ML18046A708

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-255/81-06,on 810401-0502.Noncompliance Noted:Licensed Matls Stored in Unrestricted Area Not Secured from Unauthorized Removal;Failure to Implement Fire Protection Procedures
ML18046A708
Person / Time
Site: Palisades 
Issue date: 05/19/1981
From: Boyd D, James Heller, Jorgensen B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML18046A705 List:
References
50-255-81-06, IEB-80-10, NUDOCS 8106090409
Download: ML18046A708 (9)


See also: IR 05000255/1981006

Text

U. S. NUCLEAR REGULATORY COMMISSION

OFFICE OF INSPECTION AND ENFORCEMENT

REGION III

Report No. 50-255/81-06

Docket No.

50-255

Licensee:

Consumers Power Company

212 West Michigan Avenue

Jackson, MI

49201

Facility Name:

Palisades Nuclear Generating Plant

Inspection At:

Covert, MI*

Inspection Conducted:

April 1-4, 6-10, 12-17, 20-24, 26-30, and May 1-2, 1981

/f(C~ -~

Inspectors:

B. L. Jorg'~nsen

~~-

S-/Y-J/

JJC~

J,,~ ~

J. K. Heller~

~

rvy-

Approved By:

J< c tc:uo1~

D. C. Boyd, Chief

,~

Reactor Projects Section lA

Inspection Summary

Inspection during April 1-4, 6-10, 12-17, 20-24, 26-30, and May 1-2, 1981

(Report No. 50-255/81-06)

Areas Inspected:

Augmented resident inspection program activities including

operations; surveillance; maintenance; reportable events; IE Bulletins;

spent fuel pool modifications; and independent reviews.

The inspection

involved a total of 172 inspector-hours by 2 NRC inspectors including 58

inspector-hours onsite during off-shift hours.

Results:

Of the seven areas inspected, no items of noncompliance were

identified in five areas.

Two noncompliances were identified in the other

two areas .

DETAILS

1.

Persons Contacted

2.

  • R. W. Montross, General Manager
  • J. S. Rang, Operations/Maintenance Superintendent
  • H. J. Palmer, Technical Sup~rintendent
  • G. H. R. Petitjean, Technical Engineer
  • A. D. Kowalczuk, Chemistry/Health Physics Superintendent
  • R. E. McCaleb, Quality Assurance Administrator
  • W. P. Mullins, Plant Health Physicist

W. S. Skibitsky, Operations Superintendent

G. W. Ford, Senior Engineer (STA)

A. F. Brookhouse, Shift Supervisor

S. Ghidotti, Shift Supervisor

A. S. Kanicki, Shift Supervisor

D. W. Kaupa, Shift Supervisor

E. I. Thompson, Shift Supervisor

E. Polk, Assistant Mechanical Maintenance Supervisor

S. F. Pierce, Radioactive Materials Control Supervisor

W. M. Hodge, Property Protection Superintendent

K. M. Farr, Public Affairs Director

  • Denotes those present at Management Interview on May 4, 1981 .

Numerous other members of the plant operations/maintenance, technical

and chemistry/health physics staff were also contacted briefly.

Operational Safety Verification

The inspector observed control room operations, reviewed applicable

logs and conducted discussions with control room operators during the

month of April, 1981.

The inspector verified the operability of

selected emergency systems, reviewed tagout records and verified proper

return to service of affected components.

Tours of auxiliary and

turbine buildings were conducted to observe plant equipment conditions,

including potential fire hazards, fire extinguisher verified operable

and in place, fluid leaks, and excessive vibrations and to verify

that maintenance requests had been initiated for equipment in need of

maintenance.

The inspector by observation and direct interview

verified that the physical security plan was being implemented in

accordance with the station security plan.

Tours of the security

fence were conducted.

During a tour of the auxiliary building (spent fuel pool area) on

May 29, 1981, at approximately 1930 hours0.0223 days <br />0.536 hours <br />0.00319 weeks <br />7.34365e-4 months <br />, the inspector found a

bottle of methyl alcohol on the new fuel elevator.

Section 7,

paragraph 5.4.1.a and paragraph 5.4.2.b of the Palisades Fire

Implementing Procedure classifies methyl alcohol as a Class I

liquid and requires metal containers or safety cans for storage

and handling of all class I liquids. This item was discussed with

-

2 -

-

the shift supervisor who took appropriate action to assure compliance

with the Fire Protection Implementing Procedures.

The methyl alcohol

was apparently staged for work being performed on the new fuel elevator.

The inspector verified, during subsequent tours of the spent fuel pool

area, adherence to the Fire Protection Implementing Procedures when a

class I liquid was on the job site.

Establishment, maintenance, and

implementation of the Fire Protection Implementing Procedure is a

requirement of Technical Specification 6.8.1.d.

Failure to implement

the Fire Protection Implementing Procedure as described above is

deemed to constitute an item of noncompliance with Technical Specifi-

cation 6. 8 .1. d.

The inspector observed plant housekeeping/cleanliness conditions

and verified implementation of radiation protection controls.

During

the month of April 1981, the inspector walked down the accessible

portions of the service water system and the electrical portion of

M0-29.

The inspector also witnessed portions of the radioactive

waste system controls associated with radwaste shipment and barreling.

Two radwaste trucks awaiting shipment were independently surveyed on

April 8 and April 28.

These reviews and observations were conducted

to verify that facility operations were in conformance with the require-

ments established under Technical Specifications, 10 CFR, and

administrative procedures.

The plant operated at essentially full power throughout the month

of April 1981, under the provisions of an NRC Confirmatory Order

dated March 10, 1981.

The plant has incorporated all items of para-

graph V.A.2 of the NRC Confirmatory Order dated March 10, 1981 into

chapter 18.1, "Procedure Development" of the Palisades Administrative

Procedures.

One item of noncompliance was identified.

3.

Monthly Maintenance Observation

Station maintenance activities of safety related systems and components

listed below were*observed/reviewed to ascertain that they were conducted

in accordance with approved procedures, regulatory guides and industry

codes or standards and in conformance with technical specifications.

The following Maintenance Order packages were reviewed:

a.

81-EPS-026

b.

81-EPS-022

c.

81-CVC-016

d.

81-WAS-006

e .

81-VAS-025

Rebuild emergency diesel air-start motor

Quarterly emergency diesel air-start system

preventive maintenance

Recharging "B" charging pump discharge accumulator

Replace inlet gasket on RV-1160

Replace solenoid coil on CV-1810

-'3 -

l

f.

81-VAS-006

g.

81-SWS-006

h.

81-SWS-002

i.

81-RPS-001

j.

80-CVC-189

Reconnect damper/stem and recalibrate CV-1804

Repair service water pressure sensing line on

EDG 1-2

Repack "A" service water pump

Repair/readjustment of "C" TM/LP trip channel

Replace studs and gasket on letdown heat exchanger

The following items were considered during this review:

the limiting

conditions for operation were met while components or systems were

removed from service; approvals were obtained prior to initiating the

work; activities were accomplished using approved procedures and were

inspected as applicable; functional testing and/or calibrations were

performed prior to returning components or systems to service; quality

control records were maintained; activities were accomplished by

qualified personnel; parts and materials used were properly certified;

radiological controls were implemented; and, fire prevention controls

were implemented.

Minor administrative and recordkeeping incongruities were noted in the

review, including two packages without prior Quality Control group

review, one package for which a referenced Equipment Outage Request

(EOR) was not attached, and one package for which the work performed

may have been beyond the scope of the Maintenance Order.

Further,

as identified in a previous inspectio~, one activity was apparently

performed without Shift Supervisor notification and authorization.

Again, this activity did not render components inoperable or otherwise

change their status.

The above items were discussed at the management

interview, and Shift Supervisor notification criteria for maintenance

activities not affecting equipment remains an open item.

Work requests were reviewed to determine status of outstanding jobs

and to assure that priority is assigned to safety related equipment

maintenance which may affect system performance.

The following maintenance activities were observed:

a.

Emergency Diesel Generator 1-2 oil leak repair

b.

Spent Fuel Pool rack removal and decontamination

c.

Preventive maintenance on the fuel ha~dling crane

d.

Pipe lagging on the critical service water header

e.

Verified proper use of a fire watch during welding of a hand

rail in the turbine building

Following completion of maintenance on the above systems, the inspector

verified that these systems had been returned to service properly.

1../

IE Inspection Report No. 50-255/81-05

- 4 -

No items of noncompliance or deviations were identified.

4.

Monthly Surveillance Observation

The inspector observed technical specifications required surveillance

testing on the systems/components identified below, and verified

that testing was performed in accordance with adequate procedures,

that test instrumentation was calibrated, that limiting conditions for

operation were met, that removal and restoration of the affected

components were accomplished, that test results conformed with

technical specifications and procedure requirements and were reviewed

by personnel other than the individual directing the test, and that

any deficiencies identified during the testing were properly reviewed

and resolved by appropriate management personnel.

The inspector also witnessed portions of the following test activities:

a.

M0-7B

b.

M0-24

c.

MC-11

d.

Q0-05

Fire Water Pumps (P-lOB only)

Auxiliary Feedwater System:

Inservice Test Procedure

Safeguards Boron Sample (S.I. bottles only)

Valve Test Procedure (Includes Containment Isolation

Valves)

Completed data for several tests performed in March 1981, and April

1981 were reviewed.

The results of this review are listed below.

March, 1981

a.

MC-11

b.

M0-16

April, 1981

a.

M0-23

b.

M0-19

Safeguards Boron Samples

The Shift Supervisor did not sign step 5.2.14 of

Temporary Change 81-090 for MC~ll.

Inservice Test Procedure-Service Water Pumps

The pump discharge pressure for P-7A is miscalculated.

(Math error)

The pressure test evaluation acceptable

range was filled out incorrectly.

Both items are

contained in attachment 1 to M0-16.

Neither item

affected operability of the pump.

Inservice Test Procedure - Low Pressure Safety

Injection Pumps

.step 3.6.1 and step 7.3 of M0-23 requires attachment

of a calibration data sheet for the point 504 data

logger, but the calibration data sheet was not attached

to M0-23.

Inservice Test Procedure - Containment Spray Pumps

Step 3.6.1 and step 7.4 of M0-19 requires attachment

of a calibration data sheet for FI-0404A if the point

504 data logger is not in service.

The data.logger

was not in service at the time of the test, but a cali-

bration data sheet for FI-0404A was not attached to M0-19.

-

5 -

c.

M0-7A

d.

MC-11

Emergency Diesel

  • step 6.5 of M0-7A implies that a maintenance order

should be initiated when the difference between

diesel generator loaded cylinder exhaust temperature

exceeds l00°F, but this was not performed when the

loaded cylinder exhaust temperature for diesel

generator 1-1 exceeded l00°F.

Safeguards Boron Samples

Step 5.2.14 of Temporary Change 81-090 for MC-11

requires a signature showing that the Shift Supervisor

and Chemistry Supervisor directly supervised performance

of this section.

These signatures were not made, but

signoffs were made implying a supervisor directly

supervised performance of three sections of MC-11

that were not performed.

The completed procedures listed above had gone through several levels

of review and the items listed above had not been identified by the

licensee/a' 91screpancies.

The discrepancies listed above and in other

reports?-l!+/-. are evidence that the plant lacks an effective review process

in this area.

The plant should examine their review mechanisms and pro-

vide additional guidance in this area.

These items were discussed

with licensee personnel at the monthly exit interview.

No items of noncompliance or deviations were identified.

5.

Licensee Event Reports Followup

Through direct observations, discussions with licensee personnel, and

review of records, Ehe following event reports were reviewed to deter-

mine that reportability requirements were fulfilled, innnediate corrective

action was accomplished, and corrective action to prevent recurrence

had been accomplished in accordance with technical specifications.

a.

(Closed)

LER 79-40 "Crack in Feedwater to Steam Generator Nozzle"

See Inspection Report 50-255/80-15.

b.

(Closed)

LER 80-043 "Excessive Leakage Through Component

Cooling Water (CCW) Supply Penetration". During valve inservice

testing the measured leakage through containment penetration #14

(CCW supply to containment) exceeded allowable limits.

The

containment penetration consists of a checkvalve and a butterfly

valve.

Acceptable leakage was obtained by replacing the check-

valve and repairing the seat to the butterfly valve.

c.

(Closed)

LER 80-044 "Stud Corrosion in the letdown Heat Exchanger."

While investigating a leak at the return head flange of the

letdown heat exchanger the licensee noted that the closure head

fasteners were corroded.

Stud corrosion was caused by contact

with borated water which leaked from the flange.

The leak was

2/ IE Inspection Report No. 50-255/80-20

3/ IE Inspection Report No. 50-255/80-24

!!_/ IE Inspection Report No. 50-255/81-05

-

6 -

repaired by disassembly of the head, replacement of the damaged

studs and gasket, and reassembly of the head.

The leakage

apparently resulted from improper assembly of the closure head.

d.

(Closed)

LER 80-45

"Low Condensate Makeup Inventory"

The

licensee reported that for approximately twenty minutes the

auxiliary feedwater makeup inventory fell below the 100,000

gallons of water required by the Palisades Technical Specifica-

tion.

The decreased inventory was caused by non-availability of

the makeup

demineralizers, and loss of approximately 300,000

gallons of water due to high sodium content, and makeup demands

required during plant startup.

e.

(Closed)

LER 81-005

"Inoperable Diesel Generator due to

contractor worlanan actions." Diesel generator 1-2 was made

inoperable to repair a damaged copper tubing to the diesel-

genera tor service water low pressure alarm.

The copper tubing

was accidently damaged when a contractor worlanan accidently

bumped the tubing.

The copper tubing was repaired and the diesel

generator returned to service within the time limits of the

Technical Specifications.

See (f) for corrective action.

f.

(Closed)

LER 81-007

"Inoperable Auxiliary Feedwater Pump due

to contractor worlanan actions." An auxiliary operator discovered

that the overspeed trip device for the turbine-driven auxiliary

feedwater pump was in the tripped condition.

The operator re-

stored the pump to operability by resetting the overspeed trip.

The condition is believed to have existed for one hour.

The

plant believes the overspeed trip device was accidently bumped

by a contractor worker who was in the auxiliary feedwater pump

room an hour before the discovery.

The plant has revised indoc-

trination training for contractor workers to stress necessity

to exercise caution when working in vital areas and added a

weekly contractor meeting to schedule/control the activities of

contractor workers.

6.

IE Bulletin Followup

For the IE Bulletin listed below, the inspector verified that the

written response was within the time period stated in the bulletin,

that the written response included the information required to be re-

ported, that the written response included adequate corrective action

connnitments based on information presentation in the bulletin and the

licensee's response, that licensee management forwarded copies of the

written response to the appropriate onsite management representatives,

that information discussed in the licensee's written response was

accurate, and that corrective action taken by the licensee was as

described in the written response.

a.

IE Bulletin 80-10, "Contamination of Nonradioactive System and

Resulting Potential for Unmonitored, Uncontrolled Release of

Radioactivity to Environment."

The inspector verified the only

item remaining open following a previous inspection?-/ (addition

2__/

IE Inspection Report No. 50-255/81-05

-

7 -

of service air system to routine sampling program)

had been

implemented.

The system remains free of contamination.

This

item is closed.

No items of noncompliance or deviations were identified.

7.

Spent Fuel Pool Mqdifications

During this inspection, activities relating to completion of a

facility modification involving replacement of the original spent

fuel storage racks with new high-density storage racks were observed/

reviewed.

Portions of this activity were previously examined.~/ before

work was suspended to accomplish the most recent refueling and other

activities.

This inspection included examination of a new rack for proper venting

(Reference Part 21, Report 78-0Sl); observation of new rack cleaning,

handling and installation; and observation of rack alignment and

seismic securing using a diver.

Final documentation review will be completed during a future inspection.

No items of noncompliance or deviations were identified.

8.

Independent Review

On May 1, 1981, the inspector received information that contaminated

materials had been stored in the onsite overflow parking lot - an

unrestricted area.

Independent surveys of the area were immediately

performed using an NRC -

owned radiation detection instrument, and

two SS-gallon drums were identified which showed above normal radiation

levels.

The licensee's health physics staff was contacted and

accompanied to the area for verification using their instrumentation.

The above-background readings on two barrels were confirmed, so the

barrels were immediately returned to the licensee's restricted area.

Subsequently, comprehensive surveys of the area and stored materials

(by the licensee) identified two additional items, both SS-gallon

barrels, which also showed above-background radiation levels and which

wete, therefore, immediately returned to the licensee's restricted

area.

Radiation levels from these barrels were low in each case; well below

the levels established as regulatory limits for radiation levels in

unrestricted areas.

Contamination on three of the barrels could be

characterized as trace amounts.

One barrel, however, contained

quantifiable activity (approximately 4.3 microcuries, primarily Cs-137)

contained in about three liters of water in the barrel.

The overflow parking lot is a fenced area which is normally unattended

and which was found unattended on May 1, 1981, with the area gate open.

!!._/

IE Inspection Report No. S0-2SS/79-0S

-

8 -

i *

I

-

Title 10, Code of Federal Regulations, Part 20.207 prohibits storage

of licensed materials in unrestricted areas unless attended or secured

from unauthorized removal.

Storage of licensed material in the form

of contaminated containers as described above is an item of noncompliance

with 10 CFR 20.207.

9.

Management Interview

A management interview (attended as indicated in Paragraph 1) was

conducted after the conclusion of the inspection, on May 4, 1981.

The

following items were discussed with licensee response as indicated.

a.

b.

c.

d.

e.

f.

The scope and findings of the inspection were summarized.

The two instances of apparent noncompliance were specifically

identified and discussed.

The licensee briefly described exist-

ing systems for processing and control of company-owned materials

such as those stored in the onsite overflow parking lot. (Para-

graphs 2 and 8)

Preliiuinary licensee evaluations concerning how and when con-

taminated materials may have been placed in storage in the over-

flow parking lot were discussed.

Incongruities identified in maintenance package review were

identified.

(Paragraph 3)

Examples of errors and omissions identified in completed sur-

veillance package review were stated, with the inspectors ex-,

pressing concern for the apparent weakness of the licensee's

earlier reviews.

(Paragraph 4)

IE Bulletins and Licensee Event Reports to be closed on the

basis of reviews conducted during this inspection were identi-

fied.

(Paragraphs 5 and 6)

-

9 -