Text
. **'
December 23, ~8 Docket No. 50-272/311 Mr. Steven E. Miltenherger Vice President and Chief Nuclear Officer Public Service Electric and Gas Company Post Office Pox 236 Hancocks Bridge, New Jersey 08038
Dear Mr. Miltenberger:
SUBJECT:
ATWS RULE (10 CFR 50.62)
DISTRIBUTION Docket File NRC PDR & LPDR PDI-2 Reading SVarga/BBoger WButler MO' Brien JStone/MThadani OGC EJordan/BGrimes
- ACRS (10)
-JA~)
SC(1J&
59131 RE:
SALEM GENERATING STATION, UNITS 1 AND 2 On July 26, 1984, the Code of Federal Regulations (CFR) was amended to include Section 10 CFR 50.62, "Requirements for Reduction of Risk from Anticipated Transients Without Scram {ATWS) Events for Light-Water-Cooled Nuclear Power Plants 11 (known as the ATWS Rule).
The requirements of Section 10 CFR 50.62 apply to Salem Generating Station, Units 1 and 2.
The ATWS Rule requires specific improvements in the design and operation of conmercial nuclear power facilities to reduce the probability of failure to shut down the reactor following anticipated transients and to mitigate the consequences of an ATWS event.
The purpose of this memorandum is to forward the enclosed (Enclosure
- 1) safety evaluation report associated with the proposed implementation of the ATWS Rule.
The staff has concluded that the ATWS design proposed by Public Service for Salem Units 1 and 2 is in compliance with the requirements of 10 CFR 50.62, paragraph (c)(11.
Further, the staff's conclusion is based on the successful completion the human-factors engineering reviews noted. in sections 5., 6., 7.,
and 12. of the enclosed safety evaluation. Also, as noted in section 14., it is the staff's intention to provide future guidance regarding the Technical Specifications requirements for AMSAC, for which Public Service 1s required to provide NRC a response.
Enclosure:
As stated cc:
See next page PDI-2/PM Q,lr\\_JStone: mr
- t. )~ /'J.~ /88 89011 :30 !(:/~/
F'DR ADOCI<
F' PDI-2/D IA WButler 12 /2,J/88 J
- 122:3 05000272 PDC Sincerely,
/SI James C. Stone, Project Manager Project Directorate I-2 Division of Reactor Projects I/II Office of Nuclear Reactor Regulation
[MILTENBERGER]
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D. C. 20555 Docket No. 50-272/311 Mr. Steven E. Miltenberger Vice President and Chief Nuclear Officer Public Service Electric and Gas Company Post Office Box 236 Hancocks Bridge, New Jersey 08038
Dear Mr. Miltenberger:
SUBJECT:
ATWS RULE (10 CFR 50.62)
December.23, 1988 RE:
SALEM GENERATING STATION, UNITS 1 AND 2 On July 26, 1984, the Code of Federal Regulations (CFR) was amended to include Section 10 CFR 50.62, "Requirements for Reduction of Risk from Anticipated Transients Without Scram (ATWS) Events for Light-Water-Cooled Nuclear Power Plants" (known as the ATWS Rule).
The requirements of Section 10 CFR 50.62 apply to Salem Generating Station, Units 1 and 2.
The ATWS Rule requires specific improvements in the design and operation of co11111ercial nuclear power facilities to reduce the probability of failure to shut down the reactor
_ following anticipated transients and to mitigate the consequences of an ATWS event.
The purpose of this memorandum is to forward the enclosed (Enclosure
- 1) safety evaluation report associated with the proposed implementation of the ATWS Rule.
The staff has concluded that the ATWS design proposed by Public Service for Salem Units 1 and 2 is in compliance with the requirements of 10 CFR 50.62, paragraph (c)(l). Further, the staff's conclusion is based on the successful completion the human-factors engineering reviews noted in sections 5., 6., 7.,
and 12. of the enclosed safety evaluation. Also, as noted in section 14., it is the staff's intention to provide future guidance regarding the Technical Specifications requirements for AMSAC, for which Public Service is required to provide NRC a response.
Enclosure:
As stated cc:
See next page Sincerely,
~t.k-James C. Stone, Project Manager Project Directorate I-2 Division of Reactor Projects I/II Office of Nuclear Reactor Regulation
Mr. Steven E. M1ltenberger Public Service Electric & Gas Company cc:
Mark J. Wetterhahn, Esquire Conner and Wetterhahn Suite 1050 1747 Pennsylvania Avenue, NW Washington, DC 20006 Richard Fryling, Jr., Esquire Law Department - Tower SE 80 Park Place Newark, NJ 07101 Mr. L. K. Miller General Manager - Salem Operations Salem Generating Station P.O. Box 236 Hancocks Bridge, NJ 08038 Mr. S. LaBruna Vice President - Nuclear Operations Nuclear Department P.O. Box 236 Hancocks Bridge, New Jersey 08038 Robert Traee, Mayor Lower Alloways Creek Township Muni ci pa 1 Ha 11 Hancocks Bridge, NJ 08038 Richard W. Borchardt, Resident Inspector Salem Nuclear Generating Station U.S. Nuclear Regulatory Commission Drawer I Hancocks Bridge, NJ 08038 Richard F. Engel Deputy Attorney General Department of Law and Public Safety CN-112 State House Annex Trenton, NJ 08625 Mr. David M. Scott, Chief Bureau of Nuclear Engineering Department of Environmental Protection State of New Jersey CN 411 Trenton, NJ 08625 Salem Nuclear Generating Station Richard B. McGlynn, Commission Department of Public Utilities State of New Jersey 101 Commerce Street Newark, NJ 07102 Regional Administrator, Region I
- u. S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Lower Alloways Creek Township c/o Mary 0. Henderson, Clerk Municipal Building, P.O. Box 157 Hancocks Bridge, NJ 08038 Mr. Bruce A. Preston, Manager Licensing and Regulation Nuclear Department P.O. Box 236 Hancocks B~idge, NJ 08038 Mr. David Wersan Assistant Consumer Advocate Office of Consumer Advocate 1425 Strawberry Sauare Harrisburg, PA 17120 Scott B. Ungerer MGR. - Joint Generation Projects Atlantic Electric P.O. Box 1500 1199 Black Horse Pike Pleasantville, NJ 08232 Delmarva Power & Light Company c/o Jack Urban General Manaqer, Fuel Supply 800 King Street P.O. Box 231 Wilmington, DE 19899