Letter Sequence Other |
|---|
EPID:L-2017-LLA-0390, Orano USA - Application for Amendment No. 4 to Certificate of Compliance No 1029 - Revised UFSAR Changed Pages (Approved, Closed) |
|
MONTHYEARML18024A4992018-01-24024 January 2018 Letter to J. Bondre Application for Amendment No. 4 to Certificate of Compliance No. 1029-Supplemental Information Needed Project stage: Other ML18065A3622018-02-22022 February 2018 Acceptance Review of Tn Americas LLC Application for Amendment No. 4 to Certificate of Compliance No. 1029 - Response to Request for Supplemental Information (Docket 72-1029) Project stage: Supplement ML18071A1242018-03-12012 March 2018 Letter to J. Bondre Application for Amendment No. 4 to Certificate of Compliance No. 1029 - Accepted for Review Project stage: Other ML18138A2892018-05-16016 May 2018 Orano USA - Application for Amendment No. 4 to Certificate of Compliance No 1029 - Revised UFSAR Changed Pages Project stage: Request ML18179A1742018-06-26026 June 2018 Orano USA - Application for Amendment No. 4 to Certificate of Compliance No. 1029- Partially Redacted UFSAR Tables Project stage: Request ML18201A2022018-07-18018 July 2018 Orano USA - Application for Amendment No. 4 to Certificate of Compliance No. 1029- Revised Rsi 5-1 Response Project stage: Request ML18263A0482018-09-19019 September 2018 Memorandum to K. Morgan-Butler User Need for Rulemaking for Amendment No. 4 to the Orano Transnuclear Standardized Advanced NUHOMS Horizontal Modular Storage System Project stage: Approval ML18263A0442018-09-19019 September 2018, 16 January 2019 Package: Memorandum to K. Morgan-Butler User Need for Rulemaking for Amendment No. 4 to the Orano Transnuclear Standardized Advanced Nuhoms Horizontal Modular Storage System Project stage: Request ML18263A0472019-01-16016 January 2019 Enclosure 3: Preliminary SER (Memorandum to K. Morgan-Butler User Need for Rulemaking for Amendment No. 4 to the Orano Transnuclear Standardized Advanced NUHOMS Horizontal Modular Storage System) Project stage: Approval ML18263A0452019-01-16016 January 2019 Enclosure 2: Proposed TS (Memorandum to K. Morgan-Butler User Need for Rulemaking for Amendment No. 4 to the Orano Transnuclear Standardized Advanced NUHOMS Horizontal Modular Storage System) Project stage: Approval ML18263A0462019-01-16016 January 2019 Enclosure 1: Proposed CoC No. 1029, Amendment No. 4 (Memorandum to K. Morgan-Butler User Need for Rulemaking for Amendment No. 4 to the Orano Transnuclear Standardized Advanced NUHOMS Horizontal Modular Storage System) Project stage: Approval ML19036A5612019-02-0505 February 2019 Enclosure 2: Final SER Letter to P. Narayanan Amendment No. 4 to Certificate of Compliance No. 1029 for the Standardized Advanced NUHOMS System) Project stage: Approval ML19036A5572019-02-0505 February 2019 Package: Letter to P. Narayanan Amendment No. 4 to Certificate of Compliance No. 1029 for the Standardized Advanced Nuhoms System Project stage: Request ML19036A5602019-02-0505 February 2019 Letter to P. Narayanan Amendment No. 4 to Certificate of Compliance No. 1029 for the Standerized Advanced NUHOMS System Project stage: Other ML19036A5582019-02-0505 February 2019 Enclosure 3: Technical Specifications (Letter to P. Narayanan Amendment No. 4 to Certificate of Compliance No. 1029 for the Standardized Advanced NUHOMS System) Project stage: Other ML19036A5592019-02-0505 February 2019 Enclosure 1: CoC No. 1029 Letter to P. Narayanan Amendment No. 4 to Certificate of Compliance No. 1029 for the Standardized Advanced NUHOMS System) Project stage: Other 2018-06-26
[Table View] |
Text
March 12, 2018 Jayant Bondre, Chief Technical Officer TN Americas, LLC 7135 Minstrel Way, Suite 300 Columbia, MD 21045
SUBJECT:
APPLICATION FOR AMENDMENT NO. 4 TO CERTIFICATE OF COMPLIANCE NO. 1029 - ACCEPTED FOR REVIEW
Dear Mr. Bondre:
By letter dated November 15, 2017, as supplemented February 22, 2018, you submitted an application for amendment four to Certificate of Compliance (CoC) No. 1029 (Docket No. 72-1029). By letter dated January 24, 2018, the U.S. Nuclear Regulatory Commission (NRC) staff requested TN Americas, LLC (TN) provide supplemental information to complete the acceptance review of the application. By letter dated February 22, 2018, TN submitted their responses to the NRC request for supplemental information.
The staff has conducted an acceptance review of the application, as supplemented, and determined that it contains sufficient information to begin a detailed technical review. We have established a schedule for the review and estimated that the staff may need approximately 350 hours0.00405 days <br />0.0972 hours <br />5.787037e-4 weeks <br />1.33175e-4 months <br /> to complete its review. The schedule allows the staff to complete and issue a request for additional information (RAI) in May 2018, and a draft CoC and safety evaluation report for rulemaking by August 2018, based on TN responding to any RAI by June 2018. If no additional information is needed, the draft approval for rulemaking may be issued by July 2018.
Please reference Docket No. 72-1029 and EPID No. L-2017-LLA-0390 in future correspondence related to this request. If you have any questions regarding this matter, I may be contacted at (301) 415-6877.
Sincerely,
/RA/
Chris Allen, Project Manager Spent Fuel Licensing Branch Division of Spent Fuel Management Office of Nuclear Material Safety and Safeguards Docket No. 72-1029 EPID No. L-2017-LLA-0390
ML18071A124 OFC:
SFM SFM SFM NAME:
WAllen WWheatley JMcKirgan DATE:
3/1/18 3/2/18 3/12/18