ML18096A274

From kanterella
Jump to navigation Jump to search
Insp Repts 50-272/91-16 & 50-311/91-16 on 910520-24. Violations Noted.Major Areas Inspected:Licensee Corrective Actions Taken in Response to 900409-27 Maint Team Insp Findings,Including 900821 Violations from Insps
ML18096A274
Person / Time
Site: Salem  
Issue date: 08/16/1991
From: Blumberg N, Caphton D, Finkel A
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML18096A272 List:
References
50-272-91-16, 50-311-91-16, NUDOCS 9109240103
Download: ML18096A274 (17)


See also: IR 05000272/1991016

Text

Report Nos.

Docket Nos.

License Nos.

Licensee:

Facility Name:

Inspection At:

U. S. NUCLEAR REGULATORY COMMISSION

REGION I

50-272/91-16; 50-311/91-16

50-272; 50-311

DPR-70; DPR-75

Public Service Electric and Gas Company

P. 0. Box 236

Hancocks Bridge, New Jersey 08038

Salem Nuclear Generating Station, Units 1 & 2

Hancocks Bridge, New Jersey

Inspection Conducted:

May 20 - 24, 1991

phton, Sr. Technical Reviewer

Approved byL LC?~~ief

-fl* Performance Programs Section

Operations Branch, DRS

Engineer

Date

Date

Date

Inspection Summary:

Inspection May 20 - 24, 1991 (Combined Report Nos.

50-272/91-16 and 50-311/91-16)

Areas Inspected:

Licensee's corrective actions taken in response to the

April 9 - 27, 1990, maintenance team inspection findings including the

August 21, 1990, Notice of Violation for Inspection Nos. 50-272/90-200 and

50-311/90-200, and the licensee's program for surveillance testing of safety-

related equipment.

Results:

Material conditions and housekeeping since the April 1990 MT! were

noticeably improved as observed during walkdown inspections.

The licensee's

corrective action taken to the April 1990 maintenance team inspection (MTI)

violation was found to be inadequate (a violation) in that water tight door

locking dogs were again found to be inoperable, and the licensee's programs for

9109240103 910820

PDR

ADOCK 05000272

Q

PDR

17

2

deficiency identification again failed to identify the problem.

One unresolved

item was closed relating to the control of a Q-listed ~onsumable; however, a

new unresolved item was opened because the licensee did not assure*that other

Q-listed consumables were being controlled, and a new unresolved item was

opened relating to the Nuclear Services Departments 1 s lack of procedures to

assure control of contractors doing safety-related maintenance work.

Surveil-

lance testing and calibration control programs were inspected and found to be

functioning well.

DETAILS

1.0 Scope (62700)

This inspection assessed the corrective action taken by the licensee to

three violations issued by letter dated August 21, 1990, resulting from a

maintenance team inspection (MTI) conducted during April 9 - 27, 1990.

The inspection included the licensee's response letter to the MT! dated

September 21, 1990.

People were interviewed, hardware and equipment were

in~pected, and docu~ents were reviewed.

Individuals contacted during the course of the inspection and the attendees

at the inspection's exit meeting held on_ May 24, 1991, are identified

on Attachment 1.

Findings

Violation 1 (50-272 and 50-311/90-200)(Closed)

This violation concerned modified hatch covers installed in the service

water rooms of both units that did not meet the water tightness specified

by the Updated Final Safety Analysis Report; no safety evaluation had

been made pursuant to 10 CFR 50.59.

The inspector visually inspected the new permanent hatch installations

and found that the hatches appeared to be tightly sealed.

The inspector

had no further questions regarding the installation of the hatches, the

sealing of the hatches, or the 10 CFR 50.59 safety evaluation performed

for the temporary hatches that since had been replaced with the permanent

hatches.

The licensee's September 21, 1990, response letter to the Notice of

Violation stated that

11 these hatches have been stenciled to identify them

as having to be maintained water tight and to contact the Shift Supervisor

prior to opening.

11

The visual inspection of the accessable hatch areas

did not find the stated stenciling.

The licensee's representative stated

that plastic plates with the subject information had been installed in

lieu of stenciling, but appeared to have been broken off and lost.

At the

end of the inspection, the licensee's representative stated that the

stenciling had now been completed.

The new stenciling of the hatches was

not verified by the NRC inspector.

The licensee's September 21, 1990, response letter stated that a

11 revised

Temporary Modification Program procedure was approved in August 1990.

11

The inspector noted that the procedure was approved in March 2, 1990, not

in August 1990, as stated in the subject letter.

The licensee's

representative stated that the new procedure was actually implemented in

August 1990.

Implementation was phased in because the procedure replaced

two station procedures which were controlling ongoing work.

The inspector

had no further questions except for the lack of specificity of the

response letter.

4

The September 21, 1990, response letter for corrective action stated that,

11A procedure revision has been initiated to incorporate these water tight

hatches into Abnormal Operating Procedure (ADP) Wind 1.

This rev1s1on

will be completed by October 1990.

11

On May 21, 1991, the inspector found

that the current Wind 1 revision was Revision 0, approved September 29, 1987,

and that the last periodic review of the procedure was completed on

May 24, 1990.

Based upon interviews, the inspector determined that SORC

meeting 90-133 on September 19, 1990, had approved fhe commitment to

revise Wind 1 and that there appeared to have been an oversight in the

tracking of the commitment.

Failure to track the commitment was stated by

the licensee's representative to be the cause for not completing the

committed corrective action.

During this inspection, the licensee

initiated revisions to Wind 1 and approved Revision 1 to the procedure for

both units on May 24, 1991.

Based upon the revised Wind 1 procedure, the

inspector had no further questions, except for the lapse in the licensee 1s

management controls that resulted in misstng the corrective action

commitment.

A licensee 1s representative stated that the licensing group

has now initiated an

11Action Tracking

11 computer program to track- corrective

action commitments to the NRC.

The representative stated that this was

not being done at the time of the MTI.

In conclusion, for Notice of Violation No. 1, the new replacement hatches

were found to be adequate.

The licensee failed to maintain stencil signs

on the hatches as tommitted by their response letter.

The issue was

identified by the inspector.

The licensee 1 s_management control for

commitments in their response letter to the NRC was inadequate in that

stencilling was not maintained and a procedure revision was not completed.

Violation 2 (50-272 and 50-311/90-200)(0pen)

This April 1990 MTI vi o 1 at ion was

11Water tight doors between the service

water valve rooms and the surrounding areas of the auxiliary building had

not been adequately maintained in that the door latching dogs required to

be operated to make the door closure water tight were unmovable from their-

undogged position when reasonable force was applied.

This condition had

not been promptly identified and corrected. 11

The licensee's September 21, 1990, response letter stated that

11All water

tight doors specified in the FSAR, including those required by abnormal

operating procedures (ADP) were ins~ected, adjusted, and re-gasketed to

bring them to an acceptable condition.

11

During this current inspection, the inspector interviewed cognizant

maintenance personnel, examined, and verified a sample of the. work orders

(approximately 60 noted) that had been written and completed to fix the

water tight doors during the period of May to August 1990.

Water tight

doors in both units were inspected.

The inspector found (in both units)

that some latching dogs required unreasonable manual force to operate and

several coul-d not be operated due to mechanical interference (with the

latching dog).

No acceptance criteria were identified for a maximum

acceptable force for latching a dog.

The licensee provided no erigineering

analysis or other information to provide a basis for not requiring all

5

door latching dogs to be capable of latching.

The inspector*opined that

the licensee's corrective action taken had not corrected (in total) the

conditions cited in the Notice of Violation.

Alternatively, if the

corrective action previously taken had fixed the latching dogs as indicated

in the licensee's response letter, the conditions identified on

May 21, 1991, had not been promptly identified and corrected to maintain

the doors' latching dogs in an operable condition.

The inspector did note

that all doors sampled would close against their gaskets and that the

gaskets appeared to be in good condition.

The licensee's corrective action response letter stated that

11to increase

awareness of the FSAR requirements in this area, the General Manager of

Salem Operations has issued a letter to all station personnel detailing

this violation and the importance of water tight doors and hatches to the

physical plant.

11

The letter was issued on September 7, 1990.

The letter

stated the importance of the doors to protect against flooding in the

event of a storm as well as to prevent flooding from internal sources in

the event of a high energy water or steam line break.

The letter stated

that

11deficiencies in water tight doors and hatches be identified, work

requests initiated ... doors are significant to plant safety.

11

The

inspector had no further questions regarding the general manager's letter

except for the effectiveness to implement identification of deficiencies

in the water tight doors' latching dogs.

This part of the licensee's

quality assurance efforts appeared inadequate based upon the NRC inspector

identifying problems with latching dogs.

The licensee's corrective action response letter stated that a periodic

PM task request had been initiated.

The inspector interviewed the cognizant

PM person identified to have been assigned responsibility for initiating

the PM procedures.

This person stated that the PM procedures were scheduled

to be issued by September 1991.

Based upon interviews, no interim PM task

was initiated to ensure water tight door operability, including their latching

dog operability, i.e., the only PM action taken was the task to develop

the PM procedures.

The inspector concluded that, based upon finding the

inoperable latching dogs during this inspection, the licensee's PM

corrective action was less than adequate.

In concl~sion, for Violation No. 2, the corrective action planned and

taken to assure and maintain water tight door operability was inadequate.

Findings during this inspection in May 1991 were similar to findings of

the April 1990 MTI.

Evidence exists that maintenance had been performed

on the water tight doors; however, no definitive acceptance criteria for

latching dog operability was established, including any engineering

evaluation that would permit less than all latching dogs being fully

operable.

The failure to maintain water tight doors' latching dogs

operable and to identify and promptly correct latching dog deficiencies is

a recurring violation (50-272/91-16-02 and 50-311/91-16-02) .

6

Violation 3 (50-272 and 50-311/90-200)(Closed)

This violation included four examples involving failure to follow procedures

during work performance by contractor individuals.

The inspector

concluded that the licensee had taken reasonable corrective action for

each of the performance violations which included emphasizing that

contractor employees need to follow procedures.

The licensee also verified

that corrective actions had been completed for the items involving

hardware deficiencies.

The inspector had no further questions regarding these specific items.

Conclusion

Violation 1

The replacement hatches were found to be installed adequately, thus closing

the violation.

The licensee did not maintain _an information sign on the

hatch covers as committed in their September 21, 1990, response letter;

during *this inspection, the licensee took corrective action to identify

the hatches.

The licensee's management controls for commitments in their

response letter was inadequate.

Violation 2

The corrective actions planned and taken to assure and maintain water

tight door operability were inadequate.

The licensee's failure to identify

and promptly correct latching dog deficiencies is a recurring violation.

This violation remains open.

Violation 3

The corrective actions taken to specific items involving failure to

follow procedures were adequate.

This violation is closed.

2.0 Scope

This inspection assessed the action taken by the licensee to correct

five MTI weaknesses identified in Appendix B of the August 21, 1990, NRC

letter to the licensee.

The weaknesses were identified during the MT!

conducted during April 9 - 27, 1990.

The licensee responded by letter

dated October 19, 1990.

People were interviewed and records and documents

were inspected.

Findings

Weakness 1

"Management of mainten~nce backlog items and an absence of an effective

backlog reduction program.

11

7

The actual maintenance backlog was stated to be approximately 3100 work

orders at the time of this inspection or slightly higher than at the time

of the MTI.

The licensee

1s representative stated that, currently, more

work orders are being written than are being worked off by the available

resources.

The inspector toured areas of both units and noted a number of material

condition improvements.

The facilities visited were noted to be maintained

clean and well painted, reflecting improvements that have taken place

since the MTI.

The licensee has instituted a maintenance backshift to

more efficiently use resources.

Improvements have been made in planning

and scheduling to improve work effectiveness.

Based upon the continuing large work order backlog, this weakness remains

an open concern until the licensee has demonstrated effectiveness in his

backlog reduction program.

Weakness 2

11 Lack of root cause analysis training for system engineers.

Genera 1 1 ack

of adequate root cause analysis.

11

The licensee 1 s October 19, 1990, response letter stated that four one-week

sessions of root cause analysis training had been scheduled for 1991 and

that

11 ten seats have been res.erved for* system engineers in each session.

The Technical Department will schedule two or more engineers from each

discipline to attend these classes.

Based upon this schedule, all system

engineers will be root cause analysis trained by the end of 1991.

11

The

technical manager stated that, due to imposed budget restraints, the

schedule given in the October 19, 1990, response letter will not be met.

Two of the four 1991 root cause analysis training classes have been

postponed.

To date, eleven system engineers have been trained in root

cause analysis, 12 system engineers are in the course, and 17 are expected

to complete the training in 1992, not

11 by the end of 1991,

11 as stated in

the licensee 1 s October 19, 1990, letter.

The licensee 1 s representative

stated intent to provide this change in commitment information to the NRC

by letter.

The licensee 1 s October 19, 1990, response letter stated a general guidance

procedure on root cause would be issued by January 31, 1991, for use by

. system engineers.

The Technical Department procedure was approved .on

February 14, 1991; however, it was not issued January 31, 1991, as stated

in the licensee 1 s response letter.

The procedure TI-37,

11 Root Cause

Analysis Guidelines,

11 Rev.ision 0, sets down the minimum training requirements

for a root cause investigation team, provides guidance for the analysis

process, data and information collection, methods for event analysis

including corrective actions for root causes .

8

The inspector concluded that the licensee's issued procedure and completed

training of system's engineers has provided a po~itive base upon which to

improve root cause analyses.

This weakness is closed.

Weakness 3

Lack of capability to readily analyze older maintenance data for performance

monitoring and evaluation."

The Maintenance Management Information System (MMIS) data base includes

equipment hi story and records from 1987 forward.

This data base is

improving with time.

Also, NPRDS data is available since 1984.

A new initiative to improve reliability of equipment and components is the

Reliability Centered Maintenance (RCM) program which is doing indepth

reviews of systems and identifying critical components relative to

establishing improved maintenance.

The licensee's October 19, 1990,

response stated that "To date, the RCM has completed the review of 12

systems ... " Based upon interviews and a.review of the May 13, 1991,

Preventive Maintenance Improvement Project Monthly Report - April 1991,

the inspector determined that only 10 systems were complete as of May 1991,

not

11 12 systems" as stated in the licensee's October 19, 1990, response

letter.

The RCM efroup manager stated that 7 systems were completed for

Salem and 3 for Hope Creek.

The RCM group plans to do 4 systems in 1991.

He stated that the RCM budget had been reduced for 1991; h6wever,

efficiencies achieved in their work methods permit meeting their schedule

for 1991.

He stated that, in the original RCM scope, it was planned to do

a total of 60 systems.

The licensee's stated intent is to include the old pre-1987 maintenance

data for critical components with history problems into the RCM database.

The inspector noted the slow progre~s being made in completing the RCM

program.

However, the MMIS database initiated in 1987 is growing with

time and NPRDS and other historical maintenance data are used during RCM

system reviews.

This results in evaluation of older data.

This weakness

is closed.

Weakness 4

"Inadequate technical procedures, absence of formal maintenance procedures

for important and repetitive tasks.

11

Specific procedural concerns identified by the MTI inspection report in

paragraph 4.1.7, "Maintenance Procedures," were addressed by the licensee

through revisions to procedures.

No other concerns were identified

regarding the action taken.

The

licen~ee's procedure upgrade project (PUP) was initiated in

September 1989, PUP is providing a general techn.ical upgrade to approximately

388 (on May 21, 1991) maintenance procedures.

The total PUP project

includes 3949 procedures per the PUP manager.

The total project

was stated to be 32.5% complete.

As of May 5, 1991, 160 maintenance and

9

electrical procedures were upgraded.

Based upon the actions taken to

address the specific MT! findings and the overall_ actions underway in the

PUP, this weakness is closed.

Weakness 5

11 Poor control of contractor maintenance activities. 11

During the MT!, the licensee took immediate and satisfactory corrective

action to specific concerns the team identified relative to contractor

control.

However, the team was concerned that the licensee had not taken

any broad actions to identify, evaluate, and correct potential problems

indicated by the team's findings.

The inspector first determined the PSE&G departments that were controlling

contractors performing safety-related maintenance activities in the plant.

Based on interviews, these departments were Maintenance, Engineering and

Plant Betterment, and the Nuclear Services (site services) Department.

The inspector next assessed contractor controls for each of these

departments.

Maintenance Department

The licensee's October 19, 1990, response letter stated that the

Salem Administrative Procedure, SC.MD-AP.ZZ-0005,

11 Control of Contractor

Work,

11 Revision 1, had been revised.

This is a Maintenance Department

procedure and defines the requirements for control of work performed

by contractors under the direction of the Maintenance Department.

Responsibilities are clearly defined, including requirements for

monitoring of contractor work.

The procedure covers personnel

qualification, procedure requirements, and makes the Salem Handbook

of Standards a qualification requirement for contract personnel.

The

inspector interviewed three maintenance contract administrators.

Based upon the interviews and a review of maintenance monitoring

observation reports of contractors, the inspector concluded that the

Maintenance Department has a program to achieve acceptable control

over their contractors.

Engineering and Plant Betterment (E&PB)

Procedure DE-CS.ZZ-0031(0),

11 E&PB Contractor Site Qualification &

Training,

11 Revision DA, provides a program to assure that E&PB

contractors are knowledgeable of the site procedures and controls for

conducting work.

The procedure includes responsibilities for both

E&PB and contractor personnel.

The procedure also calls for job

specific briefings and training.

E&PB conducts periodic meetings

with contractors and conducts a formalized contractor evaluation

including a weekly published report card.

E&PB maintains a core of

24 contractor staff full time, 12 from Bechtel and 12 from Stone and

Webster.

Each staff is permitted to work* up to 50 craftmen with the

existing core team.

Although the E&PB did not have an overall

10

procedure delineating all of the controls, the inspector concluded,

based on interviews and sampling of documen~ation, that existing

controls over contractors, although somewhat fragmented, appeared

adequate.

-

Nuclear Services

Cognizant Nuclear Services representatives stated that Nuclear Services

Department has no formal department procedures for delineating

qualification and management controls of contractors performing

maintenance work.

They stated that their department did not use the

Maintenance Department 1s procedure for control of contractor work.

Nuclear Services was stated to have conducted the bulk of the

~aintenance work within containment the last outage.

The represen-

tatives stated that, for example, Westinghouse used their own

procedures for performing steam generator work; the procedures were

reviewed by Nuclear Services before the job.

Also, the Nuclear

Services Department qualified contractors to form NC.NA-AP.ZZ-0014-4,

which is from the Nuclear Department 1 s

11Training, Qualification, and

Certification," procedure.

A representative further said that nuclear

services only checks to see if qualifications of contractors are in

order, whereas QA verifies contractor qualification.

It was stated

that Nuclear Services conducted daily meeting with contractor managers,

e.g., Westinghouse* doing steam generator work and that all contractor

supervisors were also briefed regarding the

11Salem Handbook of

Standards.

11

An interview of a cognizant station QA person and review of station QA

surveillance report (91-049) determined that the qualification and work

history of Westinghouse people doing containment work had been verified

by QA.

A review of the

11 IR9 Outage QA critique,

11 dated May 8, 1991,

identified contractor problems relative to steam generator work under the

cognizance of Nuclear Services.

The Nuclear Services Department has not demonstrated that existing

procedures are adequate to control contractors conducting safety-related

maintenance, i.e., they meet Regulatory Guide 1.33, "Quality Assurance

Program Requirements,

11 and ANSI NI8.7-1976,

11Quality Assurance for the

Operational Phase of Nuclear Power Plants,

11 relative to administrative and

management controls.

This is an unresolved item (50-272/91-16-03, 311/

91-16-03).

In conclusion regarding

11 Poor control of contractor maintenance activities,

11

the Maintenance Department has improved their control over contractors and

this was found to be acceptable; E&PB Department 1 s control was adequate;

However, Nuclear Services Department 1 s management and administrative

controls over contractors performing safety-related maintenance were not

demonstrated and were made an unresolved item .

3.0

L

11

Conclusion of Review of Identified MTI Weaknesses

Three of the five weaknesses (numbers 2, 3, and 4) were closed.

Weakness 1,

11Management of maintenance backlog items and an absence

of an effective backlog reduction program remains open pending the

licensee demonstrating effectiveness in his backlog reduction program.

The backlog has slightly increased (worsened) since the MTI.

Regarding

weakness No. 5,

11 Poor control of contractor maintenance activities.

11

This control has improved and is at an acceptable level in the

Maintenance Department and E&PD Department; however, the Nuclear

Services Department appears to lack management and administrative

procedural control coverage for conducting safety-related maintenance

work using contractors.

This issue is an unresolved item.

During

inspection of Weakness 1, the inspector identified an apparent

inaccurate statement in the licensee's October 19, 1990, response

letter regarding the number of completed RCM analyses.

Technical Specification Surveillance Testing (61700 and 61725)

A technical specification (TS) audit project was established for the S~lem

Generating Station resulting from a series of overdue surveillance

requirement tasks identified in 1987 and 1988.

A TS verification project

was initiated in September 1988 to review the managed maintenance information

system (MMIS).

(Note:

The MMIS is a work order database program the

licensee uses to schedule surveillance requirement tasks with a frequency

of greater than 7 days).

This was subsequently expanded to include:

(1)

a Technical Specification Surveillance Monitoring Program, (2) a Technical

Specification Amendment Implementation Program, and (3) a line-by-line

reverification that all Technical Specification surveillance requirements

were covered by surveillance procedures.

The objective of the audit project was to eliminate noncompliance with TS

surveillance requirements due to improper TS scheduling, amendment

implementation, and surveillance requirement identification.

The TS audit

project included four distinct, but related activities:

(1) the MMIS

database reverification, (2) the TS surveillance monitoring program, (3)

the TS amendment implementation program, and (4) the TS surveillance

reverification project.

The results of the audit project are:

(1) all recurring tasks in the MMIS

database have been verified to reflect the TS requirements they fulfill;

(2) a PC-based database has been developed that cross-references the TS,

the procedures used to meet TS requirements, and the department responsible

for each recurring TS requirement; (3) LERs have been submitted to the NRC

for all cases of noncompliance that this program identified (Attachment 2

to this report contains a listing), and (4) administrative controls have

been established to monitor TS surveillances and insure that the present

program provides controls over TS amendments.

The completion of the audit

project and the controls the licensee has established to maintain their

present TS status should ensure that future changes will be captured by

the system and effect any needed updating.

i

12

The licensee has scheduled audits of the technical specification program

  • .for June 24, 1991, and the inservice testing program (IST) for

August 5, 1991 .. These audits are designed to test the function of the

various systems and interfaces developed as a result of the technical

specification audit project.

The inspector had no further questions regarding TS surveillance testing

within the sample taken.

No violations or deviations were found.

4.0 Inservice Test Program (IST) (Module 73756)

The

11 Inservice Testing Program Revision and Request for Interim Approval

of Second Ten Year Interval IST Program Salem Generating Station, Unit

Nos. 1 and 2,

11 dated June 26, 1987, has beeff submitted to the NRC for

approval.

In May 1991, the licensee submitted to the NRC the latest

revision of the Inservice Testing (IST) Program for Salem Unit Nos. 1 and

2.

The inservice inspection and testing programs for the Salem Unit Nos. 1

and 2 i-s described in procedures WPN-PLP-10 and AP27.

These procedures,

both titled

11 Inservice Inspection and Testing Program,

11 are implemented

at the Salem Unit Nos. 1 and 2.

The Technical Department Inservice Test-

ing Engineer maintains the status of the IST program and is developing a

system for analyzing test results and issuing trending information based

on test data.

The technical specification (TS) requirements for IST have been incorporated

into procedures. and identified in their second ten year plan.

A

verification to ensure that each TS requirements has been procedurally

covered is completed.

A Quality Assurance Audit of the TS vs. the IST

procedures is scheduled for August 5, 1991.

The Inservice Test Engineer

has completed an inspection to verify that the TS requirements for IST are

in procedures.

Procedures describing TS testing requirement have been written using the

guidance defined in procedure QA-PJ.ZZ-1031(0),

11 Procedure Upgrade Project

Manual,

11 (PUP) issued April 26, 1991.

A sample review of IST procedures

verified that such areas as post-maintenance testing are considered and

included where necessary, TS references are identified, both TS and ASME

Boiler and Pressure Vessel Code,Section XI, are referenced, and an

acceptance criteria is required.

No violations or deviations were

identified.

Attachment 2 also provides a listing of surveillance-related documents

reviewed and Attachment 3 provides completed surveillance test work orders

that were reviewed by the inspector during the course of the inspection.

These WOs were inspected to verify that the licensee met TS requirements

and tests were performed in accordance with the test procedure.

The

inspector also verified that when a requirement was not met, the required

documentation was completed and a review of the item was performed and

documented by the responsible supervisor.

13

No violations or deviations were identified.

5.0

Inspection of a Previous Unresolved Item

(Closed) Unresolved Item 50-272/89-15-01.

Improper mix of boric acid

compounds had been inadvertently used in the batching process and,

subsequently, injected in the reactor coolant system (RCS).

The licensee has revised their boron concentration operations procedures

II-3.3.6, Revision 2, for Unit 2 and procedure II-3.3.6, Revision 11, for

Unit 1 to include a verification test and sign-off by the Chemistry

Supervisor before this type of material can be issued.

A training

procedure change and retraining courses on this subject hav~ also been

given.

Based on the above actions taken by the licensee and the present controls

that have been put in place to control this material, this item is

considered closed.

The inspector found, however, that other licensee programs to control

Q-listed expendable and consumable items had not been addressed by the

licensee.

Reviews and evaluations by the licensee to assure that acceptable

programs exist to control Q-listed expendable and consumable items is

a new unresolved item.

(50-272/91-16-01, 50-311/91-16-01).

6.0

Unresolved Items

Unresolved items are matters about which additional information is

necessary in order to determine whether they are acceptable or they

constitute a violation.

Unresolved items are discussed in the details

of Sections 2 and 5.

7.0 Management Meetings

Licensee management was informed of the scope and purpose of the inspection

at an entrance meeting conducted on May 20, 1991.

The findings of

the inspection were periodically discussed with licensee personnel during

the course of the inspection.

The inspector met with the licensee

representatives (denoted in Attachment 1) at the conclusion of the inspection

on May 24, 1991.

The inspector summarized the scope and findings of

the inspection as described in this report.

Attachments:

1.

List of Individuals Contacted

2.

LERs

3.

Work Order Nos .

14

ATTACHMENT 1

Individuals Contacted

Public Service Electric and Gas Company

  • R. Brown
  • B. Connor
  • R. Donges
  • F. Kaminski
  • M. Morroni
  • A. Orticelle
  • L. Pi ott i
  • V. Polizzi
  • M. Shedlock

W. Schultz

  • E. Villar
  • C. Vondra
  • Principal Engineer, Licensing and Regulation

Technical Staff Engineer

Licensing Engineer

Inservice Testing Coordinator

Technical Department Manager

Manager, Training

Quality Assurance Auditor

Operations Manager

Maintenance Manager

Manager of Station Quality Assurance

Station Licensing Engineer

General Manager, Salem Operations

U. S. Nuclear Regulatory Commission

  • S. Barr
  • N. Blumberg
  • S. Pindale

Resident Inspector

Chief, Performance Programs Section, DRS

Resident Inspector

  • Denotes those present at the exit meeting on May 24, 1991.

Other plant, technical, and management personnel were contacted during the

course of the inspection .

15

ATTACHMENT 2

1.0 The following LERs were sent to the NRC as a result of the Technical

Specification Audit Project.

LERs applicable to both Units 1 and 2.

Unit 1

  1. 89-004

RCP Breaker Position Trip not tested.

Unit 1

  1. 89-015

Mechanical Snubbers not fully tested.

Unit 2

  1. 89-015

Containment Wide Range Pressure not calibrated wi thi.n

proper time frame.

Unit 1

  1. 90-020

Setpoint for P-6 for both units.

Unit 1

  1. 90-024

P-10 and P-12 permissives not fully tested.

Unit 1

  1. 90-035

PORV secondary indication not tested within proper

time frame.

Unit 2

  1. 90-035*

Safety Injection Input From SSPS not tested within

proper time frame.

LERs applicable to Unit 1 only.

Unit 1

Unit 1

Unit 1

  1. 89-022
  1. 89-028
  1. 89-029

TS Amendment 91 implementation problems.

TS Amendment 94 implementation problems.

AFW motor driven pumps not tested within

frame.

proper time

LERs applicable to Unit 2 only.

Unit 2

  1. 89-025

AFW motor driven pumps not tested within proper time

frame.

2.0 The following documents and surveillance test results were reviewed by the

inspectors to establish that Technical Specification (TS) surveillances

were identified, tested, and conducted on schedule.

Documentation

AP-12

AP-27

TI-28

PLP-10

Technical Specification Surveillance Program

Inservice Inspection and Testing Program

Pumps Surveillance Testing Results Analysis

Vice President Nuclear Procedure, Inservice Inspection and

Testing Programs

SP (0) 4.0.5-P (Gen)

SP (0) 4.0.5-P-BA (11)

Operations Department Surveillance Procedure

Inservice Testing - Boric Acid Pumps

Revised 1991 QA Audit Schedule

Audit Plan - Surveillance Testing (TS) Index No. 170

Audit Plan - Inservice Testing, Index No. 012


16

Surveillance No. 91-0094 - Assessment of Procedure Upgrade Project (PUP)

3.0 The following documents were reviewed by the inspector during the inspec-

tion of the sodium intrusion event of June 1989 (URR 50-272/89-15-01)

and the calibration control program for safety-related instrumentation not

specifically controlled by Technical Specifications:

Operating Procedure II-3.3.6, Revision No. 11, Boron Concentration

Control, Unit 1

Operating Procedure II-3.3.6, Revision No. 2, Boron Concentration

Control, Unit 2

Quality Assurance Audit Report No.91-142, Mechanical Maintenance,

April 1 - 26, 1991 .

Work Order Nos.

WO-NO. 910424070 Unit 1

WO-NO. 901010016 Unit 1

WO-NO. 910328082 Unit 2

WO-NO. 910227046 Unit 1

WO-NO. 901211030 Unit 1

WO-NO. 910430042 Unit 2

WO-NO. 910420069 Unit 1

WO-NO. 901021032 Unit 1

WO-NO. 91022034 Unit 2

WO-NO. 920901003 Unit 2

WO-NO. 910423090 Unit 2

17

ATTACHMENT 3

Nuclear Instrumentation System Channel

Calibration Check on Power Range Channel

IN43.

(4/8/91)

IPT457 Pressurizer Pressure Sensor CAL/CH

111 Sensor Calibration.

I&C Procedure

IPT-457 Pressurizer Sensor Calibration.

(3/11/91)

150UDC Reactor Trip Breaker B - SSTS Train

B.

Procedure NC.NA-AP.ZZ-0032-4.

Solid

State Protection System Functional Test -

Train B (4/1/91)

Containment Hydrogen Analyzer Functional

IAW Procedure lC-3.9.049 - Containment

Hydrogen Analyzer Channel Functional Check.

(4/3/91)

Rod Control System/Measure Rod Drop Time.

Procedure No. IIC-5.2.001 - Rod Drop Time

Measurement Hot Full Flow (4/22/91)

Radiation - Monitoring System/ Perform

Channel Calibration Procedure No. 2PD

4.5.011 Channel Calibration Check.

(5/1/91)

14A NIS Power Range Drawer.

Procedure No.

IIC-16.4.0.24.

Power Range Channel IN44

Detector Current Adjustment.

(4/28/91)

llSTM Gen Feed and Cond Differential

Pressure TMTR.

Procedure No. IIC-2.5.033.

Sensor Calibration.

(2/21/91)

2TE4131A/B/#23 Loop TAVG/Chan. Func./Ch.

111.

Procedure No. 2TE-431A-B #23 Rx

Coolant Loop Delta-T TAVG Prot. Ch 111.

(2/25/91)

2E11F/460V BKR Maint/21 RCP Mtr Htr.

Procedure No. M94.5 (4/25/91)

STA Batteries.

Perform Weekly TS Surveil-

lance.

Procedure No. SC.MD-ST.ZZ-0003 (Q)

(4/25/91)