ML18093A253

From kanterella
Jump to navigation Jump to search
Insp Repts 50-272/87-08 & 50-311/87-09 on 870407-10. Violations Noted.Major Areas Inspected:Licensee Responses & Subsequent Analysis & Mods of Masonry Walls Re IE Bulletin 80-11, Masonry Wall Design
ML18093A253
Person / Time
Site: Salem  PSEG icon.png
Issue date: 07/17/1987
From: Gregg H, Varela A
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML18093A250 List:
References
50-272-87-08, 50-272-87-8, 50-311-87-09, 50-311-87-9, IEB-80-11, NUDOCS 8707250206
Download: ML18093A253 (17)


See also: IR 05000272/1987008

Text

U.S. NUCLEAR REGULATORY COMMISSION

REGION I

50-272/87-08

Report No.

50-311/87-09

50-272

Docket No~ 50-311

~~---------* --- ***-

...... .

DPR-70

License No. DPR-75

Category.C

Licensee:

Public Service Electric and Gas Co.

P.O. Box 236

Hancocks Bridge, New Jersey 08038

Facility Name:

Salem Unit #1 and Salem Unit #2

Inspection At:

Hancock's Bridge, New Jersey

Inspection Conducted:

April 7-10, 1987

Inspectors:~~~

f&r A. A. Vareia)Ledeador Engineer

NRC Contractor Personnel:

M. E. Nitzel, EG&G Idaho

M. J. Russell, EG&G Idaho

Approved by:~~~

H. I. Gre~Chief

Materials & Processes Section, EB, DRS

~e

Inspection Summary:* Inspection on April 7-10, 1987 (Inspection Report

Nos. 50-272/87-08 and 50-311/87-09) _

-

.

, *.-

.

.

Areas Inspected: A special announced inspction by a regional-:based inspector

and two contractor personnel was cohduted at the licensee's-engineering office

and the Salem 1 and 2 plant sites.

The inspection encompassed review of

1 i censee responses and subsequent *analysis and modifications of masonry wa 11 s

related to IE Bulletin 80-11, Masonry Wall Design.

The inspection included a

walkdown of existing walls affecting safety related e,ql!iP~~ri~, a revi_ew of

design_ analyses and a review of work packages on wall modfffcations.

Results:

Two violations were identified.

8707250206 870717

PDR

ADOCK 05000272

G

PDR

DETAILS

1.

Persons Contacted

Public Service Electric and Gas Company

  • R. A. Burricelli, General Manager Engineering and Plant Betterment
  • R. Crapo, Principal Engineer
  • R. L. Gura, Manager Engineering
  • D. J. *Jagt, M~nager Project Engineering
  • J. Kowalewski, QA Engineer
  • F. Parkell, Civil Engineer
  • D. A. Preston, Manager Licensing

M. Rosenzweig, Manager QA Engineering and Procurement

E. Rozovsky, QA Engineer

W. R. Schultz, Manager QA Programs and Audits

T. Taylor, Manager E&PB Controls

D. Tauber, QC Supervisor

  • D. Vito, Senior Engineer Licensing

NRC Contractor EG&G Idaho, Inc.

  • M. E. Nitzel, Engineer Specialist
  • M. J. Russell, Engineer Specialist
  • Attendees at Exit Meeting April 10, 1987.

2.

Inspection Purpose And Scope

The purpose of this inspection was to review with cognizant and

responsible licensee representatives, at the corporate office and the

plant, the completeness of their response~ to NRC/IE Bulletin 80-11,

Masonry Wall Design .. The scope of the inspection included a review of

engineering design and quality assurance documentation relating to

inspection, testing, analysis and modifications satisfying requirements

and licensee commitmerits with respect to the bulletin. A walkdown

inspection of the plant verified repairs and/or modifications relating to

the bulletin.

3.

Review Criteria

The latest revision of the bulletin was used to define required actions

by the utility. *In addition, Temporary*Instruction (TI) 2515/37 was used

to further define in~pection requirements.

Applicable sections of the

Code of Federal Regulations (10 CFR 50) were used. *

3

4.

Review Of Licensee Responses

The inspection team reviewed bulletin responses available from NRC files

prior to the inspection .. These responses included reports addressing the

re-evaluation methodology, acceptance criteria, wall configurations and

functions, structural adequacy, proposed modification plans, and modifi-

cation schedules.

Table 1 lists those documents reviewed prior to the

inspection.

Any items of noncompliance or those requiring fu~ther dis-

cussion. were noted as i terns to be addressed while at the corporate office

or plant site. Questions relating to licensee responses were fowarded to

the licensee in advance of the inspection as a preliminary agenda for

discussion. These questions are presented in Table 4.

The inspection team reviewed additional material provided by the licensee

during the inspection.

This material consisted of calculations concerning

poss.ible masonry wall modifications, engineering procedures in effect at

the time of the bulletin work, quality control (QC) and quality assurance

(QA) procedures in effect at the time of the bulletin work, licensee

internal correspondence pertinent to bulletin ~ctivities, Design Change

Request (OCR) forms for the wall modifications, and field inquiries re-

lating to the wall modifications.

The pertinent documerits described above

for IEB 80-11 are listed in Table 2, except for licensee performed

calculations.

It should be noted that several calculations were reviewed.

Calculations

performed by the licensee

1 s consultant are included in the reports listed

in Table 1.

Calculations performed by the licensee for the design of

wall modifications were requested; however, only a few were available for

review.

Because the calculations performed by the licensee were found to

be inadequately contro1led no useful reference to them could be included

in this report.

(See Violation Number 2, below)

Findings:

It was determined from the review of the documentation de-

scribed above that, in general, most aspects of the work done in response

to the subject bulletin were acceptable.

Ho~ever, two violations were

identified during the reviews described above.

Further details regarding

these items are given below.

Viol*tion Number 1:

Criterion V of Appendix B to 10 CFR 50 states in part that

11Activities

affecting quality shall be prescribed by documented instructions,

procedures ....

11

Further, it states,

11Instructions, procedures, or

drawings shall include appropriate quantitative or qualitative acceptance

criteria for determining that important activities have been satis-

factorily accomplished.

11

The licensee's Quality Assurance (QA) program

incorporated 10 CFR 50, Appendix B, prior to the issuance of the bulletin.

Also, Action Item 1 of IEB 80-11 requires that the licensee

11 Identify all

masonry walls in your facility which are in proximity to or have attach-

ments from safety-related piping or equipment such that wall failure could

.*

  • 4

affect a safety-related system." Action Item 4 of IEB 80-11 required that

the identity of the subject walls be reported within 60 days of the

issuance.of the bulletin.

Description of Circumstances:

A review of the docketed submittals showed that the licensee performed a

masonry wall survey during 1980 which was used as the basis of the*

required 60 day response transmitted in a letter dated July 2, 1980.

During the inspection, the licensee was asked what specific procedure was

used to determine which walls were safety-related and, thus subject to

IEB 80-11 action.

The licensee was also asked what specific procedure

was ~sed to perform the field survey~ required as part of the bulletin

response.

The licensee's verbal response to these questions indicated

that the subject walls were identified by a drawing review; however, no

procedure was used to govern this activity and no clear documentation

.trail existed to describe the process or results. With regard to the

field surveys, the licensee stated that mirked-up drawings were used to

indicate which masonry walls were to be field surveyed and that all wall*

attachments were to be noted.

However, no documented procedure governed

the survey activity. A review of the document'ation available during the

inspection did not disclose any documented procedures gov~rning the

determination of safety-related walls or field survey activities. It was

found that the field survey was initiated via an internal memo and did

not reference any documented procedures.

The licensee stated that most

field survey information was passed between organizations by telephone

conversations.

Canel usiOn:

Contrary to the requirements of 10 CFR 50, Appendix B, the determination

of which masonry walls were safety-related and the 1980 wall survey

performed by the 1 i censee were not' performed utilizing documented and

controlled procedures.

This lack of procedural ~ontrol over activities

which could affect safety-related components and/or systems is a viola-

tion of 10 CFR 50, Appendix B, Criterion V.

(50-272/87-08-01 and

50-311/87-09-01).

Violation Number 2:

  • Criterion III of Appendix B to 10 CFR 50 states in part that, "The design

control measures s~all provide for verifying or checking the adequacy of

design .....

11

Also, the licensee's own Engineering Directive EDD #4

(Revision 1), Section 4.2, states that,

11 *** calculations shall be

recorded on documents identified in the EDODP, Section 4, and shall be

added to the Design History as appropriate.

11

Further, Action Item 2 of

IEB 80-11 requires the demonstration of the structural adequacy of all

subject masonry walls.

  • ~*

5

Description of Circumstances:

Prior to the inspection, the licensee was notified to have available for

audit all calculations performed for the evaluation of masonry wall

-structural adequacy.

The licensee was also notified to have all

calculations regarding masonry wall modifications available for audit.

During the inspection it was found that reevaluation calculations for all

walls could not be produced. The results of ana Tyses performed by the

licensee's consultant (Computech) were available; however, the a~alyses

themselves were not.

Thus, the finite element models and other parameters

actually used in the computerized analyses could not be verified.

OnJy

certain walls as identified in the licensee's submittals were computer*

analyzed, the remaining walls were analyzed by hand calculations or, in

some cases, the licensee's submittals *state that "Wall was not analyzed

since corrective action will prevent its failure during a seismic

event ....

11

During the review of documentation provided by the licensee

during the inspection, some hand calculations regarding wall structural

adequacy and modification~ were found (for example, control room block

wall calculations and. plating and beam stiffener modification on a wall at

elevation 122').

However, these calculations.appea~ed to be uncontrolled

since they were not identified by an individual calculation number, signed

by a checker, etc ..

By the end of the inspection, the licensee had not*

produced evidence that reevaluation calculations existed for each safety-

related masonry wall or that structural adequacy calculations existed for

all wal.l modifications.

Procedures were in place at the time of the

bulletin responses that would have required the control of design inputs

such as calculations.

Conclusion:

The inspectors found that the licensee did not have recorded, controlled

calculations demonstrating the structural adequacy of all the subject

walls and the modifications which had been made to them.

This is a.

violation of the licensee's own Engineering Directive EDD #4 and a

violation of Criterion XVII of 10 CFR 50, Appendix 8.

(50-272/87-08-02

and 50-311/87-09-02).

5.

Inspection Follow-Up Item

During the inspection, the licensee was ask~d what measures were being

taken to assure that the physical condition (absence of cracks, boundary

conditions, .etc.) of the walls would be maintained.

The licensee stated

that periodic surveillance of the subject masonry walls would be performed

to ensure that the physical conditions assumed during the reanalysis ef-.

fort remain valid. It was noted that no such plan was currently in

existence.

The licensee did produce a draft of a procedure for surveil-

lance of plant conditions that included masonry walls; however, this.

procedure was general in nature.

The licensee stated that the general

procedure would be modified or a new procedure developed to include

! .

6

specific guidance defining the period of inspection and the attributes

of each masonry wall that must be examined and the standards for accept-

ability.

The licensee committed to forward the completed surveillance

procedure to .the NRC Region I office.

6..

Verification Walkdown Inspection

A physical inspection of certain masonry walls subject to bulletin action

was conducted.

The walls .included in this sample were chosen by the

inspection team.

The purpose of this walkdown was to verify samples of

inspections and/or modifications required by the bulletin. The walls

shown in Table 3 were ~xamined. Walkdown activities concentrated on

determining if the physical characteristics of the walls as observed in

  • the plant reasonably matched those data used in the walt reevaluation

calculations and/or modification packages.

Examples of those items spot

checked during the.walkdown include overall dimensions, bond type, number

of wythes, boundary conditions, attached equipment, and equipment in

proximity,

Findings:

The results of _the plant walkdown indicated that, in gen~ral,

the configurations of the walls and the applicable modifications agreed.

  • with information found in the modification package~. . Upon examination of*

th~ wall designated as 2-4A (elevation 100 1 , separating units 1 and 2) jt

was noted that a through-wall crack exists near the west boundary.

This

crack starts in the mortar between the fifth and sixth courses of block

and proceeds vertically through both block ~nd mortar joints to the mortar

joint between the twelfth and thirteenth courses of block.

The crack then.

proceeds horizontally to the west boundary.

This crack was not addressed

in the information available to the inspecti-0n team; thus, it was

concluded that it wa~ not taken into account in the wall reanalysis

effort. Also, it Was noted that eight pipe supports were mounted on the

Unit 2 (north) side of this wall.

The licensee was asked to provide

information describing in detail the magnitude of the loads on this wall

and how they were incorporated into the structural analysis. The licensee

subsequently supplied information concerning the magnitude of these loads.

A review of this information disclosed that certain of these loads were i~

excess of the licensee's definition of a significant wall load (100

pounds).

Additional review of the report of the analysis of this wall

performed by the licensee's consultant could not confirm that these loads

had been included or, if so, the resulting effects.

Thus, the structural

adequacy of this wall was considered inconclusive.

This is an unresolved

item pending:

a.

Detailed information that demonstrate the magnitudes and methods

used by their consultant to incorporate _the pipe support loads in

their reported analysis .

b.

___ ___

7

Either the results of a reanalysis of the subject wall including the

effects of the degraded boundary due to the area of through-cracking

or documentation regarding the repair of this wall.

The licensee

stated that if the wall is repaired, the applicable repair pro-

cedure(s) and complete documentation showing successful restoration

of structura 1 adequacy wi 11 be provided.

The 1 i censee a 1 so stated

that an analysis of the probable initiating cause of this crack

and an assessment of the probabilities of its recurrence would be

provided (50-272/87-08-03 and 50-311/87-09-03).

7.

Licensee Administrative Controls and Assurance of Quality

8.

The licensee QA Manual, Document No. QAP-3 dated July 6, 1976 establishes

design responsibilities for documenting the design control and review

procedures and implementation thereof for safety related structures for:

Design responsibility within PSEG

Design responsibility of Contractors

This design interface is committed to be in accordance with 10 CFR 50,

Appendix B.

QAP-3 also requires PSEG QA Department (QAD) to review/audit

the conformance of the appropriate departments within PSEGS Engineering

and Construction for design control to Appendix B .

The inspector ascertained from his review of documentation presented by

the licensee during this inspection identified in Table 5 that no formal

audit had been performed of the masonry wall survey activities required

by bulletin 80-11 item number 1.

Neither was there QA/QC oversight of

design activities to establish wall structural adequacy and design of

wall modification.

PSEG internal memorandum, dated May 14, 1980 from QA

Manager to the General Manager Electrical Production required appropriate

action in response to bulletin.

The memorandum required that wall

evaluation be accomplished in conjunction with PSEG Engineering Department.

The licensee was requested prior to the inspection.

(Table 4, Questions 2

and 9) and during the inspection to provide assurance of quality in these

activities, however, no documentary evidence of design control audits were

produced.

Conclusion

Based on the results of this inspection and, pending the licensee's

response to the violations and open items in this report, IEB 80-11

remains open.

9.

Exit Meeting

An exit meeting was conducted on April 10, 1987, by the NRC inspector.

Attendees at the meeting are listed in paragraph 1.

The NRC inspector

summarized the inspection findings and the licensee acknowledged these

findings.

No written material, other than that described in paragraph 4

(preliminary agenda for discussion) was furnished to licensee personnel.

Document

8

Table 1 - DOCUMENTATION REVIEWED PRIOR TO INSPECTION

Description

F. Schneider (PSEG) letter to B. Grier (USNRC; RI) d~ted

7-2-80 transmitting licensee's 60 day response to !EB

80-11, for Salem #1.

R. Mittl (PSEG) letter to B. Grier dated 9-5-80 trans-

mitting additional information regarding factors of safety

used in licensee masonry wall evaluations, for Salem #2.

Draft of criteria for the reevaluation of concrete masonry

walls at Salem Nuclear Generating Station prepared by

Computech Engineering Services, Inc. (Computech).

Draft is

dated October, 1980.

F. Schneider letter to B. Grier dated li-4-80 amending

licensee 60 day response to !EB 80-11 and requesting an

extension for submission of the required 180 day report, for

Salem #1 .and #2.

E. Brunner (USNRC, RI) letter to F. Schneider dated

11-19-80 approving delay in schedule for bulletin response.

F. Librizzi (PSEG) letter to B. Grier dated 11-24-80

transmitting Licensee Event Report (LER) 80-56/0lT.

LER

notifies of discrepancy between construction specification

and detail drawings for certain masonry walls, for Salem #1.

H. Midura (PSEG) letter to B. Grier dated 12-1-80

transmitting description of reportable occurrence

80-56/0lX-l which states that eight additional masonry

wall areas were constructed not in accordance with

specifications, for Salem #1.

B. Grier letter to R. Eckert (PSEG) dated 12-9-80

transmitting requirements for wall repairs prior to

resumptiom of operation.

F. Schneider letter to B. Grier dated 12~4-80

transmitting report of the bulletin responses (180 day

report) for Salem Unit 1.

Internal NRC memo by J. Kerrigan (NRC Project Manager)

dated 12-11-80 summarizing the results of a site meeting

on 11-20-80 between NRC and licensee representatives, for

Salem #1 and #2.

Document

9

Table 1 - DOCUMENTATION REVIEWED PRIOR TO INSPECTION (Cont'd)

Description

Internal NRC Memo for NRC Commissioners dated 12-30-80,

from H. R. Denton, Consideration of Full Power Operating

License for Sa:l em Unit 2", proposed wa 11 capacity

  • strengthening program for non-conforming As-Built

condition.

Internal NRC memo by W. Ross dated 12-30-80 which

summarizes results of a meeting between NRC and licensee

representatives held on 12-5-80 to discuss seismic design

deficiencies in Controlled Facilities Building, for Salem

  1. 1.

R. Tedesco (NRC) letter to R. Mittle dated 1-8-81

requesting additional information regarding bulletin

response activities.

R. Mittle letter to F. Miraglia (NRC) dated 1-29-81

responding to the 1-8-81 request for additional

information.

R. Uderitz (PSEG) letter to B. Grier dated 4-1-81

transmitting LER 80-56/0lX-2 regarding discrepancies

between construction arid specifications for Controlled

Facilities Building walls.

F. Schneider letter to B. Grier dated 12-10-80

transmitting 180 day report of bulletin response

activities for Salem Unit 2.

D. Eisenhut (NRC) letter to R. Mittle transmitting

operating licensee for Salem Unit 2.

License contains

required licensee actions prior to full power operation

(includes some requird actions on masonry walls).

E. Liden (PSEG) letter to S. Varga (NRC) dated 12-8-82

transmitting additional information regarding IEB 80-11

responses.

Internal NRC memo from J. Knight to G. Lainas dated

7-15-83 forwarding Safety Evaluation Report (SER) for

Salem Units 1 and 2 .

Document

66128

2EC-1049

QAI

360

lEC-1048

2EC-2140

SFC-4

GM8-EMP-005

A-5-SOOO-SGS-O

10

Table 2 -.DOCUMENTATION REVIEWED DURING INSPECTION

Description

PSEF Research report on masonry wall testing. and

inspection at Salem units 1 and 2.

F. Linn (~SEG) l~tter to L. Jones (Computech Engineering

Services) dated 11-20-80 transmitting information

regarding wall survey data and analysis instructions.

PSEG Design Change Request (OCR) for modifications to

masonry walls at Salem Unit 2.

-*

PSEG Quality.Assurance (QA} manual, revision 52

(select~d sections reviewed).

E. Henrys (The E.P. Henrys Companie~) letter to

F. Parkell (PSEG) certifying masonry block use in

construction meets ASTM C-90 ..

  • PSEG Engineering Directiv~ #1 - Operational Design

Change Control.

Nonconformance Report (NRC) 360 regarding material

traceability of material used on OCR lEC-1048.

PSEG OCR to modify masonry walls in Salem Unit 1.

PSEG OCR to modify previously modified masonry wall on

elevation 122'-0 11

PSEG internal letter from G. Kapp to Assistant

Engineering Managers regarding OCR lEC-1594, Post

Installation Engineering, Review, and Document Update.

Letter is dated 1-25-84. *

PSEG Structural Field Directive #4 - directs *that no

reinforcing steel rods may be cut without approval of the

structural engineer. *

PSEG engineering procedure governing the initiating,

performance, and documentation of calculations. *This is

the current revision in use.

This document was used to

compare to similar engineering procedures in use at the

time of the bulletin re~nalyses. *

PSEG draft procedure for inspection of civil/structural

items at Salem Units 1 and 2 Hope Creek.

Document

11

Table 2 - DOCUMENTATION REVIEWED DURING INSPECTION (Cont'd)

Description

PSEG Engineering Directive #4 regarding control of

design input and verification.

Dated 5-19-81.

Lic~nsee

stated that this document was in effect at the time of the

masonry wall modifications.

PSEG Engineering Dep~rtment Organization and Design

Procedures (EDODP) Section 8 regarding design input.

PSEG Engineering Department Organization and Design

Procedures (EDODP) Section 11 regarding design

verification.

PSEG Structural Division organization and procedures

manual (selected sections reviewed).

12

Table 3 - MASONRY WALLS FIELD VERIFIED

Wall

Elevation (ft)

Location

1-1

64

Aux i 1 i a ry B.l dg. 1

1-2

84

Auxiliary Bldg.

1-3A

84

Auxiliary Bldg.

1-38

84

Auxiliary Bldg.

1-3C

84

Auxiliary Bldg.

1-3D

84

Auxiliary Bldg.

1-3E

84

Auxiliary Bldg.

1-6

100

Auxiliary Bldg.

1-10

122

Auxiliary Bldg.

1-13

Cont. *Fae. Bldg. (east wall)

1-14a

Cont. Fae. Bldg. (truck bQ.y}

1-14b

Cont. Fae. Bldg. (truck bay)

2-1

64

Auxiliary Bldg. 1

2-2

84

Auxiliary Bldg.

2-3A

84

Auxiliary Bldg.

2-3b

84

Auxiliary Bldg.

2-3C

84

Auxiliary Bldg.

2-3D

84

Auxiliary Bldg.

2-3E

84

Auxiliary Bldg.

2-4A

100

Auxiliary Bldg. 2

2-4B

100

Auxiliary Bldg. 2

2-4C

100

Auxi 1 iary Bldg. 2

2-5

100

Auxiliary Bldg.

2-9A

122

Auxiliary Bldg.

2-9B

122

Auxiliary Bldg.

2-10

122

Auxiliary Bldg.

2-16

122

Auxiliary Bldg:

Note:

1.

This was divided into three walls for analysis.

2 . * Common wa 11 to Units 1 and 2.

    • I

13

Table 4 - REQUEST FOR INFORMATION

The following is a list of preliminary requests for information pertinent

to actions taken in response to the*subject bulletin.

It is planned that the

responses to these requests will be reviewed and discussed during the

inspection.

1.

How was the overall engineering effort for response to bulletin

requirements o~ganized, coordinated, and directed?

2.

How was QA/QC involved in the overall effort .to satisfy bulletin,

requirements?

3.

What AE/consultant firms (if any) were used to develop bulletin

responses?

What was the extent of their involvement (scope of work)?

4.

What personnel qualifications and/or special training was pr6vided (or

required) for licensee and/or consultant personnel involved in bulletin

response work?

5.

What procedure was used to identify masonry walls subject to bulletin

action?

Provide a copy for review.

6.

What procedure was used to compete the wall date sheets or survey forms;

ie., were these data based on field surveys, con~truction records or

other sources?

7.

If field surveys were used, provide the procedure used and marked up

drawings or other first generation field documentation showing results

obtained.

8.

Have any additional safety related p1p1ng systems be~n found to have

supports attached to the subject ~alls?

9.

Provide documentation of QA oversight/audits of all contract

organizations involved in bulletin actio~s.

10.

Information regarding all ~alls subject ~o bulletin action should be

readily available at the beginning of the inspection.

Provide the

reevaluation calculations and complete modification *packages (wh~re

applicable).

Modification packages should include all stress

calculations, design/construction drawings, QC documentation and any

other pertinent information such as nonconformance reports (NRC 1 s) and

their dispositions that may exi~t.

14

11.

Provide the .surveillance plan for routine inspecti9n to assure the

continued validity of assumed boundary conditions, physical condition

(such a~ absence of cracks) and continued structural adequacy.

12.

Describe the procedure(s) used to control addition to or changes in the

configurations of the masonry walls subject to bulletin action.

Provide

copies for review.

13.

Have any recent resurveys been ~ndertaken to ascertain that plant

  • modifications or regulatory requirement made in the intervening time

since 1980 have not changed the status or classification of any masonry

walls?

14.

Were any unreinfbrced walls found to have cracks? . If so,

a.

Which walls were found to contain cracks?

b.

Were they reanalyzed to account for the cracked sections?

c.

Were the cracks repaired or was any other corrective action taken?

d.

If the cracks were repaired provide the governing procedure and

samples of documentation demonstrating successful rep~ir completion.

15.

List all computer codes used in the wall reevaluations.

Also, identify

which groups or organizations used them

16.

Were all computer codes (including the SAPIV pre and post processors)

used

11benchmarked?

11

If so, provide documentation.

17.

What procedure(s) were used to assure that computer codes were used

properly to obtain accurate results?

Provide copies for review.

18.

The 7-2-80 Schneider - Grier letter (60 day response) states that

11all

partition and battery room walls are filled solid with mortar and heavily

reinforced in both directions.

11

However, sketches of the walls presented

in later submittals indicated that rebar does not extend the full height

of the walls.

Clarify whether these walls do in fact have rebar

extending the full height and if tredit was taken for the horizontal

reinforcing (dur-o-wall) in the analyses.

19.

The GO day response states that drawings were consulted and accessible

areas of the plants were walked down. What walls were not completely

accessible? Were walkdowns of inaccessible areas subsequently

performed? If so, when?

20.

The 11-4-80 Schneider - Grier letter states that seven control air piping

system supports were found mounted on a masonry wall.

The letter further

states that the imposed loads are small.

List the loads used for these

15

pipe supports in the wall analyses.

How were the piping loads calculated

(ie., hand calcs, computerized dynamic analyses, etc.)?

How were these

loads incorporated in the wall analyses (ie., absolute sum of DW, TE,

seismic, etc. or some other technique)? Did the piping loads used

reflect accurate as-built information and analyses such as would have

resulted from other bulletins (I~B 79-02, IEB 79-14, etc.) or plant

modifications?

21.

The 12-1-80 Midura - Grier let~er deicribes reportable occurrence

80-56/0lx~l. This letter states that eight masonry walls were found to

be not erected per design.

Clarify what these discrepancies were and how

they differed from those discussed at the 11-20-80 site meeting between

by the NRC and licensee.

This letter also states that a detailed report

would be prepared and submitted;. however, no such report was discovered*

in a search of docket files.

Provide a copy of this report.

22.

What procedure and QC measures were taken to verify that all equipment

was accounted for in the data for each wall shown in section 3 of the

final reports?

23.

A discontin~ity was observed in the numbering of the unit 2 walls in

section 3 of the unit 2 report.

In particular, there were no walls 2-6,

7, .8, 11, 12, or 14 listed.

We~e these walls designated but determined

not to be safety-related? Clarify the numbering scheme used.

24.

Section 4 of the unit 1 and unit 2 reports doesn't really fully describe

construciton practices used in the walls.

Provide the construciton

specifications(s) used for original construction.

25.

Section 1.0 of the Computech re~ort references drawings and also says

that recent modifications, not shown on the drawings, were incorporated

in the analyses.

Was this information the result of a walkdown by

Computech personnel?

If not, who provided the information?

In any case,

what QC was provided to verify the accuracy of the informatioh? Were

"recent modifications" made prior to the issuance of the bulletin or did

they result from preliminary bulletin activities?

26.

Section 1.0 of the Computech report (both plants) states that "no

additional stregthening of any wall is required." However, as shown in

Sect ion 3 of the main report, wa 11 s. were modified.

Clarify whether the

modifications mentioned in Section 3 are the "recent modifications"

referred to in question 25 or are a separate set of modifications.

27.

Section 3 of the unit 1 ~nd unit 2 reports indicate that a number of

walls were deemed as needing corrective action by inspection and, thus,*

were not analyzed.

What basis.was used to determine adequacy of the as-

modified condition?

Provide the calculations for the modifications

showing structural adequacy of the walls in their final configuration

including all attached steel, bolts, etc. used in the modifications.

16

28.

What QC coverage was applied to the masonry wall testing and in5pection

program described in the procedure contained in Appendix B-1?

Provide

evidence of QC activities.

29.

Clarify the QC role in the block core fill verification program described

in Appendix B-2.

Was QC applied to all activities on a continuous

basis?

Provided evidence of QC activities.

30.

Correlate the individual wall numbers used in Section 3 of the report to

the sketches shown in Appendix D (ie., show the PSE&G wall numbers -0n the

sketches).

31 ..

How was the grouting procedure contained in Appendix D issued and

controlled?

Provide evidence of QC coverage of this activity.

17

Table 5 - DOCUMENTATION OF LICENSEE ADMINISTRATIVE CONTROLS

Document

QAI 18-1

QAI 2-5

QAI 3-1

QAI 2-12

QAD Audit M-80-01

QAD Audit M-80-01

QAD Audit M-80-:,01

QAD Audit S~80-14

QA Audit S;..80-14

Project QA Plan

PSEG Mechanical

Design Manual

CI Procedure

Manual

,Description

PSEG internal memo dated 5-14-80 from E. N. Schwalje,

Manager of QA to Sale~ Unit #1.

General Manager -

Electrical Production F. P. Librizzi ori r~-evaluation ~f

design adequacy of masonry walls as required by IEBU 80-11.

QAM Instruction; revision 7, Audits by the Auality ..

Assurance Department 1-23-79, and revision 8, 9-4-81.

QAM Instruction, revision 5, 4-10-79, and revision 6,

11-12~81, Surveillance Program.

QAM Instruction, revision 3, 6-21-79, Design Control

Program.

QAM Instruction, rev1s1on 1, Processing of NRC Bulletins,

Circulars and Information Notices.

QA Department Audit of PSE&G Engineering Department

and Purchasing March 24 - April 3, 1980.

Corre~tive Action Request SE-34 dated 12-10-80.

Response to CAR SE-34 Accepted 2-19-81.

Audit of Catalitic, Inc. (CI) (Masonry Wall Modification*

Contrac~or) July 30 - August 1, 1980, covering QA.review

of Cl's Management Audit Reports for 1979 in reference to

10 CFR 50, Appendix B Criterion II, III, IX, XVI, XXVI,,

and XVIII.

Corrective Action Re~uest dated 8~5-80.

Manenan~e and Modifications at Sale~ dated 6-1-78.

Operational Design Change Control, revision 3

CMP-4 job rev1s1on 2 completion and walkdown/PSEG

approval of masonry wall modifications - design

design changes.

(SAMPLE) PSEG Salem Resident QA Department Surveillance Log, No. 791,

Walkdown/CMP-4 Surveillance of Masonry wall modification by CI of struct.ural

st~el and bolting, OCR #lEC-1048.