Proposed Tech Specs Re Verification of Automatic Interlock Function of RHR Sys
ML18094A734
Person / Time
Site: Salem  PSEG icon.png
Issue date: 09/28/1989
From:
Public Service Enterprise Group
To:
Shared Package
ML18094A733 List:
References
NUDOCS 8910050398
Download: ML18094A734 (4)


Text

ATTACHMENT 2 EMERGENCY CORE COOLING SYSTEMS SURVEILLANCE REQUIREMENTS (Continued)

i.

The automatic interlock function of the RHR System shall be verified within the seven (7) days prior to placing the RHR System in service for cooling of the Reactor Coolant System. This shall be done by verifying with a test signal corresponding to a reactor coolant pressure of 586 psig or greater, that the lRHl and 1RH2 valves cannot be opened.

375 SALEM - UNIT 1 3/4 5-5b Amendment No.

ATTACHMENT 2 EMERGENCY CORE COOLING SYSTEMS SURVEILLANCE REQUI REM f1~NTS (Continued)

1.

The automatic interlock function of the RHR System shall be verified within the seven (7) days prior to placing the RHR System in service for cooling of the Reactor Coolant System. This shall be done by verifying with a test signal corresponding to a reactor coolant pressure of 586 psig or greater, that the 2RH1and2RH2 valves cannot be opened.

375

  • (Footnote from page 3/4 5-6)

Flow balance testing pursuant to Specification 4.5.2.h shall be performed for the first time the unit is in COLD SHUTDOWN after December 15, 1981.

SALEM - UNIT 2

.3/4 5-5b

EMERGENCY CORE COOLING SYSTEMS

. ~

SURVEILLANCE REQUIREMENTS (Continued)

i.

The automatic interlock function of the RHR System shall be verified within the seven (7) days prior to placing the RHR System in service for cooling of the Reactor Coolant System. This shall be done by verifying that with a test signal corresponding to a reactor coolant pressure of 375 psig or greater, that the lRHl and 1RH2 valves cannot be opened.

SALEM - UNIT 1 3/4 5-5b Amendment No.

L EMERGENCY CORE COOLING SYSTEMS lo>

SURVEILLANCE REQUIREMENTS (Continued)

i.

The automatic interlock function of the RHR System shall be verified within the seven (7) days prior to placing the RHR System in service for cooling of the Reactor Coolant System.

This shall be done by verifying with a test signal corresponding to a reactor coolant pressure of 375 psig or greater, that the 2RH1 and 2RH2 valves cannot be opened.

  • (Footnote from page 3/4 5-6)

Flow balance testing pursuant to Specification 4.5.2.h shall be performed the first time the un.i t is in GOLD SHUTDOWN after December 15, 1981.

SALEM - UNIT 2 3/4 5-6a Amendment No.

j