Comment (011) of Pamela Cowan, Vice President of Nuclear Generation - Nuclear Energy Institute (Nei), Regarding Revision of Fee Schedules; Fee Recovery for Fiscal Year 2018ML18058A247 |
Person / Time |
---|
Site: |
Nuclear Energy Institute |
---|
Issue date: |
02/26/2018 |
---|
From: |
Nuclear Energy Institute |
---|
To: |
|
---|
References |
---|
83FR03407, Docket No. NRC-2017-0026, PR-170 and 171 |
Download: ML18058A247 (3) |
|
|
---|
Category:Rulemaking-Comment
MONTHYEARML24023A6042024-01-22022 January 2024 Comment (011) from Jennifer Uhle on Behalf of the Nuclear Energy Institute on PR-50, 51, and 71 - Increased Enrichment of Conventional and Accident Tolerant Fuel Designs for Light-Water Reactors ML23296A0792023-10-18018 October 2023 Comment Period Extension Request from the Nuclear Energy Institute on PR-50, 51, and 71 - Increased Enrichment of Conventional and Accident Tolerant Fuel Designs for Light-Water Reactors ML23177A2492023-06-23023 June 2023 Comment (012) from Thomas Basso on Behalf of the Nuclear Energy Institute on PR-50 - American Society of Mechanical Engineers Code Cases and Update Frequency ML23171B0032023-06-15015 June 2023 Comment (011) from Thomas Basso on Behalf of the Nuclear Energy Institute on PR-50 - American Society of Mechanical Engineers Code Cases and Update Frequency ML23123A4072023-05-0202 May 2023 Comment (0018) from Jennifer Uhle on Behalf of the Nuclear Energy Institute on PR-51 - Renewing Nuclear Power Plant Operating Licenses - Environmental Review ML23095A0372023-04-0404 April 2023 Comment (001) from Mark A. Richter on Behalf of the Nuclear Energy Institute on PR-50 - American Society of Mechanical Engineers Code Cases and Update Frequency ML23093A1882023-03-31031 March 2023 Comment (003) from Dr. Jennifer L. Uhle on Behalf of the Nuclear Energy Institute on PR-170 and 171 - Revision of Fee Schedules; Fee Recovery for Fiscal Year 2023 ML23080A1862023-03-17017 March 2023 Comment (001) from Douglas E. True on Behalf of the Nuclear Energy Institute on PR-30, 40, 50, 70 & 72 - Alternatives to the Use of Credit Ratings ML23062A7162023-03-0303 March 2023 Comment (006) from Frances Pimentel on Behalf of Nuclear Energy Institute on PRM-50-124 - Licensing Safety Analysis for Loss-of-Coolant Accidents ML23031A3022023-01-30030 January 2023 Comment (006) from Tony Brown on Behalf of the Nuclear Energy Institute on PR-50 - Reporting Requirements for Nonemergency Events at Nuclear Power Plants ML22333B0322022-11-28028 November 2022 Comment (014) from the Nuclear Energy Institute on PR-71 - Harmonization of Transportation Safety Requirements with IAEA Standards ML22243A2572022-08-31031 August 2022 Comment (115) of Doug True on Behalf of Nuclear Energy Institute (NEI) on PR-53 - Risk-Informed, Technology-Inclusive Regulatory Framework for Advanced Reactors ML22243A1972022-08-30030 August 2022 Comment (092) from Bruce Montgomery of the Nuclear Energy Institute on PR-20, 26, 50, 51, 52, 72, 73 and 140 - Regulatory Improvements for Production and Utilization Facilities Transitioning to Decommissioning ML22087A0522022-03-24024 March 2022 Comment (003) of Jennifer Uhle on Behalf of Nuclear Energy Institute on PR-170, 171 - Fee Recovery for Fiscal Year 2022 ML22025A2332022-01-21021 January 2022 Comment (01) of Janet Schlueter on Behalf of Nuclear Energy Institute on PR-11, 25 and 95 - Access Authorization Fees ML21309A5782021-11-0505 November 2021 Comment (080) of the Nuclear Energy Institute and the U.S. Nuclear Industry Council on PR-53 - Risk-Informed, Technology-Inclusive Regulatory Framework for Advanced Reactors ML21288A1302021-10-14014 October 2021 Comment (004) of Dr. Jennifer L. Uhle on Behalf of the Nuclear Energy Institute on PR-52 - NuScale Small Modular Reactor Design Certification ML21287A1462021-09-30030 September 2021 Comment (008) of Nuclear Energy Institute on PRM-50-119 - Access to the Decommissioning Trust Fund for the Disposal of Large Components ML21274A0702021-09-28028 September 2021 Comment (062) of Douglas True on Behalf of the Nuclear Energy Institute on PR-53 - Risk-Informed, Technology-Inclusive Regulatory Framework for Advanced Reactors ML21265A4442021-09-15015 September 2021 Comment (007) of Marcus Nichol on Behalf of the Nuclear Energy Institute on PR-2,21,26,50,51,52,55,73 - Alignment of Licensing Processes and Lessons Learned from New Reactor Licensing ML21244A3312021-08-31031 August 2021 Comment (061) of Marcus Nichol on Behalf of Nuclear Energy Institute on PR-53 - Risk-Informed, Technology-Inclusive Regulatory Framework for Advanced Reactors ML22133A2292021-08-30030 August 2021 EPFAQ 2021-001 Clarification of Section 4.3 of NUREG-7002, Criteria for Development of Evacuation Time Estimate Studies, Regarding Acceptable Error And/Or Confidence Interval ML21203A2252021-07-21021 July 2021 Comment (006) of Martin O'Neill on Behalf of Nuclear Energy Institute on ANPR-51 - Categorical Exclusions from Environmental Review ML21197A1032021-07-16016 July 2021 Comment (056) of Marcus Nichol on Behalf of the Nuclear Energy Institute on PR-53 - Risk-Informed, Technology-Inclusive Regulatory Framework for Advanced Reactors ML21196A4982021-07-14014 July 2021 Comment (054) Submitted by Nuclear Energy Institute on Behalf of Multiple Stakeholders as Unified Industry Position on PR-53 - Risk-Informed, Technology-Inclusive Regulatory Framework for Advanced Reactors ML21168A0952021-06-15015 June 2021 Comment (002) from the Nuclear Energy Institute on PRM-37-2 - Advance Tribal Notification of Certain Radioactive Material Shipments ML21166A1192021-06-14014 June 2021 Comment (045) of David Young on Behalf of Nuclear Energy Institute (NEI) on PR-53 - Risk-Informed, Technology-Inclusive Regulatory Framework for Advanced Reactors ML21145A1722021-05-25025 May 2021 Comment (004) of Thomas Basso on Behalf of Nuclear Energy Institute on PR-50 - American Society of Mechanical Engineers 2019-2020 Code Editions ML21144A2892021-05-20020 May 2021 Comment (024) of William Gross on Behalf of Nuclear Energy Institute Regarding PR-26 - Fitness for Duty Drug Testing Requirements ML21144A1642021-05-14014 May 2021 Comment (005) of Marcus Nichol on Behalf of the Nuclear Energy Institute on PR-2,21,26,50,51,52,55,73 - Alignment of Licensing Processes and Lessons Learned from New Reactor Licensing ML21095A1002021-04-0101 April 2021 Comment (006) from the Nuclear Energy Institute on PR-50 - Approval of American Society of Mechanical Engineers' Code Cases ML21083A2882021-03-24024 March 2021 Comment (005) of Jennifer Uhle on Behalf of Nuclear Energy Institute on PR-15, 170 & 171 - Revision of Fee Schedules; Fee Recovery for Fy 2021 ML21068A3572021-03-0909 March 2021 Comment Period Extension Request of Marcus Nichol on Behalf of the Nuclear Energy Institute on PR-2,21,26,50,51,52,55,73 - Alignment of Licensing Processes and Lessons Learned from Nr Licensing ML21068A0972021-03-0808 March 2021 Comment (004) of Douglas True on Behalf of Nuclear Energy Institute (NEI) on PR-30, 40, 50, 70, and 72 - Alternatives to the Use of Credit Ratings ML21042B8892021-02-11011 February 2021 Comment (016) of Marcus Nichol on Behalf of Nuclear Energy Institute (NEI) on PR-53 - Risk-Informed, Technology-Inclusive Regulatory Framework for Advanced Reactors ML21048A3602021-02-0101 February 2021 Comment (004) of Ellen C. Ginsberg on Behalf of the Nuclear Energy Institute on PR-1 - NRC Enforcement Policy ML21061A0442021-01-0707 January 2021 Comment (03) of Douglas True on Behalf of Nuclear Energy Institute (NEI) on Proposed Evaluation Policy Statement ML20363A2272020-12-23023 December 2020 Comment (004) of Marcus Nichol on Behalf of Nuclear Energy Institute (NEI) on PR-53 - Risk-Informed, Technology-Inclusive Regulatory Framework for Advanced Reactors ML20289A6322020-10-15015 October 2020 Comment (001) of David Young on Behalf of the Nuclear Energy Institute on PRM-50-123- Public Protective Actions During a General Emergency ML20267A3262020-09-22022 September 2020 Comment (194) of Marcus Nichol on Behalf of Nuclear Energy Institute on PR- 50, 52- Emergency Preparedness for Small Modular Reactors and Other New Technologies ML20233A5892020-08-10010 August 2020 Comment (03) of Hilary Lane on Behalf of Nuclear Energy Institute (NEI) on PRM-50-121 - Voluntary Adoption of Revised Design Basis Accident Dose Criteria ML20128J3402020-05-0606 May 2020 Comment (01) of James E. Slider on Behalf of the Nuclear Energy Institute on PR-Chap 1- Retrospective Review of Administrative Requirements ML20077K3382020-03-16016 March 2020 Comment (003) from Jennifer Uhle on Behalf of the Nuclear Energy Institute on PR-170 and 171 - Revision of Fee Schedules; Fee Recovery for Fiscal Year 2020 ML19338D2552019-12-0202 December 2019 Comment (017) of William Gross on Behalf of the Nuclear Energy Institute Regarding PR-026 - Fitness for Duty Drug Testing Requirements ML19325C8352019-11-19019 November 2019 Comment (043) of Janet Schlueter from the Nuclear Energy Institute on PR-061 - Greater-Than-Class-C and Transuranic Waste ML19228A1842019-08-15015 August 2019 Comment (07) of Michael Tschiltz on Behalf of Nuclear Energy Institute on PR-50, 52, 73 - Physical Security for Advanced Reactors ML16068A2522019-07-30030 July 2019 Mitigation Beyond-Design-Basis Events Proposed Rule Comment (9) - NEI (Annotated) Original Submission Dated February 9, 2016 (ML16041A445) ML19178A3312019-06-27027 June 2019 Comment (01) of Michael D. Tschiltz on Behalf of Nuclear Energy Institute (NEI) on PRM-171-1 - Petition of Southern Nuclear to Revise Part 171 - Nuclear Power Plant Licensee Fees Upon Commencing Commercial Operation ML19149A4742019-05-28028 May 2019 Comment (06) of Janet Schlueter on Behalf of Nuclear Energy Institute (NEI) on PR-71 - Harmonization of Transportation Safety Requirements with IAEA Standards ML19123A1302019-05-0303 May 2019 Comment (25) from Nima Ashkeboussi on Behalf of NEI on PR-40 Regarding Ground Water Protection at Uranium in Situ Recovery Facilities 2024-01-22
[Table view] |
Text
Page 1 of 1 PR-170 and 171 83FR03407 11 As of: 2/27/18 9:13 AM Received: February 26, 2018 PUBLIC SUBMISSION Status: Pending_Post Tracking No. 1k2-91pw-udjv Comments Due: February 26, 2018 Submission Type: Web Docket: NRC-2017-0026 Revision of Fee Schedules: Fee Recovery for FY 2018 Comment On: NRC-2017-0026-0001 Revision of Fee Schedules; Fee Recovery for Fiscal Year 2018 Document: NRC-2017-0026-DRAFT-0010 Comment on FR Doc # 2018-01065 Submitter Information Name: Pamela Cowan Submitter's Representative: Allison Borst Organization: Nuclear Energy Institute General Comment See attached file(s)
Attachments 02-26-18_NRC_NEI Comments on FY18 Proposed Fee Rule https://www.fdms.gov/fdms/getcontent?objectId=0900006482f6502e&format=xml&showorig=false 02/27/2018
PAMELA B. COWAN Vice President, Nuclear Generation 1201 F Street, NW, Suite 1100 Washington, DC 20004 P: 202.739.8093 pbc@nei.org nei.org February 26, 2018 Ms. Annette Vietti-Cook Secretary U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 ATTN: Rulemaking and Adjudications Staff Submitted via Regulations.Gov
Subject:
Industry Comments on Fiscal Year 2018 Proposed Fee Rule (NRC Docket ID NRC-2017-0026)
Project Number: 689
Reference:
Letter, J. Pollock (NEI) to A. Vietti-Cook (NRC), Fuel Cycle Industry and Materials User Comments on Fiscal Year 2018 Proposed Fee Rule (NRC Docket ID NRC-2017-0026), dated February 26, 2018
Dear Ms. Vietti-Cook:
On behalf of the Nuclear Energy Institutes (NEI)1 members (hereinafter referred to as industry), we provide the following comments for the U.S. Nuclear Regulatory Commission (NRC) staffs consideration as it finalizes the fiscal year 2018 fee rule. Additional comments highlighting specific concerns of fuel cycle licensees and materials users are provided in the above referenced NEI letter.
We appreciate the public meeting held by Ms. Maureen Wylie and other NRC managers and staff on February 12, 2018 to discuss the FY 2018 proposed fee rule and its underlying basis and assumptions.
These meetings are informative and we ask that they be continued.
The FY 2018 proposed fee rule is based on the FY 2018 Congressional Budget Justification (CBJ) with $15 million added for the Integrated University Program. While we recognize that the final fee rule will be adjusted based on the final Congressional appropriation, the NRC budget in the proposed rule represents a 5% increase over fiscal year 2017. Accommodating any increase in budget and associated fees to licensees will be challenging to industry and further highlights the need for the agency to continue its efforts to 1
The Nuclear Energy Institute (NEI) is the organization responsible for establishing unified industry policy on matters affecting the nuclear energy industry, including the regulatory aspects of generic operational and technical issues. NEI's members include entities licensed to operate commercial nuclear power plants in the United States, nuclear plant designers, major architect/engineering firms, fuel cycle facilities, nuclear materials licensees, and other organizations and entities involved in the nuclear energy industry.
Ms. Annette Vietti-Cook February 26, 2018 Page 2 pursue efficiencies in its operations and programs.
Safe and reliable operation has been, and will always be, the top priority of our industry, and in todays current economic environment, where budgets are shrinking and cost reductions are mandated, the NRCs budget is a fundamental concern. There are eight operating commercial nuclear power plants with announced premature closings between now and 2025, representing a significant portion of the current NRC budget. In the last two fiscal years there has been a 13% decrease in work directly billable to licensees (Part 170), reflecting in part the economic constraints noted above. However, despite the implementation of efficiency measures resulting from Project AIM, most fee classes are facing a 6% or more increase in annual fees (Part 171), as well as a 2.7% increase in the professional hourly rate. Given the critical state of the industry, this disparity cannot be maintained and must be promptly corrected.
Recent improvements in the clarity and transparency of invoices issued to licensees are greatly appreciated.
However, additional action is needed to address remaining areas of concern. One such area occurs in billing of inspection costs. Estimates of direct inspection hours are available for each inspection (totaling approximately 1,863 hour0.00999 days <br />0.24 hours <br />0.00143 weeks <br />3.283715e-4 months <br />s/site under the baseline inspection program), but invoices currently do not distinguish between direct inspection hours and inspection support activities. The cost for these support activities, which include documentation, preparation, travel and significance determination efforts, are in many cases double or triple the cost of direct inspection hours (Average 3,488 hour0.00565 days <br />0.136 hours <br />8.068783e-4 weeks <br />1.85684e-4 months <br />s/site). The absence of estimates for support activities necessary for each inspection and a clear identification of support hours presents a challenge for accountability and tracking of inspection costs. Invoices should identify costs associated with the separate and distinct aspects of inspections (e.g., direct inspection hours, preparation, documentation, travel, significance determination process).
Regarding the administrative changes included in the proposed rule, we support the revision that removes the 6% overhead charge for project managers and resident inspectors; replacing this charge with actual hours for activities that support licensees.
NRC fees represent a significant factor in the preparation and planning of budgets for the industry, therefore, it is important that NRC communicate anticipated changes to fee schedules as early as possible.
We ask that revised fee schedules be released in advance of publication of the final fee schedule so that timely adjustments to budgets can be made.
Please contact me if you have any questions regarding these comments.
Sincerely, Pamela Cowan c: Ms. Maureen Wylie, NRC/CFO