SUP 80,l APPENDIX G FEEDWATER HAMMER TEST 1.0 TEST OBJECTIVE 1.1 To demonstrate that the operation of the auxiliary feedwater system, following a plant trip at power, will not cause unacceptable feedwater hammer.

2.0 REFERENCES

2.1 Government Contact Memorandum June 19, 1978 Caller - E.A. Liden, PSE&G Project Licensing Manager Agency Personal Involved: R. Stright, NRC Licensing Project Manager 2.2 NRC Letter of Review of SUP 80.1, Appendix G dated 11/7/80 R. Tedesco (Assistant Director for Li.censing, NCR) to R. Mittl (General Manager, Licensing, PSE&G).

2.3 PSE&G Drawing 205336-A-8763, Salem Unit II Auxiliary Feedwater Piping Diagram.

3.0 PREREQUISITES

_ _ _ 3.1 Theplant,is*operating at 50"% RTP.*

_ _ _ 3.2 Instrumentation designated in Section 7.0 has been installed to monitor 21 Steam Generator feedwater piping at 21FWH-ll-17, 21FWH-ll-18 and 21BF58.

_ _ _ 3.3 The NRC has been given at least a 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> notification prior to the commencement of this *test.

communications are established between the control room and personnel at the* visico,rc

- - -3. 4 er.

4.0 INITIAL CONDITIONS

_ _ _ 4.1 The Test Engineer has conducted a briefing with personnel involved in the test.

5.0 ENVIRONMENTAL CONDITIONS 5.1 The plant is at normal operating pressure and temperature.

6.0 ACCEPTANCE CRITERIA 6.1 The steam generator feedring modifications shall prevent excessive vibration and water hammer following the reactor trip.

Salem Unit 2 SUP 80.l Page 70 of 71 Appendix G 810605 0 ~1

7.0 SPECIAL EQUIPMENT EQUIPMENT NO. CALIBRATION DATE 7.1 Visicorder 7.2 ~inear Displacement Transmitter (1)

(for monitoring 21FWH-ll-17 and 21FWH-ll-18 in the X-Y-Z direction) (2)

(3)

(4)

(5)

(6) 7.3 Accelerometer 7.4 Pressure Transmitter (time constant less than .039 seconds range of 0-3000 psi installed at 21BF58) 8.0 DATA COLLECTION 8.1 Visicorder traces shall be collected and retained with the procedure.

9.0 PRECAUTIONS 9.1 During the injection of auxiliary feedwater following the reactor trip do not allow the reactor coolant system to be cooled at a rate greater than 100°F per hour.

10. 0 ElE'l'ATLEB: PROCEDURE

_ _ _10.1 Start the visicorder and verif:y the: correct input: of the parameters being monitored.

_ _ _10.2 Trip the reactor in accordance with SUP 80.1, NSSS Sequence Document.

_ _ _10.3 Following the plant trip verify tne Auxiliary Feedwater"Pumps start and adjust auxiliary feedwater flow to each steam generator to 440 gpm (220,600 lbm/hr).

_ _ _10.4 Maintain the flow until the feedwater ring in each steam generator is covered (11% narrow range indication) .

_ _ _10.5 Stop the visicorder and evaluate the traces to determine the degree of vibration and water hammer recorded at the monitored locations.

Salem Unit 2 Page 71 of 71 SUP 80.l

- ...--1:*"'*.t- ..... , .*. -* .~...... ... .--".

10.6 Adjust Auxiliary Feedwater flow as required to allow restoring the steam


generator water levels above the LOW LEVEL alarm setpoint while limiting plant cooldown below 547°F.

11.0 TEST COMPLETION 11.1 Comments 11.2 Senior Shift Supervisor _________________~

Test Engineer QA Surveillance 11.3 Changes in the SPM required as a result of the test have been noted and necessary correction initiated.