Forwards Confirmation That Implementation Dates in NUREG-0737 Will Be Met,In Response to NRC 801031 Request
ML18085A445
Person / Time
Site: Salem PSEG icon.png
Issue date: 12/09/1980
From: Mittl R
Public Service Enterprise Group
To: Miraglia F
Office of Nuclear Reactor Regulation
References
RTR-NUREG-0737, RTR-NUREG-737 NUDOCS 8101070190
Download: ML18085A445 (10)


Text

*/

0 PS~G

  • Public Service Electric and Gas Company 80 Park Place Newark, N.J. 07101 Phone 201/430-7000 December 9~ 1980 Director of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C.

20555 Attention:

Mr. Frank J. Miraglia, Chief Licensing Branch 3 Division of Licensing Gentlemen:

CLARIFICATION OF POST -

TMI REQUIREMENTS NUREG-0737 NO. 2 UNIT SALEM NUCLEAR GENERATING STATION DOCKET NO. 50-311 PSE&G hereby submits, in the enclosure to this letter, its response to your letter dated October 31, 1980, requesting confirmation that implementation dates identified in NUREG-0737 for operating reactors can be met.

Should you have any questions in this regard, do not hesi-tate to contact us.

.... CC:

Mr. Leif Norrholm Salem Resident Inspector C-D r.:'-l t

z1;;;;;

R. L. Mittl General Manager -

Licensing and Environment 95-0942

Clarification Item I.A.1.1 e

I.A.1.2 I.A.1.3 I.A.2.1 I.A.2.3 I.A.3.1 l.C.l M P80 llO 22/l ENCLOSURE 1 POST-TM! REQUIREMENTS FOR OPERATING REACTORS (NUREG-0737)

IMPLEMENTATION SCHEDULE SALEM 2 Shortened Title Description Shift technical advisor

1.
2.
3.

On duty Tech specs Trained per LL Cat B Shift supervisor responsibilities Shift manning Immediate upgrading of RO and SRO training and qualifications Administration of training programs Revise scope and criteria for licensing exams Short-term accident and procedures review

4.

Describe long-term program Delegate non-safety duties

1.

Limit overtime

2.

Min shift crew

1.

SRO exper

2.

SROs be ROS 1 yr 3,

Three month train-ing on shi.ft

4.

Modify training

5.

Facility certification Instructors complete SRO exam

1.

Increase scope

2.

Increase passing grade

3.

Simulator exams

1.

SB LOCA

2.

Inadequate core cooling Implementation Schedule 1/1/80 12/15/80 1/1/81 1/1/81 1/1/80 11/1/80 7/1/82 5/1/80 12/1/80 8/1/80 8/1/80 5/1/80 8/1/80 5/1/80 5/1/80 10/1/81 6/1/80' Remarks Complete Complete Will be completed by 1/1/81 Will be submitted in &ccordance with implementation schedule Complete To be accomplished per SER, Supplement 5 Will be completed in accordance with imple-mentation schedule Complete Complete Complete Complete Complete Complete Complete Complete Complete

~larif ication

  • item l.C.l I.C.2 r.c. 3 I.C.4 I.C.5 I.C.6 M P80 llO 22/2 Shortened Title Short-term accident and procedures review (continued)

Shift and relief turnover procedures Shift-supervisor responsibility Control-room access Feedback of operating experience Verify correct per-formance of operating activities ENCLOSURE 1 (CONTINUED)

Description

a.

Reanalyze and propose guide-lines

b.

Revise procedures

3.

Transients &

accidents

a.

Reanalyze and propose guidelines

b.

Revise procedures Implementation Schedule 1/1/81 First refuel-ing outage after 1/1/82 1/1/81 First refuel-ing outage after 1/1/82 Implement shift 1/1/80 turnover checklist Clearly define superv.

1/1/80 and aper. responsibili-ties Establish authority, 1/1/80 limit access Licensee to implement 1/1/81 procedures Revise 1/1/81 performance procedures Remarks The Westinghouse Owners Group will submit a detailed description of our program to comply with the requirements of Item I.C.l by 1/1/81.

The program will identify Owners Group submittals to be made.

The additional effort required to attain full compliance with Item I.C.l, with proposed schedules for completion, will be identified as discussed with the NRC on 11/12/80.

The Westinghouse Owners Group will submit a detailed description of our program to comply with the requirements of Item I.C.l by 1/1/81.

The program will identify Owners Group submittals to be made.

The additional effort required to attain full compliance with Item I.C.l, with proposed schedules for completion, will be identified as discussed with the NRC on 11/12/80.

Complete Complete Complete Will be completed in accordance with implemen-tation schedule Will be completed in accordance with implemen-tation schedule

A Clarification Witem II.B.l II.B.2 II.B.3 II.B.4 II.D.l M P80 110 22/3 Shortened Title Reactor coolant system vents Plant shielding Postaccident sampling ENCLOSURE 1 (CONTINUED)

Description

1.

Design vents

2.

Install vents (LL Cat B)

3.

Procedures

1.

Review designs

2.

Plant modifications (LL Cat B)

3.

Equipment qualification

1.
2.

Interim system Plant modifications (LL Cat B)

Implementation Schedule 7/1/81 7/1/82

.1/1/82 1/1/BO 1/1/82 6/30/82 1/1/BO 1/1/82 Training for mitigating

1.

core damage Develop training program 1/1/81 Relief & safety valve test requirements

2.

Implement program

a.

Initial

b.

Complete 4/1/81 10/1/81

1.

Submit program 1/1/80

2.

RV & SV testing (LL Cat B) fie

a.

Complete 7/1/81 testing

b.

Plant-speciting 10/1/81 report

3.

Block-valve testing 7/1/82 Remarks Will be submitted in accordance with imple-mentation schedule.

Will be completed in accordance with imple-mentation schedule; subject to availability of a unit outage of sufficient duration Will be completed in accordance with imple-mentation schedule Complete Will be completed in accordance with imple-mentation schedule Will be completed in accordance with imple-mentation schedule Complete Will be completed in accordance with imple-mentation schedule; subject to availability of a unit outage of sufficient duration c;omplete Will be completed *in accordance with* imple-mentation schedule Will be completed in accordance with imple-men-tation schedule Complete EPRI test program scheduled for completion by 9/1/81 Will be completed in accordance with implemen-tation schedule, subject to EPRI test program completion by 9/1/81 Subject to development and execution of test program by EPRI

ENCLOSURE l (CONTINUED)

Clarification Shortened Implementation

~-t_e_m~~~~~~-T~i_t_1_e~~~~~~~~~~~D_e_s_c_r_i_p_t_i_*o_n~~~~~~~~s_c_h_e_d~u_1_e~~~~--R_e_m_a_r_k~s~~~~~~~~~~~~~~~~~~~~-

II.D.3 II.E. l.l II.E.1.2 II.E.3.1 e

II.E.4.1 II.E.4.2 M P80 110 22/4 Valve position indication Auxiliary feedwater system evaluation Auxiliary feedwater system initiation

& flow Emergency power for pressurizer heaters Dedicated hydrogen penetrations Containment isolation dependability

l.

Install direct indications of valve position

2.

Tech specs

l.

Short term

2.

Long term

l.

Initiation

a.

Control grade

b.

Safety grade

2.

Flow indication

a.

Control grade

b.

LL A tech specs

c.

Safety grade

l.

Upgrade power supply

2.

Tech specs

l.

Design

2.

Install 1-4.

Imp. diverse isolation

5.

Containment pres-sure setpoint

a.

Specify pressure

b.

Modifications 1/1/80 12/15/80 7/1/81 1/1/82 6/1/80 7/1/81 1/1/80 12/15/80 7/1/81 1/1/80 12/15/80 1/1/80 7/1/81 1/1/80 1/1/81 7/1/81 Complete Complete Complete Complete Complete Complete; required information will be submitted by 1/1/81.

Complete Complete Design complete; delivery of qualified trans-mitters is scheduled for 6/81; required information will be submitted by 1/1/81.

Complete Complete Not applicable to Salem(recombiners installed)

Not applicable to Salem(recombiners installed)

Complete Will be submitted in accordance with implemen-tation schedule Will be completed in accordance with implemen-tation schedule

Clarification Item II.E.4.2 II.F.l II.F.2 II.G.l II.K.l M P80 llO 22/5 ENCLOSURE 1 (CONTINUED)

Shortened Title Description Implementation Schedule Containment isolation dependability (continued)

6.

Containment purge 1/1/81 valves

7.

Radiation signal on 7/1/81 purge valves

8.

Tech specs 12/15/80 Accident-monitoring

1.

Noble gas monitor

2.

Iodine/particulate sampling

3.

Containment high-range monitor

4.

Containment pressure

5.

Containment water level

6.

Containment hydrogen Instrumentation for

1.

detection of inadequate

2.

core cooling Subcool meter Tech spec (LL Cat A)

Install level instruments (LL Cat B)

Documentation

3.
4.

Power supplies for

1.

pressurizer relief valves, block valves,

2.

and level indicators Upgrade to emergency sources Tech specs IE Bulletins 79-05' 06' 08 1/1/82 1/1/82 1/1/82 1/1/82 1/1/82 1/1/82 1/1/80 12/15/80 1/1/82 1/1/81 1/1/80 12/15/80 Bulletin specific Remarks Complete Complete Complete Will be completed in accordance with implemen-tation schedule Will be completed in accordance with implemen-tation schedule Will be completed in accordance with implemen-tation schedule; subject to availability of a unit outage of sufficient duration Will be completed in accordance with implemen-tation schedule; subject to availability of a unit outage of sufficient duration Will be completed in accordance with implemen-tation schedule; subject to availability of a unit outage of sufficient duration Will be completed in accordance with implemen-tation schedule; subject to availability of a unit outage of sufficient duration Complete Complete Installation requires removal of reactor ves-sel head; will be completed during first re-fueling outage, currently scheduled for 4/82 Will be submitted in accordance with implemen-tation schedule, howeve~ much of the analyt-ical information will not be available from Westinghouse until mid-1981.

Complete Complete Complete

.r

..... Clarification W'Item II.K.2 II.K.3 M PRn lln ??/r:.

Shortehed Title Orders on B&W plants Final recommendations, B&O task force ENCLOSURE 1 (CONTINUED)

Description

13.

Thermal-mechanical report

17.

Voiding in RCS

19.

Benchmark analysis of seq. AFW flow

1.

Auto PORV isolation

a.

Design

b.

Test/Install Implementation Schedule 1/1/82 1/1/82 1/1/82 7/1/81 1st refuel 6 mos. after staff approval 1/1/81 Remarks Report will be submitted by Westinghouse Owners Group in accordance with implementa-tation schedule.

This report will address thermal-mechanical conditions in the reactor during recovery from small breaks with extended loss of feedwater, and will consist of analyses for generic plant groupings.

Following completion of the above, additional plant specific analyses, if required, will be provided.

Schedules for plant specific anal-yses will be determined based on the results of the generic analysis.

Report will be submitted by Westinghouse Owners Group in accordance with implementa-tation schedule.

This report will address potential for void formation in the RCS during natural circulation cooldown conditions, as described in Westinghouse letter, NS-TMA-2298 (T.M. Anderson to P. Check)

The transient analysis code (LOFTRAN) and the present small break analysis code (WFLASH) have both undergone benchmarking against plant information or experimental test facil-ities.

The codes have also been compared with each other under appropriate conditions.

Westinghouse Owners Group will submit a report addressing the benchmarking of these codes on a schedule consistent with the requirements of Task II.K.2.19.

Complete Will be completed in accordance with implemen-tation schedule

A Clarification Witem II.K.3

)

M P80 llO 22/7 Shortened Title Final recommendations*,

B&O task force (continued)

ENCLOSURE 1 (CONTINUED)

Description

2.

Report on PORV failures

3.
s.
9.
10.
11.
12.

Reporting SV & RV failures &

challenges Auto trip of RCPs

a.

Propose modifications

b.

Modify PIO controller Proposed antici-patory trip modifi-cations Justifiy use of certain PORV Anticipatory trip on turbine trip

a.

Confirmation or propose modifi-cations

b.

Modify Implementation Schedule 1/1/81 7/1/81 3/1/82 1/1/81 Plant specific Plant specific 1/1/81 1st refuel 6 mos. after staff approval Remarks Westinghouse Owners Group is developing a report to address Item II.K.3.2.

This report will include historical valve failure rate data and documentation of actions taken to decrease the probability of a stuck-open PORV.

However, due to the lengthy process of data gathering, breakdown and evaluation, this report is currently scheduled for submittal by 3/1/81.

This report will be used to support a decision with regard to the necessity of incorporating an automatic PORV isolation system as specified in Item II.K.3.1.

Complete Will be completed in accordance with implemen-tation schedule Will be completed in accordance with implemen-Complete Not implemented; Reference PSE&G letter, R. L.

Mittl to A. Schwencer, dated 5/20/80 Not applicable to Salem Complete Not applicable to Salem

Clarification Item III.A.l.l III.A.l.2 III.A. 2 M P80 llO 22/8 Shortened Title Emergency prepared-ness, short term Upgrade emergency support facilities Emergency preparedness ENCLOSURE l (CONTINUED)

Description

17.

ECC system outages

25.

Power on pump seals Implementation Schedule 1/1/81

a.

Propose modifi-1/1/82 cations

b.

Modifications 7/1/82

30.

SB LOCA methods

a.

Schedule out-line

b.

Model

c.

New analyses

31.

Compliance with CFR 50.46 Short-term improvements

1.

Interim TSC, OSC &

EOF

1.

Upgrade emergency plans to App. E, 10 CFR 50 11/15/80 1/1/82 l yr. after staff approval 1/1/83 or l yr after staff approval Complete Complete 4/1/81

2.

Meteorological data 6/1/83 Remarks Will be completed in accordance with implemen-tation schedule Will be completed in accordance with implemen-tation schedule Will be completed in accordance with implemen-tation schedule Will be completed in accordance with imple-mentation schedule, as outlined in Westinghouse letter, NS-TMA-2318 (T.M.

Anderson to D. G. Eisenhut), dated 9/26/80.

Will be completed in accordance with imple-mentation schedule.

Complete Complete Will be completed in accordance with implemen-tation schedule Will be completed in accordance with implemen-tation schedule

e Clarification Item III.D.1.1 III.D.3~3 III.D.3.4 RWS:li 12/9/80 Shortened Title Primary coolant containment outside Inplant radiation monitoring Control-room habitability M P80 110 22/9 1/9 ENCLOSURE 1 (CONTINUED)

Description

1.

Leak reduction

2.

Tech specs

1.

Provide means to determine presence of radioiodine

2.

Modifications to accurately measure I2

1.

Review

2.

Modification Implementation Schedule Complete 12/15/80 Complete 1/1/81 1/1/81 1/1/83 Remarks Complete Complete Will be completed in accordance with implemen-tat ion schedule Complete No modifications required