Letter Sequence Request |
|---|
CAC:MF9307, Addition of New Tech Spec on RCS Boron Limits and Revisions to Tech Spec 3.3.1 to Address Rwfs (Approved, Closed) |
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance, Acceptance
- Supplement, Supplement, Supplement, Supplement, Supplement, Supplement
|
MONTHYEARML17053B3932017-01-17017 January 2017 License Amendment Request for the Transition to Westinghouse Core Design and Safety Analyses Project stage: Request ML17054C2262017-01-17017 January 2017 License Amendment Request for the Transition to Westinghouse Core Design and Safety Analyses - WCAP-18083-NP, Rev 0, Westinghouse Revised Thermal Design Procedure Uncertainty Calculations Project stage: Request ML17054C2292017-01-17017 January 2017 License Amendment Request for the Transition to Westinghouse Core Design and Safety Analyses - Responses to NRC RAIs on August 2013 Methodology Transition LAR Submittal Project stage: Response to RAI ML17054C2272017-01-17017 January 2017 License Amendment Request for the Transition to Westinghouse Core Design and Safety Analyses - Alternative Source Term, Rev 1 Project stage: Request ML17151A9972017-03-0909 March 2017 Wolf Creek Revision 30 to Updated Final Safety Analysis Report, Chapter 3.0, Design of Structures, Components, Equipment, and Systems Project stage: Request WO 17-0026, Errata for License Amendment Request for Transition to Westinghouse Core Design and Safety Analyses2017-03-22022 March 2017 Errata for License Amendment Request for Transition to Westinghouse Core Design and Safety Analyses Project stage: Request ML17088A3312017-03-22022 March 2017 Transmittal of the Kansas Water Pollution Control Permit and Authorization to Discharge Under the National Pollutant Discharge Elimination System Project stage: Request ML17100A2662017-04-18018 April 2017 Supplemental Information Needed for Acceptance of Requested Licensing Action Transition to Westinghouse Core Design and Safety Analyses Project stage: Acceptance Review ET 17-0011, Response to Supplemental Information Needed for Acceptance of Requested Licensing Action Transition to Westinghouse Core Design and Safety Analyses2017-05-0404 May 2017 Response to Supplemental Information Needed for Acceptance of Requested Licensing Action Transition to Westinghouse Core Design and Safety Analyses Project stage: Request ML17132A3632017-05-15015 May 2017 Acceptance of Requested Licensing Action License Amendment Request for the Transition to Westinghouse Core Design and Safety Analyses in Addition to Adopting of Alternative Source Term Project stage: Acceptance Review ML17136A3592017-05-22022 May 2017 Request for Withholding Information from Public Disclosure, 11/14/2016(CAW-16-4499), Affidavit Executed by James A. Gresham, Westinghouse Electric Company LLC Enclosure I of the Letter Dated 01/17/2017 Project stage: Withholding Request Acceptance ML17137A2862017-05-22022 May 2017 Request for Withholding Information from Public Disclosure, 11/14/16 (CAW-16-4500) Affidavit Executed by James A. Gresham, Westinghouse Electric Company LLC for Enclosure VI to the Letter Dated 1/17/17 Project stage: Withholding Request Acceptance ML17166A0382017-06-14014 June 2017 NRR E-mail Capture - Request for Additional Information - License Amendment Request for Transition to Westinghouse Core Design and Safety Analyses Including Adoption of Alternative Source Term Project stage: RAI ET 17-0016, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analyses2017-07-13013 July 2017 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analyses Project stage: Response to RAI ML17265A0142017-09-21021 September 2017 NRR E-mail Capture - Request for Additional Information - License Amendment Request for Transition to Westinghouse Core Design and Safety Analyses Project stage: RAI ML17291A7102017-10-17017 October 2017 NRR E-mail Capture - Request for Additional Information - License Amendment Request (LAR) for Transition to Westinghouse Core Design and Safety Analyses Including Adoption of Alternative Source Term Project stage: RAI ET 17-0024, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analyses Including Adoption of Alternative Source Term2017-10-18018 October 2017 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analyses Including Adoption of Alternative Source Term Project stage: Response to RAI ML17297B7972017-10-31031 October 2017 Request for Withholding Information from Public Disclosure (CAC No. MF9307; EPID L 2017-LLA-0211) Project stage: Withholding Request Acceptance ET 17-0025, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analyses Including Adoption of Alternative Source Term2017-11-14014 November 2017 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analyses Including Adoption of Alternative Source Term Project stage: Response to RAI ML17331A1782017-12-0404 December 2017 Request for Additional Information License Amendment Request for Transition to Westinghouse Core Design and Safety Analyses Including Adoption of Alternate Source Term (CAC No. MF9307; EPID L-2017-LLA-0211) Project stage: RAI WO 18-0004, Response to Request for Additional Information Re License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of .2018-01-15015 January 2018 Response to Request for Additional Information Re License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of . Project stage: Response to RAI ET 18-0004, Supplement to License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term2018-01-29029 January 2018 Supplement to License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term Project stage: Supplement ML18066A0502018-03-0808 March 2018 Regulatory Audit Plan for March 19-21, 2018, in Support of the LAR for Transition to Westinghouse Core Design and Safety Analyses Including Alternative Source Term (CAC No. MF9307;EPID L-2017-LLA-0211) Project stage: Approval L-2018-077, Schedule for Re-Analysis of Turkey Point Licensing Basis Analyses Affected by PAD5 Implementation2018-03-27027 March 2018 Schedule for Re-Analysis of Turkey Point Licensing Basis Analyses Affected by PAD5 Implementation Project stage: Request ML18114A1162018-04-19019 April 2018 SAP-18-34, Supplemental 30 Day Responses to NRC Request for Additional Information Regarding Wolf Creek Generating Station Transition to Westinghouse Safety Analysis and Alternate Source Term Methodologies Project stage: Supplement ET 18-0012, Operating Corp., Supplement to License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term2018-04-19019 April 2018 Operating Corp., Supplement to License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term Project stage: Supplement ML18115A3522018-05-0303 May 2018 Request for Withholding Information from Public Disclosure, Affidavit Dated April 16, 2018 Supplemental 30 Day Responses to NRC RAI WCGS Transition to Westinghouse Safety AST Methodolgies Project stage: RAI ML18107A7562018-05-0303 May 2018 Regulatory Audit Summary License Amendment Request for Transition to Westinghouse Core Design and Safety Analyses Including Adoption of Alternative Source Term (CAC MF9307; EPID L-2017-LLA-0211) Project stage: Other ET 18-0018, Supplement to License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term2018-06-19019 June 2018 Supplement to License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term Project stage: Supplement ML18183A5832018-07-23023 July 2018 Request for Withholding Information from Public Disclosure - 6/18/18 Affidavit Executed by Edmond J. Mercier, Westinghouse Electric Company Adoption of AST Amendment Request(Cac No. MF9307; EPID L-2017-LLA-0211) Project stage: Withholding Request Acceptance WO 18-0034, Operating Corp., Additional Supplement to License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term2018-08-0909 August 2018 Operating Corp., Additional Supplement to License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term Project stage: Supplement ML18270A0942018-10-0404 October 2018 Request for Additional Information License Amendment Request for Transition to Westinghouse Methodology for Selected Accident and Transient Analyses Project stage: RAI 05000482/LER-2018-001, Inappropriate Use of Blind Flange for Containment Isolation Valve Results in Condition Prohibited by Technical Specifications2018-10-0404 October 2018 Inappropriate Use of Blind Flange for Containment Isolation Valve Results in Condition Prohibited by Technical Specifications Project stage: Request ML18332A1772018-10-25025 October 2018 Email Slides for 10/30 Public Meeting Project stage: Request ML18313A2252018-10-25025 October 2018 Westinghouse Affidavit CAW-18-4828 - Application for Withholding Proprietary Information from Public Disclosure Project stage: Request ML18299A0492018-10-30030 October 2018 Accident Analyses Methodology Transition LAR Public Meeting Project stage: Meeting ML18304A1052018-11-0505 November 2018 Request for Additional Information License Amendment Request for Transition to Westinghouse Core Design and Safety Analyses and Alternative Source Term (CAC No. MF9307; EPID L-2017-LLA-0211) Project stage: RAI WO 18-0047, Timeline for Response to RAI for License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term2018-11-15015 November 2018 Timeline for Response to RAI for License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term Project stage: Response to RAI WO 18-0044, Clean Revised Technical Specification Pages for License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term2018-11-15015 November 2018 Clean Revised Technical Specification Pages for License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term Project stage: Request ML18313A2542018-11-16016 November 2018 Summary of Public Meeting with Wolf Creek Nuclear Operating Corporation Regarding License Amendment Request for Transition to Westinghouse Core Design and Safety Analyses for Wolf Creek Generating Station Project stage: Meeting ML18327A1342018-11-30030 November 2018 Request for Withholding Information from Public Disclosure, Affidavit Dated October 25, 2018, Executed by Mr. Paul A. Russ, Westinghouse (CAC No. MF9307; EPID L-2017-LLA-0211) Project stage: Withholding Request Acceptance ET 18-0035, Operating Corp., Supplemental Response to RAI for License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term2018-12-0606 December 2018 Operating Corp., Supplemental Response to RAI for License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption of Alternative Source Term Project stage: Supplement ML18360A0342018-12-21021 December 2018 NRR E-mail Capture - Review Schedule for Wolf Creek Generating Station License Amend Request (LAR) for Transition to Westinghouse Core Design and Safety Analyses Including Adoption of Alternative Source Term Project stage: Approval ET 19-0008, Response to Request for Additional Information Related to Thermal Conductivity Degradation for License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption2019-03-0505 March 2019 Response to Request for Additional Information Related to Thermal Conductivity Degradation for License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption Project stage: Response to RAI ML19070A1392019-03-0505 March 2019 Response to Request for Additional Information Related to Thermal Conductivity Degradation for License Amendment Request to Revise Technical Specifications to Transition to Westinghouse Core Design and Safety Analysis Including Adoption. Project stage: Request ML19070A1162019-03-0505 March 2019 Westinghouse, Responses to NRC Request for Additional Information Documented in ADAMS Accession No. ML 18270A094 on the Core Design and Safety Analyses Methodology Transition Program Project stage: Response to RAI ML19099A1772019-04-16016 April 2019 Request for Withholding Information from Public Disclosure, 2/13/19 Affidavit Executed by Stephen Rigby, Westinghouse Electric Company LLC RAI Response Related to Adoption of Alternative Source Term (CAC MF9307; EPID L-2017-LLA-0211) Project stage: RAI ML19122A2552019-05-0202 May 2019 Closed Predecisional Enforcement Conference with an Employee of Wolf Creek Nuclear Operating Corporation Project stage: Request ML19100A1222019-05-31031 May 2019 Issuance of Amendment No. 221 License Amendment Request for Transition to Westinghouse Core Design and Safety Analyses Including Adoption of Alternative Source Term Project stage: Approval 2018-10-30
[Table View] |
Text
March 27, 2018 L-2018-077 10 CFR 50.90 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington D C 20555-0001 RE:
Turkey Point Nuclear Plant, Unit 3 and 4 Docket Nos. 50-250 and 50-251 Renewed Facility Operating Licenses DPR-31 and DPR-41 Schedule for Re-Analysis of Turkey Point Licensing Basis Analyses Affected by PAD5 Implementation
References:
- 1.
Final Safety Evaluation for WCAP-17642-P/NP, Revision 1, Westinghouse Performance Analysis and Design Model (PAD5), September 28, 2017 (ADAMS Accession Nos. ML17257A338 and ML17257A071)
- 2.
Topical Report WCAP-16996-P-A, Revision 1, Realistic LOCA Evaluation Methodology Applied to the Full Spectrum of Break Sizes (FULL SPECTRUM LOCA Methodology)
In Reference 1, the NRC approved the Performance Analysis and Design Model (PAD) methodology and computer code described in WCAP-17642-P/NP, Revision 1, Westinghouse Performance Analysis and Design Model (PAD5). In accordance with License Condition 3.H, PAD TCD Safety Analyses, of Renewed Facility Operating Licenses DPR-31 and DPR-41 for Turkey Point Units 3 and 4 (Turkey Point),
respectively, within six months of NRC approval of a revised generic version of PAD that accounts for Thermal Conductivity Degradation (TCD), Florida Power & Light Company (FPL) shall:
- a.
Demonstrate that PAD 4.0 TCD remains conservatively bounding in licensing basis analyses when compared to the new generically approved version of PAD w/TCD, or
- b.
Provide a schedule for the re-analysis using the new generically approved version of PAD w/TCD for any of the affected licensing basis analyses.
FPL has performed an assessment to determine the impact of using PAD5 for the current licensing basis analyses that were based upon input parameters generated by PAD 4.0 and PAD 4.0 TCD. Many of the licensing basis analyses were found to remain conservatively bounding, negligibly impacted or unaffected by the version of the PAD code used. As required by License Condition 3.H, a schedule for re-analysis of the licensing basis analyses affected by PAD5 implementation is provided below. The schedule relies upon NRC approval of a license amendment request (LAR) which revises the peak fuel centerline melt temperature specified in the Turkey Point Technical Specifications (TS) to align with the value defined in Reference 1 and a LAR adopting the Reference 2 Full Spectrum LOCA (FSLOCA) methodology.
Schedule for Re-Analysis of Licensing Basis Analyses Affected By PAD5 Implementation UFSAR Section Analysis Schedule 3.1.2 Reload Fuel Rod Design Criteria Confirmation Analysis (Rod Internal Pressure, Cladding Stress / Strain, Cladding Fatigue)
Complete re-analysis and implement on a forward fit basis by no later than the next reload campaign following implementation of TS amendment revising the peak fuel centerline melt temperature. (See Note 1) 14.1.1 Uncontrolled RCCA Withdrawal From a Sub-Critical Condition Complete re-analysis and implement on a forward fit basis by no later than the next reload campaign following implementation of TS amendment revising the peak fuel centerline melt temperature. (See Note 1)
Turkey Point Nuclear Plant Docket Nos. 50-250 and 50-251 L-2018-077 Page 2 of 2 Schedule for Re-Analysis of Licensing Basis Analyses Affected By PAD5 Implementation UFSAR Analysis Schedule Section Complete re-analysis and implement on a Uncontrolled RCCA Withdrawal At Power forward fit basis by no later than the next 14.1.2 (RCS Pressure Case) reload campaign following implementation of TS amendment revising the peak fuel centerline melt temperature. (See Note 1)
Complete re-analysis and implement on a Steam System Piping Failure (Reload Power forward fit basis by no later than the next 14.2.5.2 reload campaign following implementation to Melt (kW/ft) Criteria Confirmation Analysis) of TS amendment revising the peak fuel centerline melt temperature. (See Note 1)
Complete re-analysis and implement on a Rupture of a Control Rod Mechanism forward fit basis by no later than the next 14.2.6 reload campaign following implementation Housing - RCCA Ejection of TS amendment revising the peak fuel centerline melt temperature. (See Note 1)
Complete re-analysis and submit a LAR adopting FSLOCA methodology by April 14.3.2.1 Best-Estimate Large Break Loss-Of-Coolant 2021. Implement on a forward fit basis by Accident (BE-LOCA) Analysis no later than next reload campaign following implementation of TS amendment adopting FSLOCA.
Note 1.
The LAR which revises the peak fuel centerline melt temperature is scheduled for submittal in April 2018.
This letter includes a regulatory commitment to complete the above re-analysis and implement on a forward fit basis following the approval of the specified LARs.
Should you have any questions regarding this submission, please contact Mr. Robert Hess, Turkey Point Licensing Manager, at 305-246-4112.
I declare under penalty of perjury that the foregoing is true and correct.
Executed on the 27th day of March 2018.
Sincerely,
~
Regional Vice President, Southern Region Turkey Point Nuclear Plant cc:
USNRC Regional Administrator, Region II USNRC Project Manager, Turkey Point Nuclear Plant USNRC Senior Resident Inspector, Turkey Point Nuclear Plant Ms. Cindy Becker, Florida Department of Health