Forwards IE Insp Rept 50-272/80-24 on 801006-07 & 09-10 & Notice of Violation
ML18085A737
Person / Time
Site: Salem 
Issue date: 10/28/1980
From: Robert Carlson
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Schneider F
Public Service Enterprise Group
Shared Package
ML18085A735 List:
References
NUDOCS 8102040139
Download: ML18085A737 (2)


See also: IR 05000272/1980024

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION I

631 PARK AVENUE

KING OF PRUSSIA, PENNSYLVANIA 19406

OCT 2 8 1980

Docket No. 50-272

Public Service Electric and Gas Company

ATTN:

Mr. F. W. Schneider

Vice President - Production

80 Park Plaza - 15A

Newark, New Jersey 07101

Gentlemen:

Subject:

Inspection 50-272/80-24

This refers to the routine inspection conducted by Mr. R. A. McBrearty of this

office on October 6 - 7, 1980 and October 9 - 10, 1980 at Salem Nuclear Generating

Station, Unit 1 of activities authorized by NRC License No. DPR-70 and to the

discussions of our findings held by Mr. McBrearty with Mr. H. Midura of your

staff at the conclusion of the inspection, and to a subsequent telephone

discussion between Mr. R. T. Griffith of your staff and Mr. McBrearty on October

15, 1980.

Areas examined during this inspection are described in the Office of Inspection

and Enforcement Inspection Report which is enclosed with this letter.

Within

these areas, the inspection consisted of selective examinations of procedures

and representative records, interviews with personnel, and observations by the

inspector.

Based on the results of this inspection, .it appears that one of your

activities was not conducted in full compliance with.NRC requirements, as set

forth in the Notice of Violation, enclosed herewith as Appendix A.

This

item o.f noncompliance has been categorized into the levels as described in

our correspondence to you dated December 31, 1974.

This notice is sent to you

pursuant to the provisions of Section 2.201 of the NRC 1s "Rules of Practice,

11

Part 2, Title 10, Code of Federal Regulations.

Section 2.201 requires you to

submit to this office, within twenty (20) days of your receipt of this notice,

a written statement or explanation in reply including:

(1) corrective steps

which have been taken by you and the results achieved; (2) corrective steps

which will be taken to avoid further items of noncompliance; and (3) the date

when full compliance will be achieved.

810204fl 1~'1

I

2

In accordance with Section 2.790 of the NRC 1s

11 Rules of Practice,

11 Part 2,

Title 10, Code of Federal Regulations, a copy of this letter and the enclosures

will be placed in the NRC 1 s Public Document Room.

If this report contains any

information that you (or your contractor) believe to be proprietary, it is

necessary that you make a written application within 20 days to this office to

withhold such information from public disclosure. Any such application must be

accompanied by an affidavit executed by the owner of the information, which

identifies the document or part sought to be withheld, and which contains a

statement of reasons which addresses with specificity the items which will be

considered by the Commission as listed in subparagraph (b) (4) of Section

2. 790.

The information sought to be withheld shall be incorporated as far as

possible into a separate part of the affidavit. If we do not hear from you in

  • this regard within the specified period, the report will be placed in the

Public Document Room.

Should you have any questions concerning this inspection, we will be pleased

to discuss them with you.

Enclosures:

l.

Appendix A, Notice of Violation

Sincerely,

.~~--

Robert T. Carlson, Chief

Reactor Construction and Engineering

Support Branch

2.

Office of Inspection and Enforcement Inspection

Report Number 50-272/80-24

cc w/encl:

F. P. Librizzi, General Manager - Electric Production

E. N. Schwalje, Manager - Quality Assurance

R. L. Mittl, General Manager - Licensing and Environment

H. J. Midura, Manager - Salem Generating Station

R. A. Uderitz, General Manager - Fuel Supply Department