Docket No. 50-311
Public Service Electric and Gas Company
ATTN:
Mr. Corbin A. McNeill, Jr.
Vice President - Nuclear
P. 0. Box 236
Hancocks Bridge, New Jersey 08038
Gentlemen:
Subject:
Inspection No. 50-311/85-08
APR 2 5 1985
This refers to the special readiness assessment team inspection conducted by
Mr. Thomas Kenny and others of this office. The inspection, conducted March 21
and 22, and March 25-29, 1985 at the Salem Generating Station, Hancocks Bridge,
New Jersey, reviewed activities authorized by
NRC License No. DPR-75.
The
results of this inspection were discussed with Mr. J. M. Zupko, Jr., and other
members of your staff on March 29, 1985.
Areas examined during this inspection are described in the NRC Region I Inspec-
tion Report which is enclosed with this letter.
Within these areas, the in-
spection consisted of selective examinations of procedures and representative
records, interviews with personnel, examinations of work completed on modifica-
tions, and observations by the inspectors.
Based on the results of this inspection, it appears that one of your activities
was not in full compliance with NRC requirements, as set forth in the Notice of
Violation, enclosed herewith as Appendix A.
The violation has been categorized
by severity level in accordance with the revised NRC Enforcement Policy ( 10
CFR 2, Appendix C) published in the Federal Register Notice (49 FR 8583) dated
March 8, 1984.
You are required to respond to this letter and in preparing
your response, you should follow the instructions in Appendix A.
In addition to the violation, several other concerns were identified by the
inspectors. These concerns are described within the report and they appear to
be isolated instances. However, your attention to these concerns was adequate-
ly addressed by your staff while the inspection team was at the site.
The responses directed by this letter and the accompanying Notice are not sub-
ject to the clearance procedures of the Office of Management and Budget as
required by the Paperwork Reduction Act of 1980, PL-96-511:
8505070202 850425
ADOCK 05000311
G
OFFICIAL RECORD COPY
IR50-311/85-08 - 0001.0.0
04/04/85
APR 25 1985
Public Service Electric & Gas Co.
2
Your cooperation with us in this matter is appreciated.
Sincerely,
Samuel J. Collins, Chief
Projects Branch No. 2
Division of Reactor Projects
Enclosures:
1.
Appendix A, Notice of Violation
2.
NRC Region I Report 50-311/85-08
cc w/encls:
J/'R. L. Mittl, General Manager - Nuclear Assurance and Regulation
.......--J. M. Zupko, Jr., General Manager - Salem Operations
.z...----e. J. Johnson, General Manager Nuclear Quality Assurance
~E. A. Liden, Manager - Nuclear Licensing and Regulation
......---p. M. Krishna, Manager - Nuclear Review Board
.,,,,,,.-M. J. Wetterhahn, Esquire
~R. Fryling, Jr., Esquire
Public Document Room (PDR)
Local Public Document Room (LPDR)
NRC Resident Inspector
.VState of New Jersey
.,.,,,,,--J, H. Rodriquez, Public Advocate of the State of New Jersey
bee w/encls:
,ef'Region I Docket Room (with concurrences)
~Senior Operations Officer (w/o encl)
,._.-J,* Linville, Section Chief, DRP
I/' Di rector, DRS
v
Di rector, .DRSS
,,,_.--- H. R. Denton, D/NRR
Y- J. Taylor, D/OIE
,.;---H. Thompson, Jr., D/DL, NRR
......-J. Partlow, D/DP, IE
- Jk, Jordan, D/DEPER, IE
W~I:DRP
. *:.,,__ Kenny /mj d
"xi RI:DRP
~¥Norrholm
@I:DRP
Co 11 ins
4/ /!J/85
I
- -*
4{,1' /85
OFFICIAL RECORD COPY
IR50-311/85-08 - 0002.0.0
04/18/85