Forwards IE Insp Repts 50-272/79-32 & 50-311/79-37 on 791118-1215.No Noncompliance Noted
ML18082A187
Person / Time
Site: Salem  PSEG icon.png
Issue date: 02/26/1980
From: Brunner E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Martin T
Public Service Enterprise Group
Shared Package
ML18082A188 List:
References
NUDOCS 8004170288
Download: ML18082A187 (2)


See also: IR 05000272/1979032

Text

.___;____ *o*~

\\ .. -

-

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION I

631 PARK AVENUE

KING OF PRUSSIA, PENNSYLVANIA 19406

FEB 2 6 1980

Docket No. 50-311

Public Service Electric and Gas Company

ATTN:

Mr. T. J. Martin

Vice President - Engineering and Construction

80. Park Place

Newark, New Jersey 07101

Gentlemen:

Subject: Inspection 50-311 /79-37

This refers to the inspection conducted by Mr. L. Norrholm of this office on

November 18 - December 15, 1979 at Salem Nuclear Generating Station, Unit 2,

of activities authorized by NRC License No. CPPR-53 and to the discussions of

our findings held by Mr. Norrholm with R. Griffith of your staff periodically

during the inspection.

Areas examined during this inspection are described in the Office of Inspection

and Enforcement Inspection Report which is enclosed with this letter. Within

  • these areas, the inspection consisted of selective examinations of procedures

and representative records, interviews with personnel, and observations by the

inspector.

_

Within the scope of this inspection, no items of noncompliance were observed.

In accordance with Section 2.790 of the NRC's "Rules of Practice,

11 Part 2, Title

10, Code of Federal Regulations, a copy of this letter and the enclosed inspection

report wi 11 be placed in the NRC' s Public Document Room.

If this report contains

any information that you (or your contractor) believe to be proprietary, it is

necessary that you make a written application *within 20 days to this office to

withhold such information from public disclosure.

Any such application must be

accompanied by an affidavit executed by the owner of the information, which

identifies the document or part sought to be. withheld, and which contains a

statement of reasons which addresses with specificity the items which will be

considered by the Commission as listed in subparagraph (b) (4) of Section

2.790.

The information sought to be withheld shall be incorporated as far as

possible into a separate part of the affidavit. If we do not hear. from you in

this regard within the specified period, the report will be placed in the Public

Document Room.

Public Service Electric and Gas

Company

2

FEB 2 6 1980

No reply to this letter is required; however, if you should have any questions

concerning this inspection, we will be pleased to discuss them with you.

Sincerely,

  • a *. Brunner, Chief

Re~or Operations and Nuclear

  • Support Branch

Enclosure: Office of Inspection and. Enforcement Combined Inspection

Report Numbers 50-272/79-32 and 50-311/79-37

cc w/encl:

E. N. Schwalje, Manager - Quality Assurance