3/29/18 Summary of Public Meeting Southern Nuclear Operating Company to Discuss Issues Associated with the Safety Review of Licensing Actions for Vogtle Electric Generating Plant Units 3 and 4
ML18092A305
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 04/09/2018
From: Jordan Hoellman
NRC/NRO/DNRL/LB4
To: Jennifer Dixon-Herrity
NRC/NRO/DNRL/LB4
hoellman j/415-5481
References
Download: ML18092A305 (8)


Text

April 9, 2018 MEMORANDUM TO:

Jennifer Dixon-Herrity, Chief Licensing Branch 4 Division of New Reactor Licensing Office of New Reactors FROM:

Jordan Hoellman, Project Manager /RA/

Licensing Branch 4 Division of New Reactor Licensing Office of New Reactors

SUBJECT:

SUMMARY

OF A PUBLIC MEETING WITH SOUTHERN NUCLEAR OPERATING COMPANY ON MARCH 29, 2018 The U.S. Nuclear Regulatory Commission (NRC) staff held a Category 1 public meeting with Southern Nuclear Operating Company (SNC) on March 29, 2018. The purpose of the meeting was to discuss issues associated with the safety review of licensing actions for SNCs Vogtle Electric Generating Plant (VEGP) Units 3 and 4.

The meeting notice can be found in the Agencywide Documents Access and Management System (ADAMS) under Accession No. ML18047A444. The meeting notice is also posted on the NRC public website. Enclosures 1 and 2 are the meeting agenda and attendance list for the meeting, respectively. The other documents referenced during the discussion can be found at the ADAMS Accession Nos. given below:

Draft Request for Additional Information (RAI)

Responses for License Amendment Request (LAR)

- ML18081A570 17-037, Changes to Tier 2* Departure Evaluation Process Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Closure Notification (ICN) and Uncompleted - ML18081A219 ITAAC Notification (UIN) Comment Status Sheet SNC Responses to ICN and UIN Comment Status Sheet

- ML18089A048 CONTACT:

Jordan Hoellman, NRO/DNRL (301) 415-5481

J. Dixon-Herrity Summary of Meeting:

On March 29, 2018, staff from the NRC conducted a public meeting with representatives from SNC to discuss issues associated with the safety review of licensing actions for SNCs VEGP Units 3 and 4. Specifically, the meeting discussed (1) SNCs draft RAI responses regarding LAR 17-037 and (2) items 1, 2 and 4 on the ICN and UIN comment status sheet.

The first topic discussed was SNCs draft RAI responses regarding LAR 17-037. In the response to RAI Question 1, the staff noted that the last sentence of the fourth paragraph should include dimensional fabrication, assembly, erection, inspection, examination, and testing requirements as defined by the American Society of Mechanical Engineers (ASME)

B31.1 Code in addition to design requirements and as required by the Tier 2* text in Updated Final Safety Analysis Report, Subsection 5.2.1.1 related to Chemical and Volume Control System piping inside containment. SNC agreed that the additional text would be added to the response when formally submitted. The staff noted that the response to RAI Question 2 addressed the staffs question and no further discussion was needed. Regarding the response to RAI Question 3, SNC requested that the staff provide specific examples of the staffs concerns with the related to evaluating changes to motor-operated and power-operated valves.

The staff and SNC agreed that, after additional internal discussions on both sides, further discussion on this topic was needed at a future public meeting.

The second topic discussed was items 1, 2, and 4 on the ICN and UIN comment status sheet.

For item 1, the staff agreed that the UINs submitted were acceptable since the data reports will contain the results of the component and piping hydrostatic testing per the ASME code requirements. For item 2, SNC proposed rewording the footnote in future UINs and in the ICN for ITAAC Index No. 13 to remove the confusion. The staff stated that SNCs response was acceptable. For item 4, SNC stated that they have identified that the UIN for ITAAC Index No.

98 needed to be resubmitted for an unrelated reason and that they would include the reference in the resubmittal. The staff noted that SNCs response was acceptable. Following the meeting, SNC provided written responses to the items in the comment status sheet (ADAMS Accession No. ML18089A048).

At the end of each topic discussed, there was an opportunity for the public to provide comments and ask questions. All comments and questions from members of the public were addressed before ending the meeting.

Docket Nos.: 52-025 52-026

Enclosure:

As stated cc w/encls: See next page

ML18092A305 NRC-001 OFFICE PM: DNRL/LB4 LA: DNRL/LB4 BC: DNRL/LB4 PM: DNRL/LB4 NAME JHoellman (c)

RButler (c)

JDixon-Herrity (c)

JHoellman (s)

DATE 4/9/18 4/4/18 4/9/18 4/9/18

AGENDA FOR PUBLIC MEETING U.S. NUCLEAR REGULATORY COMMISSION (NRC)

Thursday, March 29, 2018 9:00 a.m. - 10:00 a.m.

PURPOSE:

To discuss issues associated with the safety review of licensing actions for Southern Nuclear Operating Companys (SNC) Vogtle Electric Generating Plant (VEGP) Units 3 and 4.

OPEN Time Topic Led By 9:00 a.m.

Opening Remarks NRC 9:05 a.m.

Discussion of SNCs draft Request for Additional Information (RAI) Responses Regarding License Amendment Request (LAR)17-037 NRC/SNC 9:35 a.m.

Opportunity for Public Comment PUBLIC/NRC 9:40 a.m.

Discussion of Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Completion Notification (ICN) and Uncompleted ITAAC Notification (UIN) Comment Status Sheet NRC/SNC 10:00 a.m.

Opportunity for Public Comment PUBLIC/NRC 10:00 a.m.

Adjourn

PUBLIC MEETING U.S. NUCLEAR REGULATORY COMMISSION Thursday, March 29, 2018 9:00 a.m. - 10:00 a.m.

List of Attendees Name Organization Representing the Nuclear Regulatory Commission Jordan Hoellman NRO/DNRL/LB4 Chandu Patel NRO/DNRL/LB4 Jennifer Dixon-Herrity NRO/DNRL/LB4 Don Habib NRO/DNRL/LB4 Paul Krohn NRO/DCIP Tim Lupold NRO/DEI/MEB Nick Hansing NRO/DEI/MEB Surinder Arora NRO/DCIP/HOIB Chris Welch

  • NRO/DCIP/HOIB Jim Gaslevic
  • NSIR Representing Industry Jason Redd
  • Southern Nuclear Operating Company (SNC)

Tom Hicks

  • SNC Amy Augtman
  • SNC Wes Sparkman
  • SNC Amanda Pugh
  • SNC Ted Amundson
  • SNC Zach Harper

Jason Eisenhauer

  • WEC Mike Corletti
  • WEC Representing Public Tom Childress

Rob Berg

  • EPM Steve Roetger
  • GA Public Service Commission
  • = participated via teleconference

Vogtle Units 3 & 4 Mailing List (Revised 03/13/2018) cc:

Office of the Attorney General Resident Inspector 40 Capitol Square, SW Vogtle Plant Units 3 & 4 Atlanta, GA 30334 8805 River Road Waynesboro, GA 30830 Resident Manager Oglethorpe Power Corporation Mr. Barty Simonton Alvin W. Vogtle Nuclear Plant Team Leader 7821 River Road Environmental Radiation Program Waynesboro, GA 30830 Air Protection Branch Environmental Protection Division Southern Nuclear Operating Company 4244 International Parkway, Suite 120 Document Control Coordinator Atlanta, GA 30354-3906 42 Inverness Center Parkway, Bin 237 Birmingham, AL 35242 George B. Taylor, Jr.

2100 East Exchange Pl Anne F. Appleby Atlanta, GA 30084-5336 Olgethorpe Power Corporation 2100 East Exchange Place Brian H. Whitley Tucker, GA 30084 Regulatory Affairs Director Southern Nuclear Operating Company County Commissioner 42 Inverness Center Parkway, BIN B237 Office of the County Commissioner Birmingham, AL 35242 Burke County Commission Waynesboro, GA 30830 Mr. Michael Yox Site Regulatory Affairs Director Mr. Wayne Guilfoyle Vogtle Units 3 & 4 Commissioner District 8 7825 River Road, Bin 63031 Augusta-Richmond County Commission Waynesboro, GA 30830 4940 Windsor Spring Rd Hephzibah, GA 30815 Gwendolyn Jackson Burke County Library 130 Highway 24 South Waynesboro, GA 30830 Mr. Reece McAlister Executive Secretary Georgia Public Service Commission Atlanta, GA 30334 Page 1 of 3

Vogtle Units 3 & 4 Mailing List Email acchambe@southernco.com (Amy Chamberlian) agaughtm@southernco.com (Amy Aughtman)

ALPUGH@southernco.com (Amanda Pugh) awc@nei.org (Anne W. Cottingham) becky@georgiawand.org (Becky Rafter) bhwhitley@southernco.com (Brian Whitley)

Bill.Jacobs@gdsassociates.com (Bill Jacobs) bjadams@southernco.com (Brad Adams) bwwaites@southernco.com (Brandon Waites) castelca@westinghouse.com (Curtis Castell) comerj@westinghouse.com (James Comer) crpierce@southernco.com (C.R. Pierce) dahjones@southernco.com (David Jones) david.hinds@ge.com (David Hinds) david.lewis@pillsburylaw.com (David Lewis) dgbost@southernco.com (Danny Bost) dlfulton@southernco.com (Dale Fulton) drculver@southernco.com (Randy Culver) durhamdc@westinghouse.com (David Durham) ed.burns@earthlink.net (Ed Burns) edavis@pegasusgroup.us (Ed David) erg-xl@cox.net (Eddie R. Grant) fdhundle@southernco.com (Forrest Hundley) fhwillis@southernco.com (Fred Willis)

G2NDRMDC@southernco.com (SNC Document Control) graysw@westinghouse.com (Scott W. Gray) jadwilli@southernco.com (J.D. Williams) james1.beard@ge.com (James Beard) jannina.blanco@pillsburylaw.com (Jannina Blanco) jantol1dj@westinghouse.com (David Jantosik) jenmorri@southernco.com (Jennifer Buettner)

JHaswell@southernco.com (Jeremiah Haswell) jim@ncwarn.org (Jim Warren)

John.Bozga@nrc.gov (John Bozga)

Joseph_Hegner@dom.com (Joseph Hegner) jpredd@southernco.com (Jason R. Redd) jranalli@meagpower.org (Jerry Ranalli) karen.patterson@ttnus.com (Karen Patterson) karlg@att.net (Karl Gross) kmstacy@southernco.com (Kara Stacy)

KSutton@morganlewis.com (Kathryn M. Sutton)

Page 2 of 3

Vogtle Units 3 & 4 Mailing List kwaugh@impact-net.org (Kenneth O. Waugh) lchandler@morganlewis.com (Lawrence J. Chandler)

Marc.Pickering@hq.doe.gov (Marc Pickering) markus.popa@hq.doe.gov (Markus Popa) mdmeier@southernco.com (Mike Meier) media@nei.org (Scott Peterson)

Melissa.Smith@Hq.Doe.Gov (Melissa Smith)

Michael.Kuca@hq.doe.gov (Michael Kuca) mike.price@opc.com (M.W. Price)

MKWASHIN@southernco.com (MKWashington) mlgraves@southernco.com (Michelle Graves)

MSF@nei.org (Marvin Fertel) myox@southernco.com (Mike Yox) nirsnet@nirs.org (Michael Mariotte)

Nuclaw@mindspring.com (Robert Temple) patriciaL.campbell@ge.com (Patricia L. Campbell)

Paul@beyondnuclear.org (Paul Gunter) pbessette@morganlewis.com (Paul Bessette) r.joshi15@comcast.net (Ravi Joshi)

RJB@NEI.org (Russell Bell)

Ronald.Jones@scana.com (Ronald Jones) rwink@ameren.com (Roger Wink) sabinski@suddenlink.net (Steve A. Bennett) sara@cleanenergy.org (Sara Barczak) sblanton@balch.com (Stanford Blanton)

Shiva.Granmayeh@hq.doe.gov (Shiva Granmayeh) sjackson@meagpower.org (Steven Jackson) skauffman@mpr.com (Storm Kauffman) sroetger@psc.state.ga.us (Steve Roetger) stephan.moen@ge.com (Stephan Moen) stephen.burdick@morganlewis.com (Stephen Burdick) tom.miller@hq.doe.gov (Tom Miller)

TomClements329@cs.com (Tom Clements)

Vanessa.quinn@dhs.gov (Vanessa Quinn) vcsummer2n3@gmail.com (Brian McIntyre) wasparkm@southernco.com (Wesley A. Sparkman) wayne.marquino@gmail.com (Wayne Marquino) weave1dw@westinghouse.com (Doug Weaver) x2gabeck@southernco.com (Gary Becker) x2kmseib@southernco.com (Kristin Seibert)

Page 3 of 3