ML18064A875

From kanterella
Jump to navigation Jump to search
Insp Rept 50-255/95-10 on 950801-04.No Violations Noted. Major Areas inspected:post-modification Testing Activities Associated w/1992 RPS Upgrade Project & Current RPS Surveillance Testing Methodology
ML18064A875
Person / Time
Site: Palisades Entergy icon.png
Issue date: 08/22/1995
From: Gardner R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML18064A874 List:
References
50-255-95-10, NUDOCS 9509050021
Download: ML18064A875 (5)


See also: IR 05000255/1995010

Text

U. S. NUCLEAR REGULATORY COMMISSION

REGION I II

REPORT-NO. 50-255/95010(DRS)

_ FACILITY

Palisades Nuclear Generating Station

LICENSEE

Palisades Nuclear Generating Plant

27780 Blue Star Memorial Highway

Covert, MI 49043-9530 *

_

DATES

August 1 through 4, 1995

INSPECTORS

R. Winter, DRS Inspector

D. Butler,*DRS Inspector

APPROVED BY

.£M~Jtck~

$/~~115

R. N .. Gardner, Chief

Plant Systems Section

AREAS INSPECTED

Date

A special, unannou~ced safety inspection to determine the ~oot causes that led

to.the installation of containment high pressure printed circuit board jumpers

in the reactor protection system (RPS) matrix trip logics. The areas

inspected primarily involved post-modification .testing activities associated

with the 1992 RPS Upgrade Project and current RPS surveillance testing

methodology.

RESULTS

Two apparent violations were identified involving:

1) failure of the post~

modification test for a 1992 facility change to identify that the RPS

containment high pressure matrix trip logics were bypassed; and 2) failure to

maintain the six RPS matrix logic channels for containment high pressure

operable in accordance with Technical Specification 3.17 ..

-.

9509050021 950823

PDR

ADOCK 05000255

Q

PDR

i . l

l l

t

{*

. '

'

~

  • 1

1

-

~\\

I

l

t

i l

/.

INSPECTION DETAILS

1.0

Summary of Events

On July 28, 1995, while performing RPS circuit checkouts after connector

replacements, the licensee discovered that the RPS matrix trip logics * *

for containment high pressure were inoperable. Subsequent investigation

revealed that three jumpers had been created on each of the four matrix.

logic printed circuit boards. This occurred due to Pa}isad~s providing

RPS matrix logic wiring diagrams to Combustion Engineering that did not

reflect the as-b~ilt RPS configuration. Combustion Engine~ring *

developed wiring lists to manufacture new matrix logic modules from

these drawings during the 1992 RPS Upgrade Project.

The jumpers

bypassed the two of four (2/4) matrix trip logic signals for containment

high pressure.

The RPS rack bins were designed to accept 12 trip modules.

Palisades.

original RPS design had 10 RPS functional trips and 2 unused m6dules._

Containment high pressure was added during original construction as ari

eleventh RPS trip function. *The six 2/4 logic trip matrixes were.

designed as* a ladder network that receives two inputs from each RPS tri~

Opening of coincident parallel

contacts will initiate a reactor trip in any ladder network.

A trip

module logic input was hard wired bypassed (original construction) or

printed circuit jumpered (current design) when unused.

The original

construction matrix module was. wired correctly with only the unused

twelfth logic input having a bypass jumper.

However, the original

construction wiring diagram was never updated and reflected 2 unused

modules that were bypassed by jumpers.

Channel eleven {containment high pressure) was last tested and

demonstrated operable on December 3, 199lj prior to* the outage that

upgraded the RPS system.

During and following the 1992 outage, the RPS

containment high pressure logic inputs were not tested from the matrix

trip logics through the four RPS initiation logics (de-energize~ the

clutch power supplies) either by a post-modification test (PMT) or by

subsequent surveillance tests.

2.0

Root Causes

The inspectors identified the following barriers that may have

contributed to this event:

o

The original construction wiring diagrams did not reflect the as-

built configuration.

The wiring d1agrams showed a 10 trip input

RPS {the original design) and had not been updated {by removing

jumper bypasses) to reflect the addition of the containment high

pressure trip function.

These wiring diagrams were sent to

Combustion Engineering to manufacture the new printed circuit

matrix logic modules.

0

The containment high pressure portion of the manufacturer's

factory acceptance test {FAT) did not identify the matrix logic

output anomaly during the matrix channel trip select test.

2

t

. t.

.~

~

.i:

I

f

'i

  • '.

. .

0

0

0

Without knowing the test setup, the inspectors were unable to

determine if the FAT could have identified the jumpers.

This

matter is under review by the licensee.

The licensee's PMT did not test all aspects of the modification.

The PMT used the factory acceptance test to verify that the analog*

  • portions of the modification were in c.alibration. A surveillance

test was specified to complete the logic testing. Surveillance

test No. M0-3; "Reactor Protection Matrix Logic Tests,"

Revision 12, was the current procedure used to implement TS

Table 4.17.1, Functional Unit No. 13, "RPS Matrix Logic,"* and

No. 14, "RPS Initiation Logic."

The surveillance test did verify

proper' test overlap from the matrix trip logics through the

initiation logics. However, the procedure permitted the operator*

to select the functional RPS input, one of eleven Functional

Units, to test through the RPS initiation logics.

The PMT did not

specify that all *eleven RPS functional inputs should be. tested

through the RPS initiation logics. Per the survei.llance test, .the

operator randomly selected channel four.

If the operator had selected channel eleven (containment high

pressure}, the M0-3 procedure would have identified that the

channel eleven matrix tri.P logics were jumpered.

The licensee did not perform an adequate PMT review following the

completion of testing activities. The review. would.have

identified that only one RPS functional channel had been tested

through the initiation logics. For the scope of the 1992 RPS

Upgrade Project, the PMT should have demonstrated test ove.rl ap

from unmodified portions of the circuits through modified portions

of the circuits.

  • The licensee recognized in early 1995 (prior to identifying the

jumpers during the outage) that they were randomly selecting the

RPS functional channel to test each month through the initiation

logics. The M0-3 procedure was revised to select the RPS channel

to be tested by using the test month.

Using this selection

method, channel one would be.selected in January.

However, the

licensee did not review past tests to determine if all channels.

had been tested through the initiation logics during an operating

cycle. This would have identified that channel eleven had not*

been fuliy tested though the initiation logics since 1991.

The containment high pressure printed circuit jumpers would have

been identified in November 1995 during the performance of

surveillance procedure No. M0-3.

Channel eleven would be the

~elected channel for matrix logic testin~ through the initiation,

logics that month.

3

i.

I

. i !

.,

J

r

,.

i

t'o

t

~ ..

..

3.0

Licensee Corrective Actions

3.1

RPS

3.2

0

0

The six RPS matrix channels have been modified by grinding away*

the circuit board trace material.

The gap provided in the circuit

board trace was approximately ~ inch.

-

.A PMT has been written to perform a comprehensive test {wire to

wire) following current RPS modifications.

o

A new refueling outage RPS logic tesf procedure has been

developed.

Procedure No. MI-3A, "Reactor Protection Matri~ Logic

Annual Test," ~erifies that all eleven RPS functional inputs will

remove power from the clutch coils. This procedure will b~

performed before declaring the RPS operable during the 1995

.refueling outage.

Testing

0

The license~ was reviewing 19 additional surveillance procedures

and 8 PMT procedures performed during the 1995 refueling outage.

The objective of this review was to verify that procedures used to

test safety related circuits completely tested the design

functions of the circuits.

4.0

Violations

The following apparent violations were id~ntified: *

o

10 CFR 50, Appendix B, Criterion Ill, "Design Control-," requires,

in part, that measures shall provide for verifying or checking the

adequacy of desig_n by performance of a .suitable tesUng program .

0

. Contrary to the above, during the 1992 refueling *outage, the post-

modification test for Facility Change {FC) No. FC-888 did not

identify that the RPS containment high pressure matrix trip logics

were each bypassed {jumpered) by a printed circuit board trace.

As a result, the RPS containment high pressure trip logic could

not perform its safety function until identified and corrected-

during the 1995 refueling outage.

-

Technical Specification {TS) 3.17, "Instrumentation Systems,"

requires that four Reactor Protection System {RPS) trip unit

_channels and the associated instrumentation for the functions

listed.in Table 3.17.l, and 6 matrix logic channels and 4

initiation logic channels shall be OPERABLE except as allowed by

the permissible operational bypasses.

Contrary to the above, from the 1992 refueling outage until the

1995 refueling outage, the six RPS matrix logic channels for RPS

c~ntairiment high pressure were not operable in accordance with

TS 3.17.

.

4

l

t

I I

1

l

I

'

\\

f

f 1

l

t

~ . -

<;

,..,

5.0

Safety Significance

The inoperability of the RPS containment high pressure trip since 1992

is considered significant in that a reactor trip function designed to

prevent or mitigate a serious safety event, such as a main steam line

break inside containment, could not perform its intended safety

function.

The licensee. was reviewing the safety analysis to determine

if a delayed reactor trip would exceed containment design pressure.

6.0

Management Debriefing

The inspectors met with licensee representatives (denoted in

Section 7.0) after the inspection on August 4, 1995, to discuss the

scope and findings of the inspection. During the exit meeting, the

inspectors discussed the likely*infrirmational content of the. inspection.

report and documents or processes reviewed by the inspectors during the

inspection:

Licensee representatives did not identify any such

documents or processes as proprietary.

7.0

Persons Contacted

r

Consumers Power Company

  • T. J. Palmisano, Plant General Manager
  • K. P. Powers, Plant Engineering and Modifications Manager_*
  • G. B. Szczotka, RPS Project Team Leader
  • R. A. Vincent, Licensing Administrator

U. S. Nuclear Regulatory Commission

  • D. Passehl, Resident Inspector
  • Denotes those pres_ent during the exit meeting on August 4, 1995.

5

t

\\ t

.r

!

f i Il

t

l

~ ; l

(

Il

. l

t

1I

i l

li