ML18058A161

From kanterella
Jump to navigation Jump to search
Safety Insp Rept 50-255/91-26 on 911120 & 920116.Violations Noted.Major Areas Inspected:Completeness & Accuracy of Info Provided to NRC as Required by 10CFR50.9.Samples of Previous Submittals & Current Info Provided to NRC Reviewed
ML18058A161
Person / Time
Site: Palisades Entergy icon.png
Issue date: 02/05/1992
From: Jeffrey Jacobson, Ring M
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML18058A159 List:
References
50-255-91-26, NUDOCS 9202110222
Download: ML18058A161 (6)


See also: IR 05000255/1991026

Text

U. S. NUCLEAR REGULATORY COMMISSION

REGION III

Report No. 50-255/91026(DRS)

Docket No. 50-255

License No. DPR-20

Licensee:

Consumers Power Company

1945 West Parnall Road

Jackson, MI

49201

Facility Name:

Palisades Nuclear Generating Plant*

Inspection At:

Covert, MI

(November 20, 1991)

Meeting at Region III Office (January 16, 1992)

Inspection Conducted:

November 20, 1991 and January 16, 1992

Inspector: 7!11Ufftff:i f 6) J. J&cob.so~

J.

. Jacobs

Also participating in this inspection:

Approved

B. E. Holian, LPM, NRR

R. Devitto, or, RIII

By:~

M.:RiilglChief

Engineering Branch

Inspection Summary

-~/.;h~

Date

Inspection on November 20, 1991 and January 16, 1992 (Report No.

50-255/91026CDRS))

Areas Inspected:

Special unannounced inspection regarding the

completeness and accuracy of information provided to the NRC as

required by 10 CFR 50.9.

Samples of previous submittals and

current information provided to the NRC were reviewed.

Results:

Three historical samples of inaccurate information are

provided as background information and two current examples are

cited as a Severity Level IV violation of 10 CFR 50.9

requirements.

9202110222 920205

~DR ADOCK 05000255

PDR

DETAILS

1.

Persons Contacted

Consumers Power Company CCPCol

  • P .* Donnelly, Safety and Licensing Director
  • J. Kuemin, Licensing Administrator

K. Marbaugh, Performance Trending and Analysis Supervisor

G. Davis, Lead Engineer, Steam Generator Replacement

Project

R. Jenkins, Section Head, Civil, Structural Engineering

Bechtel Corporation (Bechtel)

G. Brown, Project Engineer

R. Parekj, Chief, Plant Design Engineer

Nuclear Regulatory Commission CNRCl

  • J. Gavula, Reactor Inspector
  • M. Ring, Chief, Engineering Branch
  • E. Schweibinz, Senior Project Engineer
  • Denotes those participating in the exit meeting conducted

on January 16, 1992.

2.

Review of Information Submitted to the Nuclear Regulatory

Commission

a.

Background

Two historic written responses regarding NRC

violations, and one letter to the Office of Nuclear

Reactor Regulation (NRR) regarding the use of an

alternative inspection technique, were reviewed for

accuracy of information as follows:

(1)

The licensee's response to violation 255/89024-01

(Example A.2) is discussed in Paragraph 2.d. of

NRC Inspection Report No. 50-255/90014.

As

discussed in this report, the licensee's response

dated April 12, 1990, stated on Page 8 of

Attachment 1 that the subject stress calculations

were currently in final review and would be

completed by April 30, 1990.

On May 2, 1990, the

licensee informed the NRC resident inspector that

the package was not complete and in fact, was not

in final review.

During the exit interview for

NRC Inspection Report No. 50-255/90014, the

1

(2)

potential consequences of providing false

information was discussed.

Violation 255/89007-ld, written as an example of

inadequate design control, pertained to the

calculation of post modification test acceptance

criteria for several nitrogen backup systems.

The

acceptance criteria were used to verify the design

assumptions pertaining to system leakage and

volumetric usage for certain air operated valves.

In calculating the allowable test pressure drop in

the tank, an incorrect volume of the nitrogen tank

was used.

Instead of using the actual volume of

228 standard cubic feet (scf), a smaller "usable"

volume of 209 scf was used.

While the smaller

value is conservative in determining the number of

tanks required, it is nonconservative if used to

determine the allowable pressure drop for the post

modification test.

Since the initial volume

appears in the denominator of the pressure drop

equation, it is relatively simple to deduce that

the use of the smaller tank volume resulted in a

higher allowable drop in the test pressure.

In the licensee's August 10, 1989 response to the

NRC, CPCo gave three reasons why they did not

consider this as an example of a design control

violation.

They strongly maintained that the

pressure drop calculation was appropriate and

conservative.

The NRC reviewed the response and

concluded that the reasons given did not have any

technical merit and that the licensee had again

failed to recognize that they had disregarded

basic engineering principles regarding pressure

drops.

During a subsequent discussion with the NRC on

November 2, 1989, the licensee acknowledged that

the calculation was, in fact, incorrect and

nonconservative.

It was apparent that the

licensee's initial response was inadequate and

that efforts toward assuring the accuracy of the

information provided to the NRC were insufficient.

As a result of this discussion, the licensee

submitted an additional response with corrective

actions for the design control violation.

(3)

The NRC conducted an inspection (50-255/89026)

regarding the use of an alternative inspection

technique used in lieu of ASME Code required

hydrostatic pressure testing.

The details of this

2

alternative inspection technique were specified in

the H.A.F.A. International, Inc., Topical Report

HAFA 135(P) (A).

This topical report was approved

by the NRC for licensing reference on November 7,

1985.

Contained within this topical report was a

requirement to perform an evaluation of the system

prior to application of the alternative technique.

A letter from CPCo to the NRC dated August 10,

1988, notified the NRC of CPCo's intent to utilize

the alternative technique on several plant

systems.

This letter further stated that the

appropriate evaluations, as required by Section IV

of the topical report, had been completed and were

available at the Palisades site.

During an inspection (50-255/89026), the NRC

inspector requested that the evaluations be made

available for review.

Further discussions

revealed that the evaluations were not available

at the site and in fact, had not been performed.

The licensee was cautioned that information

supplied to the NRC must be accurate and complete.

b.

Review of Current Submittals

(1)

During December 1990, while performing an NRC

inspection (50-255/90025) of the Steam Generator

Replacement Project (SGRP), an inspector

identified the application of inappropriate

seismic response spectra to the piping analysis.

On February 8, 1991, the licensee presented their

position during a meeting at NRC Headquarters and

concluded that the piping seismic analysis met the

FSAR criteria.

NRC inspection of the SGRP also identified several

examples of design control deficiencies which

ultimately led to additional inspection effort

(50-255/91202) and escalated enforcement action.

During the October 15, 1991 Enforcement Conference

held at the Region III office, the licensee again

presented their position on the NRC finding

concerning piping seismic analysis.

At this time,

information was presented which led the NRC to

believe that the licensee recognized early in the

project that the seismic calculation basis

described in the FSAR could not be met.

The apparent conflict of information prompted the

NRC to visit the site and conduct interviews of

individuals involved in this issue.

Due to the

3

potential of this information being considered a

material false statement, the NRC Office of

Investigations was asked to assist with the

interviews.

As a result of the interviews and reviews of

supporting documentation, the NRC inspectors

concluded that the apparent conflicting

information presented to the NRC was due to a CPCo

individual misinterpreting information provided by

Bechtel as indicating that early in the SGRP,

Bechtel had stated that the seismic calculation

basis described in the FSAR could not be met.

The inaccurate information presented to the NRC

regarding FSAR compliance for seismic analysis of

piping is considered an example of a violation of

10 CFR 50.9 (255/91026-0lA).

(2)

As a result of NRC Inspection Report No. 50-

255/91017, the licensee was issued violations for

operating the plant without containment spray pump

and high pressure safety injection pump

availability.

This inspection report documents

that on June 27, 1991, the NRC inspector was told

by shift supervision that when equipment is

returned to an operable status after breakers have

been racked out, the components are always start

tested.

The licensee replied to the NRC's Notice of

Violation in a letter dated December 9, 1991.

This reply stated that the racking out and in of

breakers and the removal and replacement of

closing coil and control power fuses was

considered routine and did not require start

testing of the components upon return to service.

This apparent conflict of information was brought

to the licensee's attention and resulted in a

revised reply dated December 13, 1991.

This reply

stated that the test starting of components

following the racking in of breakers or

replacement of fuses was not required by

procedures; however, instructions to test energize

equipment after racking in of breakers was posted

on the 2400v cubicle doors.

The inaccurate information presented to the NRC

regarding the licensee's practice of test starting

equipment upon racking in of breakers is

considered an example of a violation of 10 CFR

4

.

,

50.9 (255/91026-0lB).

Both of the examples cited above related to information

which was involved in escalated enforcement action and

as such, are considered to be of more than minor

significance.

3.

Exit Interview

The NRC inspectors met with the licensee representatives

(denoted in Paragraph 1) at the conclusion of the inspection

on January 16, 1992, as well as periodically during the

course of the inspection.

The inspectors summarized the

purpose and findings of the inspection.

The licensee

representatives acknowledged this information.

The

inspectors also discussed the likely informational content

of the inspection report with regard to documents or

processes reviewed during the inspection.

The licensee

representatives did not identify any such

documents/processes as proprietary .

5