVALUATED WESTINGHOUSE TESTER
- DETERMINED COMPONENT FAILURE MECHANISMS
- DETERMINED PROBABLE ROOT CAUSES
83MM3-111 c .(
SALEM UNIT 2
ROD CONTROL SYSTEM
TECHNICAL ASSESSMENT
REPLICATION TESTING
e SIMULA TED SINGLE FAILURE AT NUCLEAR TRAINING
- CENTER
- SIMULATED COMPONENT FAILURES
- DUPLICATED EXPECTED CURRENT ORDERS AND
TRACES
- DOCUMENTED CROM RESPONSE SIMULATED
FAILURE MECHANISM
e SIMULATED FAILURE MECHANISMS
- CYCLED POWER SUPPLIES
- MONITORED WESTINGHOUSE TESTER FOR
ANOMOLIES
- BENCH TESTED RELAY DRIVER/COUNTER CIRCUITRY
- SIMULATED TROUBLE SHOOTING ERRORS
- MEASURED BACK EMF
113MMS-20 e "'
SALEM UNIT 2
ROD CONTROL SYSTEM
TECHNICAL ASSESSMENT
COMPONENT EXAMINATION BY MANUFACTURER
e MOTOROLA
e PHILIPS
ROD CONTROL SYSTEM
LOGIC CABINET BLOCK DIAGRAM
..... AC,_
11*vAC*Hlt
a...,...
AC,_
..
.......... --~~~l!!!~l:!..~~t=~
-II*
I
, ........... ~_;::.!!~~1:.:==:::.~~-t;;;;;;;;;1~c:ir--~--t
- 1002-121111T23171.0IZ4
M ...
...
~
......
c,...
..................
GOIAC
caoo*
}*~.
._II
Tol'lenl
~
TOPIA
c_...
Of8J7- 5
r--"
SALEM UNIT2
ROD CONTROL SYSTEM
TECHNICAL ASSESSMENT
COMPONENT EXAMINATION BY MOTOROLA
SUPERVISORY DATA LOGGING
MC 668L NANO GATI; CHIP
- ONE CHIP PIN (INPUl) SHORT TO GROUND
CAUSE: ELECTRICAL STRESS DEGRADATION OR
ELECTROSTATIC DISCHARGES
- ONE CHIP PIN 6 AND 8 (OUTPUl) LEAKAGE
CAUSE: ELECTRICAL OVERSTRESS
- ONE CHIP PIN 8 (OUTPUl) LEAKAGE
CAUSE: ELECTRICAL OVERSTRESS
APPEARS OVERSTRESS CAUSED A SHORT TO THE
SUBSTRATE
SALEM UNIT2
ROD CONTROL SYSTEM
TECHNICAL ASSESSMENT
COMPONENT EXAMINATION BY PHILIPS
RELAY DRIVER
1N4148 BLOCKING DIODE
- ONE DIODE FOUND SAT
Ir, Vf, AND Vbr MEET SPECIFICATION
- TWO DIODES FOUND WITH DEGRADED REVERSE
CHARACTERISTICS
(VERY HIGH REVERSE LEAKAGE, PARTIALLY SHORTED)
- RESULT OF ELECTRICAL OVERSTRESS
ROD CONTROL SYSTEM
LOGIC CABINET BLOCK DIAGRAM
.._AC,_
11*vAC*et11
~
AC,_
.... a::{
....
c.-.
....
....................
IAC
F--------l =*
.......
c...-
Jol'1A
c-
lo ,._
c-..
Normal Oscillograph Trace
Lih Pole
CloMd
I
MG Pole Closed & -11-~
MG Laich In
Load Tran1ler
SO Pole Open &
SQ Latch Out
SO Pole CloMd &
SG Laich In
MG Pole Open &
MOLalchOul
Lah Pole
CIOMd
g
I
- > .. *
- l
en i
MG Pole Closed &
MG Laich In
lo*d Transler *
SG Pole Closed &
SG Laich Oul
L 111 Pole Closed
SG Pole Closed &
SG Laich In
MG Pole Open &
MG Laich Oul
Lill Pole Open
MG Pole Closed &
MG Laich In
Ill
0 c
- >
Q
U>
Gl
>
3
'O
Cl ... * ..
~
Gl
>
3
'O *
... * ..
r :i
>
3 1 i
~
Q ... *
t
U> ii
'O
- ~:*-*-:*:*********:***
J,~ :
.
.
.
.:!.:.':*.: .... **,.::; ...
- .... **-i-** ....... *~ .
. ...... ***** ... -.. .
. . .
.
... .. ..
~
'
....*
.*. ......... *!* :** . . .*......
. GAii -4' Sf At. I AM- f~
~ek.-
i1ttoi....f;~ ~d: *******~ *** * ;~
- . ** .. *
... * i
. * .
..
,.,~
1*
=
'" .... -~~ .. t .. .-. ... o..1J ........ l.1()~ ..... A r. ..
r
~ ...... /l !
'.I'
~ i ..
.i *
. . . * ... ~ ..... : * ,
. ~
!
..... t~*. -r~~ ... i.
1
~
. .
- **:*T .. ****:t***
- ..... !
.
.
d
.
. .
.
. . . *
.. "
- . a . . . -z. ~
! D,.,...,-~
lt ,'.' ~- ~
"'I! ~.Tl. e. ,.,. .... :
.. ~---~i. ...... : ... ~- ~- ~l ...... ir.. . .£1 .*..
l U~ :")*1.*" l
-~1 tJP
.. ~.DI~ ~-P.A ... . *:' ... /=."if J~t..b~, ... +. .c; ~
fJ i.. ~"'*; '"'* ,..,_, L' L
.. , ...... __ . o __ *c. ~.* * . .1 r.
_.*
. e. .
.
.
. ..
.
"' ., ,.,....
- .;.
.,,,,...
r I t.J. L . . ~ _T**t. P 5
i I.
.
I
r
.
.
()~/
f'1 I A-.fm*ll~.,,,.
- ~OG Rf.Al. I,,.._
I v . l ________ ___;.___.--'(:
r
l. * :*fr::: ..... :::r:.:*~-*::*1* ... t:::.:-::*>_:;2L~*:::: :::* ... : . : *
i ;r**
- _ ,. 1
.
.
..
... ..
,..
- ..... ;
i . . ... f . . ........ ; .. . . ..
~ . . .
- .
~ .. :.: *. *:. ~ ..
! . . :
- .**
.
.**
- ...........
,
..............
$
........
_
.... _.
_
_..
_
_..
..........
, ....... i
r** ....
. ~
..
-~ ...
. A . "c. 8 t. 1 :; II~* ~f ...
. ~
...,-. . ~ .. .
.
....... r. /~JV.:
! .
! ~~-~~~ f~:*.::.: .... /.I ..... ******
.... : ... :.,: .. : ...... r**' **
~-*
- I
! *
. J ~ ~A Ji. I) : /1f c TI c :,v
~ R~ '1. ~ ~ ~It. D
tA.P.
~.,
. ~ .::,1. x
~
.
lt.C I)
If~*"?
! ,,
~-,,.e_ i)
~** ***-**** ... ; ....
.
-
P.~$P ~
oc.4.. r-: *
o(.lj-
{,--r-13
F~it-'ii\\D : .t..c* ,,.) ~
.
. .
.
.
.
.
.
.
.
.
.
.
~r *:,Ds=*
... ~:r
.
.T ..
- ..... .
<
- \\.__~ --~ *..,.._..._JCPollfllOlllrftll'l!..,. ... 1-ixl'llllfl*-*11 ..... --_....:.('"
. ....
- ~. : ...
GtH> A SIAt.
I AN IP!iB
. ...
u
SALEM UNIT 2
ROD CONTROL SYSTEM
TECHNICAL ASSESSMENT
COMPONENT EXAMINATION BY WESTINGHOUSE
SLAVE CYCLER DECODER 3359C62 G02/WSN0079
MC 668L - 6951 NANO GATE CHIP
e CHIP 22, PIN 9 HAS 200 OHMS TO GROUND LEAKAGE
THROUGH SUBSTRATE (INSULATION BREAKDOWN)
e CHIP 21, PIN 5 LEAKAGE TO GROUND
2 MICROAMPS AT 10 VOLTS
(SPECIFICATION CALLS FOR 2 MICROAMPS AT 16V)
THE MOST LIKELY CAUSE FOR THIS FAILURE IS A
VOLTAGE TRANSIENT IN EXCESS OF DEVICE
CAPABILITY RESULTING IN OXIDE -BREAKDOWN
$
- AND THE RESULTANT "SHORT"
SALEM UNIT 2
ROD CONTROL SYSTEM
TECHNICAL ASSESSMENT
COMPONENT EXAMINATION BY MOTOROLA
SLAVE CYCLER DECODER NANO GATES
(2) MC660L, ( 1) MC662L, (2)MC668L
(1) MC668L CHIP FOUND PIN 1 TO GROUND FAULT
DUE TO ELECTRO STATIC DISCHARGE (ESD)
OTHER MC668L AND BOTH MC660L SAT
(1) MC662L EVIDENCE OF (ESD) DAMAGE THROUGH
MICROSCOPE ANALYSIS
PROCESS:
1.. COMPUTER CHIP TESTER
2. LAB CONFIRMATION (TRACER CURVE TEST)
3. MICROSCOPE ANALYSIS (COLOR VIDEO)
4. SCANNING ELECTRON MICROSCOPE (SEM)
INCLUDING SILICONE ETCHING
..
n * *.
BASIC SYSTEM BLOCK DIAGRAM
480VAC =:
60HZ
pJC
Speed
and
Direction
22* "T23' 1*.00'
Motor
BKRS
Logic
Cabinet
D
Motor
Generator
( 1 of 2)
XFMR
Gen
BKRS
Main 120VAC
Current Commands
Group Select
Auxiliary
120VAC
260VAC 3/J
Hold
Cabinet
Control
-P:-A-
L--~-----1~ Converter
Bank Steps
- - -
260 VAC
Reactor
Trip Bkrs
Power Cabinet
( 1 of 5)
D
' '
125 voe
or
10 voe
CROM
Reactor
Protection
Trip Signals
Lift
Current
Movable
Current
Stationary
Current
Control
Bank voe
. ' BRlt)GE CONTROL CIR'CUIT
Current
Orders{
from
Logic
Cabinet
H7Clt tltt11.0t t
Phaee
Control
Card
'
Error
Sign al
-
--
-
Phase
-
-
Sensing
-
XFMRS
-
Firing
-
-
-
.
Card
-
. --
~ ---*
--
-
I *
-
-1
I
Rff . ' Rz
Regulation
i.-
Card
I
I
-+
Coil Current
Samples
ftg. 2-13
fdc N
--
-
-~
, 7 ,
1 , 1
(
.. ; ..
i
...
-- -
,1 , .,l , , 1, ~ 1
- .. - .. -.. -...
I'* Ii * 1r* ~::
11111
II
1
111
11.
II
I~
11
- - -
- -
-
- * ...
- ~ ::
- * ...
.. .
.. . .. . ..
Half Wave
Thyristor
Bridge
Mechanism
Coils
SALEM UNIT 2
ROD CONTROL SYSTEM
TECHNICAL ASSESSMENT
FAILURE MECHANISMS I ROOT CAUSE SUMMARY
e RELAY DRIVERS/SUPRV. DATA LOGGING
~ PIN CONNECTION FOR SUPPRESSION DIODE
- COUNTERS COIL BACK EMF
- SLAVE CYCLER DECODER
-
VOLTAGE TRANSIENT ASSOCIATED WITH COUNTER
BACK EMF
-
EXTENSIVE TROUBLE SHOOTING
e SHUTDOWN BANK A CROM RESPONSE
-
COIL TIMING (LIFT AND MOVABLE)
-
FRICTION: DESIGN TOLERANCES AND/OR OXIDES/CRUD
BUILD-UP
e CONTROL BANK C GROUP 1 DROP
- REGULATION BOARD TRACE DEGRADATION
e P/A CONVERTER FAILURE
- SUPERVISORY DATA LOGGING (SOL) FAILURE
-
INCOMPLETE TESTING ON PRIOR REPLACEMENT OF SDL
e STEP COUNTER FAILURE
- MECHANICAL BINDING
SALEM UNIT2
ROD CONTROL SYSTEM
SAFETY ASSESSMENT
- ASSUMED SINGLE FAILURE CAN RESULT IN SINGLE
ROD WITHDRAWAL
- UFSAA ACCIDENTS ANALYSIS CONSERVATIVELY
RE-EVALUATED AGAINST CONDITION II CRITERIA
(DN BR 2: 1 .3)
- BASED ON ASYMMETRICAL ROD WITHDRAWAL
- DNBR 2: 1.3 FOR ALL CONDITION II EVENTS EXCEPT
ROD WITHDRAWAL FROM SUBCRITICAL
- STARTUP PROCEDURE MODIFIED TO ADDRESS ROD
WITHDRAWAL FROM SUBCRITICAL
- WILL DILUTE TO CRITICAL WITH CONTROL RODS
WITHDRAWN DURING RESTART
- NO FUEL FAILURES DUE TO ASYMMETRICAL ROD
WITHDRAWAL
- QDC 25 CRITERIA MET
SALEM UNIT2
ROD CONTROL SYSTEM
SAFETY ASSEMENT
- COMPENSATORY ACTIONS IMPLEMENTED TO PROVIDE
ADDITIONAL ASSURANCE
- STANDING NIGHT ORDER
- ADDITIONAL SURVEILLANCE TESTING
- CURRENT TRACES PRIOR TO RESTART
- DILUTE TO CRITICAL WITH CONTROL RODS OUT
- OPERATOR BRIEFINGS/TRAINING
- BASED ON CURRENT INFORMATION, USQ ASSUMED
TO EXIST
- TEMPORARY LICENSING BASIS CHANGE PENDING
FINAL INDUSTRY RESOLUTION
SALEM UNIT 2
ROD CONTROL SYSTEM
SERT ASSESSMENT
SERT CHARTER - MAY 28, 1993
e INVESTIGATE ROOT CAUSES FOR ONGOING FULL LENGTH
ROD CONTROL SYSTEM (FRCS) PROBLEMS
e PRUDENCE OF STARTUP DECISIONS
SALEM UNIT 2
ROD CONTROL SYSTEM
SERT OBJECTIVES
e DEVELOP SEQUENCE OF EVENTS/CAUSAL FACTORS
CHART AND IDENTIFY FAILED BARRIERS
- INVESTIGATE WESTINGHOUSE CARD TESTING
SERVICES AND OTHER OUT AGE ACTIVITIES
e ASSESS OPERATOR RESPONSE TO DROPPED RODS AND
ISA3 ANOMALY
e ASSESS MANAGEMENT CONTROL OF
TROUBLESHOOTING
e ASSESS USE OF OPERATING EXPERIENCE AND
ADEQUACY OF PM
c ".
SALEM UNIT 2
ROD CONTROL SYSTEM
ADDITIONAL AREAS EXAMINED
e RELAY ROOM VENTILATION
e DESIGN CHANGES
e PROCUREMENT
e SOLDERING
e TRAINING
SALEM UNIT 2
ROD CONTROL SYSTEM
ANALYTICAL TECHNIQUES
ACTIVITIES
e 75 INTERVIEWS
e 1350 DOCUMENTS/RECORDS REVIEWED
e 2400 TEAM HOURS TO DATE
e 18 TEAM MEMBERS - SOME PART-TIME INCLUDING 6
CONTRACTOR PERSONNEL ADDED FOR SPECIFIC
EXPERTISE
-
IECFINIQUEs-------- ------ ------- - --- --------- -- - --------- -- --
-
e EVENT AND CAUSAL FACTOR CHARTING
e HUMAN/EQUIPMENT CAUSAL FACTOR ANALYSIS TO
VALIDATE
STATUS
e PRELIMINARY FINDINGS/CONCLUSIONS DETERMINED
e CORRECTIVE ACTION RECOMMENDATIONS BEING
DEVELOPED
e VALIDATION IN PROCESS
.*- ..
.,_
SALEM UNIT 2
ROD CONTROL SYSTEM
SERT ASSESSMENT
FINDINGS/CONCLUSIONS (PRELIMINARY)
e CONTROL ROOM RESPONSE WAS CONSERVATIVE AND IN ACCORDANCE
WITH *PROCEDURES
e 1 SA3 WAS NOT ASSESSED AS A DESIGN BASIS CONCERN
e CONTROL OF TROUBLESHOOTING WAS LESS THAN EFFECTIVE
e REPETITIVE COMPONENT FAILURES DID NOT INITIATE SEARCH FOR
COMMON FAILURE MODE RESTART DECISIONS WERE MADE WITHOUT
ROOT CAUSE RESOLUTION OF THE REPETITIVE FAILURES
- SALEM HAS NO HISTORY OF SIGNIFICANT FLRCS FAILURE
e VENDOR SUPPLIED INFORMATION DID NOT DENOTE COIL RES!3TANCE
DIFFERENCES FOR SAME MODEL STEP COUNTERS ',
e WESTINGHOUSE CARD TESTER DOES NOT TEST ALL CIRCUIT DIODES
WHICH COMPLICATED TROUBLESHOOTING
- PIN CONNECTIONS/CONTACTS PROBLEMS EXISTED AT THREE (3) OTHER
WESTINGHOUSE SITES
e OTHER
- PARTS PROCUREMENT
-
OUTAGE COMPLETION INFLUENCE
-
VENDOR CONTROLS/COMPLIANCE
t':- .. -
. -
w* *.
J
SALEM UNIT 2
ROD CONTROL SYSTEM
CORRECTIVE ACTIONS
. IMMEDIATE
- OPERATIONAL
-
DEVELOP AND IMPLEMENT SAFETY
EVALUATION FOR CONTINUED SAFE
OPERATION
COMPLETE
-
STANDING ORDERS IN EFFECT
COMPLETE
-
CURRENT TRACES WILL BE PERFORMED
PRIOR TO EACH STARTUP
COMPLETE
-
FOR UNIT 2 INCREASED SURVEILLANCE
TESTING FOR IRPI VERIFICATION
COMPLETE
-
APPROPRIATE PROCEDURES HAVE BEEN
REVIEWED FOR ADEQUACY TO
IDENTIFY AND ADDRESS ABNORMAL
ROD MOVEMENT
COMPLETE
-
ESTABLISH IMPROVED PRACTICE(S)
- BEFORE S/2 CARP
FOR CARD REMOVAL/INSTALLATION
REPLACEMENT
NMMl-27
..
..
SALEM UNIT 2
ROD CONTROL SYSTEM
CORRECTIVE ACTIONS
IMMEDIATE
e OPERATIONAL (CONTINUED)
-.OPERATORS TRAINED AT SIMULATOR
FOR UNEXPECTED ROD MOTION
-CONTINUE NOTIFICATION TO THE
INDUSTRY OF THE SALEM INCIDENT
- MODIFICATIONS
-
INSTALLATION OF SUPRESSION DIODES
FOR BOTH UNITS
-
REPLACE ROD CONTROL LOGIC
CARDS - UNIT 2
-
IMPLEMENT STATIC CHARGE CARD
HANDLING GUIDANCE
PMM3-2t
COMPLETE
ONGOING
IN PROGRESS
BEFORE STARTUP
COMPLETE
,; .....
- *
- -
SALEM UNIT 2
ROD CONTROL SYSTEM
CORRECTIVE ACTIONS
LONG TERM
e MANAGEMENT ISSUES
- COMPLETE SERT EVALUATION AND IMPLEMENT
APPROVED RECOMMENDATIONS
- PROVIDE IMPROVED GUIDANCE FOR THE CONDUCT AND
CONTROL OF MAINTENANCE TROUBLESHOOTING
ACTIVITIES
- PARTICIPATE WITH WOG FOR RESOLUTION OF GENERIC
ISSUES
- ESTABLISH A "LESSONS LEARNED" TEAM BETWEEN
WESTINGHOUSE AND PSE&G FOR CONTRACTOR
SERVICES
- PROVIDE PROCEDURAL GUIDANCE FOR ROOT CAUSE
ADEQUACY
e MODIFICATIONS
- CHANGE MECHANICAL STEP COUNTERS TO DIGITAL
STEP COUNTERS
~
~-
SALEM UNIT 2
ROD CONTROL SYSTEM
SUMMARY CONCLUSIONS
e SIGNIFICANCE OF SINGLE ROD WITHDRAWAL AS A FUNCTION
OF A SINGLE FAILURE NOT IDENTIFIED SOON ENOUGH
RESULTING IN INAPPROPRIATE DECISION TO RESTART
e SUBSEQUENT TO RECOGNITION OF SIGNIFICANCE,
COMPREHENSIVE TROUBLE SHOOTING, REPAIR, ROOT CAUSE
EVALUATION
e CONSERVATIVE ACTION TO SHUTDOWN UNIT 2 AND MAINTAIN
UNIT 1 SHUTDOWN FOLLOWING TRIP
e COMPREHENSIVE SAFETY ASSESSMENT PERFORMED
e COMPENSATORY ACTIONS IN PLACE TO PROVIDE ADDmONAL
ASSURANCE
e THOROUGH CORRECTIVE ACTIONS TAKEN/UNDERWAY
e CONTINUING DETAILED SELF*ASSESSMENT BY SERT
e MODIFICATIONS TO ROD CONTROL SYSTEMS IN PROCESS
e MANAGEMENT ISSUES IDENTIFIED AND BEING ADDRESSED
e PSE&G ACTIVELY SUPPORTING LONG TERM RESOLUTION WITH
w.o.G.
SAFE, CONSERVATIVE APPROACH TO REACTOR SAFETY LEAD
TO DETAILED SAFETY ANALYSIS TO ADDRESS GENERIC ISSUE
NMM3*36