Forwards IE Insp Rept 50-272/80-29 on 801105-06.No Noncompliance Noted
ML18085A510
Person / Time
Site: Salem PSEG icon.png
Issue date: 11/20/1980
From: Robert Carlson
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Schneider F
Public Service Enterprise Group
Shared Package
ML18085A511 List:
References
NUDOCS 8101140118
Download: ML18085A510 (2)


See also: IR 05000272/1980029

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION I

631 PARK AVENUE

KING OF PRUSSIA, PENNSYLVANIA 19406

<

Docket No. 50-272 _

C)

PT

(J)

Public Service Electric and Gas Company

ATTN:

Mr. F. W. Schneider

Vice President - Production

80 Park Plaza - 15A

Newark, New Jersey 07101

Gentlemen:

Subject:

Inspection Report No. 50-272/80-29 *

This refers to the routine inspection conducted by Mr~ R. Paolino of this office

on November 5-6, 1980 at Salem Nuclear Generating Station, Unit 1 located at

Hancocks Bridge, New Jersey of activities authOrized by NRC License No. DPR-70 *

and to the discussions of our findings held by Mr. R. Paolino with Mr. H. Midura*

and other members of your staff at the conclusion of the inspection.

Areas examined during this inspection are described in the Office of Inspection

and Enforcement Inspection Report which is enclosed with this letter. Within

these areas, the inspection consisted of selective examinations of procedures

and representative records, interviews with personnel, and* observations by the

inspector.

Within the scope of this inspection,. no items of noncompliance were observed.

In accordance with Section 2.790 of the NRC's

11 Rules of Practice,

11 Part 2, Title

10, Code of Federal Regulations, a copy of this letter and the enclosed inspection

report will be placed in the NRC 1s Public Document Room.

If this report contains

any information that you (or your contractor) believe to be proprietary, it is

necessary that you make a written application within 20 days to this office to

withhold such information from public disclosure.

Any such application must be

accompanied by an affidavit executed by the owner of the information, which

identifies the document or part sought to be withheld, and which contains a

statement of reasons which addresses with specificity the items which will be

considered by the Commission as listed in subparagraph (b) (4} of Section

2.790.

The information sought to be withheld shall be incorporated as far as

possible into a separate part of the affidavit. If we do not hear from you in

this regard within the specified period, the report will be placed in the Public

Document Room.

~, : :: :

( ~.: :-_-;

~>:*~~

'-=-~

~i:::j

-!C:

-~~

c

.:::

._ ....

Public Service Electric and Gas Company

2

No reply to this letter is required; however, should you have any questions

concerning this inspection, we will be pleased to discuss them with you.

Sincerely,

p udf {..id

P,/';~f{gbert T. Carlson, Chief

~v Reactor Construction and Engineering

f

. Support Branch

Enclosure:

Office of Inspection and Enforcement Inspection

Report Number 50-272/80-29

cc w/encl:

F. P. Librizzi, General Manager - Electric Production

E. N. Schwalje, Manager - Quality Assurance

R. L. Mittl, General Manager - Licensing and Environment

H. J. Midura, Manager - Salem Generating Station

R. A. Uderitz, General Manager - Fuel Supply Department