MONTHYEARML18066A6761999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for Palisades Nuclear Plant ML18066A6351999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Palisades Nuclear Plant ML18066A6771999-08-31031 August 1999 Operating Data Rept Page of MOR for Aug 1999 for Palisades Nuclear Plant ML18066A6061999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Palisades Nuclear Plant.With 990803 Ltr ML18066A5201999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Palisades Nuclear Plant.With 990702 Ltr ML18066A4841999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Palisades Nuclear Plant.With 990603 Ltr ML18068A5941999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for Palisades Nuclear Plant.With 990503 Ltr ML18066A6371999-04-30030 April 1999 Revised Monthly Operating Rept for Apr 1999 for Palisades Nuclear Plant ML18066A4501999-03-31031 March 1999 Monthly Operating Rept for Mar 1999 for Palisades Nuclear Plant.With 990402 Ltr ML18068A5351999-02-28028 February 1999 Monthly Operating Rept for Feb 1999 for Palisades Nuclear Plant.With 990302 Ltr ML18066A3931999-01-31031 January 1999 Monthly Operating Rept for Jan 1999 for Palisades Nuclear Plant.With 990202 Ltr ML18066A3651998-12-31031 December 1998 Monthly Operating Rept for Dec 1998 for Palisades Nuclear Plant.With 990105 Ltr ML18066A3421998-11-30030 November 1998 Monthly Operating Rept for Nov 1998 for Palisades Nuclear Plant.With 981202 Ltr ML18068A4921998-10-31031 October 1998 Monthly Operating Rept for Oct 1998 for Palisades Nuclear Plant.With 981103 Ltr ML18066A3181998-09-30030 September 1998 Monthly Operating Rept for Sept 1998 for Palisades Nuclear Plant ML18066A2901998-08-31031 August 1998 Monthly Operating Rept for Aug 1998 for Palisades Nuclear Power Plant.With 980903 Ltr ML18066A3191998-08-31031 August 1998 Revised Monthly Operating Rept Data for Aug 1998 for Palisades Nuclear Plant ML18066A2701998-07-31031 July 1998 Monthly Operating Rept for July 1998 for Palisades Nuclear Plant.W/980803 Ltr ML18066A2311998-06-30030 June 1998 Monthly Operating Rept for June 1998 for Palisades Nuclear Plant ML18066A2321998-05-31031 May 1998 Revised MOR for May 1998 for Palisades Nuclear Plant ML18066A1741998-05-31031 May 1998 Monthly Operating Rept for May 1998 for Palisades Nuclear Plant.W/980601 Ltr ML18066A2331998-04-30030 April 1998 Revised MOR for Apr 1998 for Palisades Nuclear Plant ML18068A3461998-04-30030 April 1998 Monthly Operating Rept for Apr 1998 for Palisades Nuclear Plant.W/980501 Ltr ML18065B2071998-03-31031 March 1998 Monthly Operating Rept for Mar 1998 for Palisades Nuclear Plant.W/980403 Ltr ML18066A2341998-03-31031 March 1998 Revised MOR for Mar 1998 for Palisades Nuclear Plant ML18068A3041998-02-28028 February 1998 Monthly Operating Rept for Feb 1998 for Palisades Nuclear Plant.W/980302 Ltr ML18066A2351998-02-28028 February 1998 Revised MOR for Feb 1998 for Palisades Nuclear Plant ML18067A8211998-01-31031 January 1998 Monthly Operating Rept for Jan 1998 for Palisades Nuclear Plant.W/980203 Ltr ML18065B1341997-12-31031 December 1997 Revised Monthly Operating Rept for Dec 1997 for Palisades Nuclear Plant.W/980106 Ltr ML18065B1041997-11-30030 November 1997 Monthly Operating Rept for Nov 1997 for Palisades Nuclear Plant.W/971202 Ltr ML18067A7661997-10-31031 October 1997 Revised MOR for Oct 1997 for Palisades Nuclear Plant ML18067A7021997-09-30030 September 1997 Monthly Operating Rept for Sept 1997 for PNPP.W/971002 Ltr ML18067A6701997-08-31031 August 1997 Monthly Operating Rept for Aug 1997 for Palisades Nuclear Plant.W/970903 Ltr ML18067A6551997-07-31031 July 1997 Monthly Operating Rept for Jul 1997 for Palisades Nuclear Plant.W/970804 Ltr ML18067A6231997-06-30030 June 1997 Monthly Operating Rept for June 1997 for Palisades Nuclear Plant.W/970702 Ltr ML18067A5621997-05-31031 May 1997 Revised Monthly Operating Rept & Summary of Operating Experience for May 1997 for Pnpp ML18067A5251997-04-30030 April 1997 Revised MOR for April 1997 for Pnp ML18067A4741997-03-31031 March 1997 Monthly Operating Rept for March 1997 for Palisades Nuclear Plant.W/970402 Ltr ML18067A4851997-03-31031 March 1997 Revised Monthly Operating Rept for Mar 1997 for Palisades Nuclear Plant ML18066A8981997-02-28028 February 1997 Monthly Operating Rept for Feb 1997 for Palisades Nuclear Plant.W/970304 Ltr ML18066A9011997-02-28028 February 1997 Monthly Operating Rept for Feb 1997 for Palisades Nuclear Plant.W/970306 Ltr ML18066A8761997-01-31031 January 1997 Monthly Operating Rept for Jan 1997 for Palisades Nuclear Plant.W/970204 Ltr ML18066A8281996-12-31031 December 1996 Monthly Operating Rept for Dec 1996 for Palisades Nuclear Plant.W/970114 Ltr ML18065B1011996-11-30030 November 1996 Monthly Operating Rept for Nov 1996 for Palisades Nuclear Plant.W/961203 Ltr ML18065B0701996-10-31031 October 1996 Monthly Operating Rept for Oct 1996 for Palisades Nuclear Plant.W/961104 Ltr ML18065A9471996-09-30030 September 1996 Monthly Operating Rept for Sept 1996 for Palisades Nuclear Plant.W/961002 Ltr ML20117K1511996-08-31031 August 1996 Monthly Operating Rept for Aug 1996 for Palisades Nuclear Plant ML18065A8691996-07-31031 July 1996 Operating Data Rept for July 1996 for Palisades ML18065A8561996-07-31031 July 1996 Monthly Operating Rept for Jul 1996 for Palisades Nuclear Plant.W/960805 Ltr ML18065A8121996-06-30030 June 1996 Monthly Operating Rept for June 1996 for Palisades Nuclear Plant.W/960702 Ltr 1999-09-30
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML18066A6901999-11-0101 November 1999 Rev 5 to Palisades Nuclear Plant Colr. ML18066A6761999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for Palisades Nuclear Plant ML18066A6271999-09-0202 September 1999 LER 98-011-01:on 981217,inadequate Lube Oil Collection Sys for Primary Coolant Pumps Was Noted.Caused by Design Change Not Containing Appropriate Level of Rigor.Exemption from 10CFR50,App R Was Requested.With 990902 Ltr ML18066A6351999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Palisades Nuclear Plant ML18066A6771999-08-31031 August 1999 Operating Data Rept Page of MOR for Aug 1999 for Palisades Nuclear Plant ML18066A6221999-08-20020 August 1999 LER 99-002-00:on 990722,TS Surveillance Was Not Completed within Specified Frequency.Caused by Failure to Incorporate Revised Frequency Into Surveillance Schedule in Timely Manner.Verified Implementation.With 990820 Ltr ML18066A6061999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Palisades Nuclear Plant.With 990803 Ltr ML18066A5201999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Palisades Nuclear Plant.With 990702 Ltr ML18066A4841999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Palisades Nuclear Plant.With 990603 Ltr ML18066A6371999-04-30030 April 1999 Revised Monthly Operating Rept for Apr 1999 for Palisades Nuclear Plant ML18068A5941999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for Palisades Nuclear Plant.With 990503 Ltr ML18066A4161999-04-0101 April 1999 Rev 4 to COLR, for Palisades Nuclear Plant ML18066A4501999-03-31031 March 1999 Monthly Operating Rept for Mar 1999 for Palisades Nuclear Plant.With 990402 Ltr ML18066A4671999-03-31031 March 1999 Rev 0 to SIR-99-032, Flaw Tolerance & Leakage Evaluation Spent Fuel Pool Heat Exchanger E-53B Nozzle Palisades Nuclear Plant. ML18068A5351999-02-28028 February 1999 Monthly Operating Rept for Feb 1999 for Palisades Nuclear Plant.With 990302 Ltr ML18066A3931999-01-31031 January 1999 Monthly Operating Rept for Jan 1999 for Palisades Nuclear Plant.With 990202 Ltr ML18066A3781999-01-20020 January 1999 LER 98-013-00:on 981222,safeguards Transfer Tap Changer Failure Caused Inadvertant DG Start.Caused by Failed Motor Contactor.Contactor Was Replaced.With 990120 Ltr ML20206F6131998-12-31031 December 1998 1998 Consumers Energy Co Annual Rept. with ML18066A3651998-12-31031 December 1998 Monthly Operating Rept for Dec 1998 for Palisades Nuclear Plant.With 990105 Ltr ML18066A3421998-11-30030 November 1998 Monthly Operating Rept for Nov 1998 for Palisades Nuclear Plant.With 981202 Ltr ML18066A3301998-11-11011 November 1998 Part 21 Rept Re Potential Safety Hazard Associated with Wrist Pin Assemblies for FM-Alco 251 Engines at Palisades Nuclear Power Plant.Caused by Insufficient Friction Fit Between Pin & Sleeve.Supplier of Pin Will No Longer Be Used ML18068A4921998-10-31031 October 1998 Monthly Operating Rept for Oct 1998 for Palisades Nuclear Plant.With 981103 Ltr ML18068A4851998-10-29029 October 1998 LER 97-011-01:on 971012,starting of Primary Coolant Pump with SG Temps Greater than Cold Leg Temps Occurred.Caused by Inadequate Procedures & Operator Decision.Sop Used for Starting Primary Coolant Pump Enhanced ML18066A3181998-09-30030 September 1998 Monthly Operating Rept for Sept 1998 for Palisades Nuclear Plant ML18066A2901998-08-31031 August 1998 Monthly Operating Rept for Aug 1998 for Palisades Nuclear Power Plant.With 980903 Ltr ML18066A3191998-08-31031 August 1998 Revised Monthly Operating Rept Data for Aug 1998 for Palisades Nuclear Plant ML18066A2831998-08-18018 August 1998 LER 98-010-00:on 980721,reactor Manually Tripped.Caused by Failure of Coupling Which Drives Feedwater Pump Main Lube Oil Pump.Main Lube Oil Pump Coupling & Associated Components Replaced & Satisfactorily Tested ML18066A2771998-08-13013 August 1998 Part 21 Rept Re Deficiency in CE Current Screening Methodology for Determining Limiting Fuel Assembly for Detailed PWR thermal-hydraulic Sa.Evaluations Were Performed for Affected Plants to Determine Effect of Deficiency ML20237E0301998-07-31031 July 1998 ISI Rept 3-3 ML18066A2701998-07-31031 July 1998 Monthly Operating Rept for July 1998 for Palisades Nuclear Plant.W/980803 Ltr ML18066A2311998-06-30030 June 1998 Monthly Operating Rept for June 1998 for Palisades Nuclear Plant ML18066A2261998-06-30030 June 1998 LER 98-009-00:on 980531,small Pinhole Leak Found on One of Welds,During Leak Test Following Replacement of Pcs Sample Isolation Valves.Caused by Welder Error.Leaking Welds Repaired ML18066A3061998-06-18018 June 1998 SG Tube Inservice Insp. ML20249C4951998-06-17017 June 1998 Rev 1 to EA-GEJ-98-01, Palisades Cycle 14 Disposition of Events Review ML18066A1781998-06-0909 June 1998 LER 98-008-00:on 980511,noted That Procedure Did Not Fully Satisfy Requirement to Test High Startup Rate Trip Function. Caused by Misunderstanding of Testing Requirements.Revised TS Surveillance Test Procedure & Reviewed Other Procedures ML18066A1711998-06-0101 June 1998 Part 21 Rept Re Impact of RELAP4 Excessive Variability on Palisades Large Break LOCA ECCS Results.Change in PCT Between Cycle 13 & Cycle 14 Does Not Constitute Significant Change Per 10CFR50.46 ML18066A1741998-05-31031 May 1998 Monthly Operating Rept for May 1998 for Palisades Nuclear Plant.W/980601 Ltr ML18066A2321998-05-31031 May 1998 Revised MOR for May 1998 for Palisades Nuclear Plant ML18068A4701998-05-31031 May 1998 Annual Rept of Changes in ECCS Models Per 10CFR50.46. ML18065B2451998-05-13013 May 1998 LER 98-007-00:on 980413,HPIS Sys Was Noted Inoperable During TS Surveillance Test.Caused by Performance of Flawed Procedure.Operators & Engineers Will Be Trained to Improve Operational Decision Making Through Resources & Knowledge ML18066A2331998-04-30030 April 1998 Revised MOR for Apr 1998 for Palisades Nuclear Plant ML18068A3461998-04-30030 April 1998 Monthly Operating Rept for Apr 1998 for Palisades Nuclear Plant.W/980501 Ltr ML18066A3411998-04-22022 April 1998 Rev 0 to EMF-98-013, Palisades Cycle 14:Disposition & Analysis of SRP Chapter 15 Events. ML18065B2071998-03-31031 March 1998 Monthly Operating Rept for Mar 1998 for Palisades Nuclear Plant.W/980403 Ltr ML20217C2741998-03-31031 March 1998 Independent Review - Is Consumers Energy Method (W Method) of Determining Palisades Nuclear Plant Best Estimate Fluence by Combining Transport Calculation & Dosimetry Measurements Technically Sound & Does It Meet Intent of Pts ML18066A2341998-03-31031 March 1998 Revised MOR for Mar 1998 for Palisades Nuclear Plant ML18068A3041998-02-28028 February 1998 Monthly Operating Rept for Feb 1998 for Palisades Nuclear Plant.W/980302 Ltr ML18066A2351998-02-28028 February 1998 Revised MOR for Feb 1998 for Palisades Nuclear Plant ML18065B1641998-02-0505 February 1998 Rev 0 to Regression Analysis for Containment Prestressing Sys at 25th Year Surveillance. ML18067A8211998-01-31031 January 1998 Monthly Operating Rept for Jan 1998 for Palisades Nuclear Plant.W/980203 Ltr 1999-09-30
[Table view] |
Text
consumers Power l'OWERINli NllCHlliAN'S l'RDliRESS Palisades Nuclear Plant: 27780 Blue Star Memorial Highway, Covert, Ml 49043
.September 4~ 1992 US Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 LICENSEE REPORT OF MONTHLY OPERATING DATA DPR-20, DOCKET NO 50-255 Enclosed is a copy of the Monthly Operating Data and Summary of Op_erating Experience for-the Palisades Nuclear Plant for the month of August, 1992.
l.f you have any questions or concerns, please. feel free to contact me at (616) 764-8913, e~tension 0113~*
Sincerely, 111 (; ,.,,,,~
MG Mlynarek
- Reactor Engineer CC: DPHoffman, P26-ll 7B ABDavis, USNRC JLKu~min, Palisades Resid~nt Inspector, Paiisades DRHahn, Div of Rad Health Se~vices, Lansing, MI BWJorgensen, Michigan Dept of Labor, Lansing, MI JPadgett, Michigan Public Service Commission Records Center, INPO, Atlanta, GA RWTaylor, CE, Palisades AAAlatalo, Palisades.
SMMclntyre, Pl3-121 Administrator, USNRC .
Documerit Control, 950*22*35*10/L SMH92*24
~~~~~~~-~-)-~20831 l PDR. ADOCK 0500025-5
,Li. ACM5ENERGYCOMPANY g ,; Pn~
OPERATING DATA REPORT DOCKET NO 50-255 DATE 8-31-92 COMPLETED BY SMHandlovits TELEPHONE (616)764-8913 OPERATING STATUS:
NOTES:
- 1. UNIT NAME Palisades
- 2. REPORTING PERIOD: 920801-920831
- 3. LICENSED THERMAL POWER (MWt) 2530.0
- 4. NAMEPLATE RATING (GROSS MWe) 811.7
- 5. DESIGN ELECTRICAL RATING (NET MWe) 805.0
- 6. MAXIMUM DEPENDABLE CAPACITY (GROSS MWe) **770
- 7. MAXIMUM DEPENDABLE CAPACITY (NET MWe) **730
- 8. IF CHANGES OCCUR IN CAPCITY RATINGS (ITEM NUMBERS 3 AND 7} SINCE LAST REPORT, GIVE REASONS:
- 9. POWER LEVEL TO WHICH RESTRICTED, IF ANY (NET MWe):
- 10. REASONS FOR RESTRICTIONS, IF ANY:
This Month Yr-to-Date Cumulative
- 11. HOURS IN REPORTING PERIOD 744.0 5855.0 181478.0
- 12. NUMBER OF HOURS REACTOR WAS CRITICAL 638.3 3973.3 10i019.9
- 13. REACTOR RESERVE SHUTDOWN HOURS
- 14. HOURS GENERATOR ON-LINE 597.5 3807.6 96719 .1
- 15. UNIT RESERVE SHUTDOWN HOURS
- 16. GROSS THERMAL ENERGY GENERATED (MWH) 1459272.0 9394944.0 206049557.0
- 17. GROSS ELECTRICAL ENERGY GENERATED (MWH) 471820.0 3082498.0 64861223.0
- 18. NET ELECTRICAL ENERGY GENERATED (MWH) 446967.0 . 2929038.0 61101046.0
- 19. UNIT SERVICE FACTOR B0.3% 65.0% 53.3%
- 20. UNIT AVAILABILITY FACTOR 80.3% 65.0% 53.3%
- 21. UNIT CAPACITY FACTOR (USING MDC NET) 82.3% 68.5% 50.5%*
- 22. UNIT CAPACITY FACTOR (USING DER NET) 74.6% 62.1% 41.8%
- 23. UNIT FORCED OUTAGE RATE 19.7% 8.1% 30.7%
- 24. SHUTDOWNS SCHEDULED OVER THE NEXT 6 MONTHS (TYPE, DATE AND DURATION OF EACH):
- 25. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:
- 26. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION):
Forecast Achieved INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION
- Based on condenser backpressure
- Weighted Average (635 MWe used as MDC Net prior to October 1985)
._/
AVERAGE DAILY UNIT POWER LEVEL
- DOCKET NO 50-255 UNIT Palisades DATE 09/02/92 COMPLETED BY SMHandlovits MONTH AUGUST 1992 TELEPHONE (616)764-8913 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe Net) (MWe Net)
- 1. 778 17. 0
- 2. 775 18. 509
- 3. 777 19. 775
- 4. 778 20. 780
- 5. 782 21. 780
- 6. 779 22. 774
- 7. 775 23. 768
- 8. 771 24., 768
- 9. 767 25. 389
- 10. 761 26. 0
. 11. 776 27. 374
- 12. 780 28. 776
- 13. 782 29. 777
- 14. 0 30. 778
- 15. 0 31. 780
- 16. 0 INSTRUCT IONS:
On this format, list the average daily unit power level in MWe-NET for each day in the reporting month. Compute to the nearest whole megawatt.
DOCKET NO 50-255 UNIT Palisades DATE 9/02/92 COMPLETED BY SMHandlovits REPORT MONTH ~A~U~G~US~T_l~9~9~2- - - - - TELEPHONE (616)764-8913 UNIT SHUTDOWNS AND POWER REDUCTIONS No. Date Type 1 Duration Reason 2 Method of Licensee System Component Cause & Corrective (Hours) Shutting Event Code 4 Code5 Action to Down Reactor 3 Report # Prevent Recurrence 03 920814 F 95.7 A 3 LER 92036 Failed air line to Feedwater Regulating Valve 04 920825 F 50.8 A 3 LER 92037 Failed solenoid in Y-20 Preferred AC Bus
- 1. 2. 3. 4. 5.
F: Forced Reason: Method: Exhibit G - Instructions Exhibit I - Same Source S: Scheduled A-Equipment Failure (Explain) !-Manual for Preparation of Data B-Maintenance or Test 2-Manual Scram Entry Sheets for Licensee C-Refue ling 3-Automatic Scram Event Report (LER) File D-Regulatory Restriction 4-0ther (Explain) (NUREG-0161)
E-Operator Training & License Examination F-Administrative G-Operational Error (Explain)
H-Other (Explain)
SUMMARY
OF OPERATING EXPERIENCE FOR AUGUST 1992 The unit began the month at full power but tripped on August 14 at 0017 hours1.967593e-4 days <br />0.00472 hours <br />2.810847e-5 weeks <br />6.4685e-6 months <br />.
The reactor went critical August 16 at 1330 hours0.0154 days <br />0.369 hours <br />0.0022 weeks <br />5.06065e-4 months <br /> and was on-line August 17 at 1749 hours0.0202 days <br />0.486 hours <br />0.00289 weeks <br />6.654945e-4 months <br /> but then came off-1 ine at 2017 hours0.0233 days <br />0.56 hours <br />0.00333 weeks <br />7.674685e-4 months <br /> and remained critical. The unit was placed on-line again August 18 at 0230 hours~ Full power was reached August 19 at 0423 hours0.0049 days <br />0.118 hours <br />6.994048e-4 weeks <br />1.609515e-4 months <br /> and continued at 100% power until August 25 when the plant tripped at 0129 hours0.00149 days <br />0.0358 hours <br />2.132936e-4 weeks <br />4.90845e-5 months <br />. Criticality was achieved August 26 at 2200 hours0.0255 days <br />0.611 hours <br />0.00364 weeks <br />8.371e-4 months <br /> and went on-1 i ne August 27 at 0417 hours0.00483 days <br />0.116 hours <br />6.894841e-4 weeks <br />1.586685e-4 months <br />. Full power was reached August 28 by 0800 hours0.00926 days <br />0.222 hours <br />0.00132 weeks <br />3.044e-4 months <br /> and continued until the end of the month.