ML18054A823

From kanterella
Jump to navigation Jump to search
Forwards Team Insp Rept 50-255/89-07 on 890403-0505 & Notice of Violation.Both Strengths & Weaknesses Discussed
ML18054A823
Person / Time
Site: Palisades Entergy icon.png
Issue date: 06/28/1989
From: Miller H
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Hoffman D
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
Shared Package
ML18054A824 List:
References
NUDOCS 8907050304
Download: ML18054A823 (3)


See also: IR 05000255/1989007

Text

JUN 2 8 1989

Docket No. 50-255

Consumers Power Company

ATTN: 'David P. Hoffman

Vice President

Nuclear Operations

1945 West Parnall Road

Jackson, MI

49201

Gentlemen:

This refers to the special team inspection conducted by Mr. Rolf A. Westberg

and oth~rs of this office on April 3 through May 5, 1989, of activities relatjve

to the design basis reconstitution portion of the Configurati6n Control Project

(CCP), to the technical adequacy of design changes and to inservice testing

(IST) of pumps and valves at the Palisades Nuclear Generating Plant authorized

by NRC Operating License No. DPR-20.and to the discussion of our findings with

Mr. R. D. Orosz and others of your staff at the conclusion of the inspection.

The enclosed copy of our inspection report identifies areas examined during the

inspection. Within these areas, the inspection consisted of a selective

examination of procedures and representative records, observations, and

interviews with personnel .

The inspection of design changes and IST produced evidence of program strengths

such as good design procedures; improved performance in pump and valve testing;

and competent, knowledgeable ,personnel.

However, the results of this inspection

indicated weaknesses relative to design control. Several examples of problems

noted were as follows:

0

0

Review of ten specification changes and *nine facility changes resulted in

nineteen examples of inadequate design control.

One specific example

involved the addition of zener diodes in the Safety Injection Tank pressure

transmitter power supply without fully analyzing the potential failure

modes and without checking diode output voltage after installation. In this

case, vendor recommended input voltage to downstream pressure transmitters

was actually exceeded.

Review of the Backup Nitrogen Supply modification indicated that the design

engineer specified an inappropriate weld.

Field personnel did not reject

the design and implemented their own interpretation of-weld requirements

instead of referring the matte~ to engineering for resolution. This

constitutes an unauthorized design change .

Consumers Power Company

2

JUN 2 8 1989

0

0

The FSAR was changed to take advantage of the stress intensification

factor (SIF) allowed by a later edition of the ASME Code;

howe~er, this

same later edition also increasectthe SIF for so-cket welde*d fittings which

was not incorporated into the FSAR.

By selectively using the code of

convenience, the SIF employed became less than unity which had the

potential of introducing non-conservatism into analyses in which it was

used.

The Engineering Design Change (EDC) form used on site to revise facility

changes does not list the calculations affected by the EDC; therefore, it

is uncertain if the technical reviewers have considered the effects of

the EDC on the original analyses. This may constitute an undocumented

engineering judgement.

Taken individually, the safety significance of the above weaknesses and the

violations in the body of the report is small.

However, when taken as a whole,

we are concerned that the problems may be generic. Another concern that stems

from several of these examples is that modifications being made under the

Palisades Specification Change process are not consistently receiving an

adequate level of attention.

Because of the large number of implementation deficiencies relative to design

control,. consideration was given by Region III to taking escalated enforcement

action for the violations in Appendix A.

However, these violations were

categorized at Severity Level IV because the violations had minor safety

significance and did not result in deficient hardware or impact equipment

operability.

The program strengths stated previously and your effective post-

modification testing program were also considered in determining that these

violations do not represent a broad programmatic breakdown in design control

warranting a Severity Level III violation.

The inspection of the CCP indicated that electrical design basis documents

(DBDs) are well organized and useful; however, the only mechanical DBD completed

to date was considered poorly organized and difficult to use.

During this inspection, certain of your activities appeared to be in violation

of NRC requirements, as specified in the enclosed Notice.

A written response

is required; however~ any corrective action taken should include but not be

limited to the specific examples presented by this report.

We also request

that you address in your response the specific examples of program weaknesses

stated previously and the unresolved items in the repor,t relative to welding

issues concerning Auxiliary Feedwater and Reactor Coolant System Cold Leg drain

valve modifications.

This letter also confirms our plans as discussed on June 27, 1989, between

Mr. R. N. Gardner of our staff and Mr. R. D. Orosz of your staff to conduct a

meeting on August 2, 1989, at the Region III office in Glen Ellyn, Illinois .

The meeting is to discuss your corrective actions relative to the violations

and other program weaknesses described in this report.

Consumers Power Company

3

JUN 2 81989

We will gladly discuss any questions you have concerning this -inspection.

Enclosures:

1.

Notice of Violation

2.

Inspection Report

No. 50-255/89007(DRS)

3.

Attachments

cc w/enclosures:

Mr. Kenneth W. Berry, Director

Nuclear Licensing

Gerald B. Slade, General Manager

DCD/DCB (RIDS)

Licensing Fee Management Branch

Resident Inspector, RIII

Ronald Callen, Mi£higan

Public Service Commission

Michigan Department of

Public Health

.

~~

Burgess

4.{ 7...3 / s-~

Sincerely,

Original signed by R. W. Cooper, II, (for)

Hubert J. Miller, Director

Division of Reactor Safety

RIII A

., fl /J-"'

Rn

Gardner

G~L-j~'\\