ML18046A457

From kanterella
Jump to navigation Jump to search
Forwards Updated Response to NUREG-0737 Items Re Shift Technical advisor,post-accident Sampling Capability,Noble Gas Effluent Monitor,Sampling Analysis of Plant Effluents & Upgrade Emergency Support Facilities
ML18046A457
Person / Time
Site: Palisades, Big Rock Point  File:Consumers Energy icon.png
Issue date: 02/25/1981
From: Frost S
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
To: Crutchfield D
Office of Nuclear Reactor Regulation
References
RTR-NUREG-0737, RTR-NUREG-737, TASK-1.A.1.1, TASK-2.B.3, TASK-2.F.1, TASK-3.A.1.1, TASK-3.A.2.1, TASK-TM NUDOCS 8103020367
Download: ML18046A457 (8)


Text

.. >

  • consumers

.,~~~ ~~

,:1_

j ,j I(-!

1 *.* -

~ ~t!~f:~

Power -**-~*

~~~{~~

General Offices:

company 212 West Michigan Avenue, Jackson, Michigan 49201 * (517) 788-0550

-*-r.1 *'

T.J 0

r'l

,en ill ..--;£;!.-

February 25, 1981_

Director, Nuclear Reactor Regulation Att Mr Dennis M Crutchfield, Chief Operating* Reactors Branch No 5 US Nuclear Regulatory Commission Washington, DC 20555 DOCKET 50-255 - LICENSE DPR-20 NUREG-0737 - UPDATE -

PALISADES PLANT NRG letter dated October 31, 1980 incorporated into one document all TMI-related items approved for implementation by the Commission. That total package, known as NUREG-0737, provided items to be addressed by licensees to improve safety at power reactors in view of the Three Mile Island incident.

Consumers Power Company's letter dated December 19, 1980 provided our response to the items of NUREG-0737 for the Palisades Plant. Since that submittal, it has become necessary to update our response as follows:

Item I.A.1.1 Shift Technical Advisor (STA)

Add Page 3a (attached) - Our December 19, 1980 response stated that details for our long-range STA program were not complete and would be submitted in the future. Page 3a outlines our long-range plans and fulfills this commitment.

Item II.B.3 Post-Accident Sampling Capability Figure 1, Page 70 of our December 19, 1980 response is no longer correct. The correct figure of the Post-Accident Sampling System is attached (Page 70, Rev 1).

Item II.F.1(1) Noble Gas Effluent Monitor Replace Page 110 of the December 19, 1980 response with attached Page 110, Rev 1. This change reflects a change in the vendor's delivery schedule which we cannot control.

Director, Nuclear Reactor Regulation 2 Palisades Plant February 25, 1981 Item II.F.1(2) Sampling Analysis of Plant Effluents Replace Page 111 with Attached Page 111, Rev 1. This change reflects a change in the vendor's delivery schedule which we cannot control.

Item III.A.1.2 Upgrade Emergency Support Facilities Replace Page 229 with attached Page 229, Rev 1. This change provides a more accurate statement of the Technical Support Center conditions.

All changes to these items are identified by a vertical mark in the right-hand margin.

It is our intent to keep you informed of any changes to our December 19, 1980 submittal; therefore, we will continue to supply any revisions as they become necessary.

&'~~

f- Steven R Frost Palisades Licensing Engineer CC Director, Region III, USNRC NRC Resident Inspector-Palisades Attachment (6 Pages) l

3a PALISADES PLANT Summary of the Shift Technical Advisor Long-Term Training Program - NUREG-0737, Item I.A.1.1 The long-term STA training program for Palisades will consist of five segments covering the Operational Training Phase described in INPO's Recommendation for Plant Shift Technical Advisor training, Sections 6.2 through 6.8:

>':Nuclear Technology 240 Hours

  • Systems and Procedures 160 Hours
  • Transient and Accident Analysis 80 Hours

>':Management and Supervisory Skills 40 Hours

  • Simulator Training 80 Hours*

Personnel entering this program will already have completed as prerequisites a study of fundamental subjects such as Mathematics, Reactor Theory, Reactor Chemistry, Nuclear Materials, Thermal Science, Electrical Science, Nuclear Instrumentation and Control, and Nuclear Radiation Protection and Health Physics. (If an individual is missing one or more of these subjects, he may be allowed to complete a study of it in coincidence with parts of this program.) These prerequisite subjects coincide with the Section 6.1.2 INPO recommendations for Shift Technical Advisor training.

Due to the varied backgrounds of the current group of STAs, individuals who have completed comparable studies in a given subject may be excused from classes on that subject.

While personnel selection for the long-term STA program for the Palisades Plant is incomplete at this time, program development is proceeding. In the interim, until long-term STA personnel are selected, the STA function is provided by experienced STA and senior plant staff who have been provided additional training in the STA duties/responsibilities. Senior plant staff fulfilling this function include Senior Engineers, and the Technical Engineer.

nu0281-039la-43 2/25/81

10 7 4 e I . 70 Page OPERATING DATA

.-1iii~-.

r;.:..\9."") FLOW PRESS ct> fCCllUNI CPSIGl TEMP (OfJ BY REW.t.RK.S CONTAINMENT HYDROGEN MONITORING SYSTEM

~

S XVC-7 f' TYPE 31655 1100 2085 105 1100 160 105

~~SV0-30 0 0

°o o o c/:::'c/0 3 c/::::.-o0c/~*c:/2>cF:::*o0o°o0c/~*~o0c/:::*~~:~~c:/~o°o 25 0 JOO CINA 40 2085 105 F 1060 5 105 40 2085 105 REH.R~S

-;:.-1iiis'-.

.~a..-) 2 1 2485 650 500 350 CONTAINMENT HYDROGEN ~: 55 300 MONITORING SYSTEM J XVC-S ISO 175 2485 175 0330-1-775-41-02-00 r- "'

-14 175 SV0-29 cl NA LEAD COLLlllATOR REFERENCE!

CONSUMERS POll£R COW?.lNY PALISADES PLANT

1. PIPING ' INSTRUMENT DIAGRAM PROCESS SAMPLING STSTEM-M2!9
2. PiPING ' INSTRUMENT OIAGRAM RAOIO-IASTE TREATMENT SYSTEM FLUSH OIRTY WASTE iL GASEOUS IASTE-11-211 AIR J. PIPING iL INSTRUMENT OlAGRAM GAS ANALYZING SYSTEM-M-224 IOPTIONALl REACTOR COOLAHT SAMPLE

- - - - - - - - - l FILTER'"-------- ~ NOTE lil-219-F6 SVO-IBA "A" ~ I. All SDLENOIO VALVES ARE OESIGNEO TO FAIL CLOSED XV0-12 SV0-20A

' z. AOOITIONAL INFORMATJON CONCERNING COMPONENTS IN THE SYSTEM CAN BE OBTAINED FROWo A. SYSTEM DESIGN DESCRIPTION 0330-1-715-51-01 B. EOUIPUENT LIST C. INSTRUMENT LIST SV0-25 SV0-24 CATION O. VALVE LIST LOW PRESSURE RESIN E. PIPING DESIGN ANO CLASS STANDARD INJECTION PUMPS SV0-188 SV0-208 EXCHANGER F. PROJECT WANAGEWEN~ MANUAL 0I SCHARGE HEADER r LEAD

3. DIAGRAM SYMBOLS AND INSTRUMENT LEGENDS D SAMPLE ' COLLIMATOR ARE SHOWN ON ORAl!NG. 0330-1-009-41-02*001 D

~--------l FILTER 1 - - - - - - - -

liHl9-GJ "8" 4. ALL INSTRUMENTS ANO EOUIPWENT TAG t-.UWBERS

I I I Ahl) PIPE LINE t.UMBEMS ARE PREF"iXE:J 1;:rn XVO-IJ OJJO*l-775 UNLESS OTHERWISE NOTED LJNTRi~siJc

' \

I DETECTOR I

I

I

~----IOPTIONALI

_L_-_-_-_-_-_-_-_-_-_-_-_-_-_-_-:::::::.-_-_-_-::::::::::.::::::::::::::::::::::::::~J ~-s

~

~

\:J]::/

c c TO CONTAINMENT i'rYPE 31655 SUMP DRAINS RACK AND ENCLOSURE MOUNTED EQUIPMENT AND INSTRUMENTS XV0-11 sec xvo-10 Y.ATERSAMPLE

~----+--- ~!)!.ATED HOOD I

I I

IJA~ 9 1231 .

WATER L ___I SEPTUM

    • LADHIAI B

IOOOCC SURGE CYLINDER CAIORHINGNO. REY.

0330- I - 775-4 I 00 I A

!IHWN n CKE!;XE!I n ENGIHEH SUPUIVISING ENGllUH 11~~ * ///~

~----

RKA 2,21;80 *;)\...... I , /

PAfPAll(DUN!l(ATllEIISPDNSlllESUPUflSIONDF H. C. GARG P.E.

MIClllGAllPROHSSID*llllEGISllAllOllND.:::::lliB£::

_ _ PROHSStDHlR(llJSTRAllDNNO. _ __

TO ATllllDFFICU!lf RAOWASTE M-211-H6 COMMONWEAL TH ASSOCIATES INC.

SYSTEM ZDI I. WASlllNGIDN.IYE. JAClSDN, MltH.

OWNER PALISADES PO~R PLANT A CONSUllERS POWER COMPANY A JACltSON, lllCHIGAN

+ 10 2/25/81

- . ~

110 DEVIATIONS FROM AND BASIS FOR Recommendations None Schedule Vendor lead time has been increased from ten to twelve months. The purchase order for this system has been delayed also, however, it should be issued within the next two weeks. Every effort will be made to expedite the delivery and installation date to meet the January 1, 1982 requirement. If delivery cannot be expedited, March 31, 1982 would be more realistic for full operation.

REFERENCES

1. NUREG-0578, Recommendation 2.1.8.b
2. American National Standard ANSI N13.1-1969, February 1969
3. Letter From D G Eisenhut, NRC, to All Operating Nuclear Power Plants, Dated September 13, 1979
4. Letter From HR Denton, NRC, to All Operating Nuclear Power Plants, Dated October 30, 1979
5. Letter From D G Eisenhut, NRC, to All Licenses of Operating Plants and Applicants for Operating Licenses and Holders of Construction Permits, Dated September 5, 1980.
6. Letter From DP Hoffman, CP Co, to D L Ziemann, NRC, Dated October 17, 1979
7. Letter From DP Hoffman, CP Co, to D L Ziemann, NRC, Dated December 27, 1979
8. Letter From D P Hoffman, CP Co, to D L Ziemann, NRC, Dated March 4, 1980
9. Letter From D L Ziemann, NRC, to DP Hoffman, CP Co, Dated April 6, 1980 nu1280-0029a-43 Rev 1 2/25/81

111 II.F.1(2) SAMPLING AND ANALYSIS OF PLANT EFFLUENTS NRC POSITION Because iodine gaseous effluent monitors for the accident condition are not considered to be practical at this time, capability for effluent monitoring of radioiodines for the accident condition shall be provided with sampling conducted by adsorption on charcoal or other media, followed by on-site laboratory analysis.

LICENSEE ACTION Continuous sampling of plant gaseous effluent for post-accident releases of radioactive iodines and particulates will be installed at the Palisades Plant by January 1, 1982. There will be on-site laboratory capabilities to analyze or measure these samples (C-1).

The Sampling System will be designed to such that plant personnel can remove samples, replace sampling media and transport the samples to the on-site analysis facility with radiation exposures not exceeding 5 Rem whole body or 75 Rem to extremities (GDC-19) during the duration of the accident (C-2).

The design of the system for sampling of particulates and iodines will provide for nozzle entry velocities which are approximately the same velocities with expected induct or instack air velocities within +/- 20%. We will comply with this clarification unless such equipment cannot be procured (C-3).

Provisions will be made to ensure that the absorber is not degraded while providing a sample of an effluent stream that may contain air with entrained water (C-4).

This system is an integral part of the noble gas effluent monitor and will be supplied by the same vendor.

Design details will be available for review by January 1, 1981 as requested by your October 31, 1980 letter (D).

Technical Specifications will be proposed as required.

DEVIATIONS FROM AND BASIS FOR Recommendations None Schedule Vendor lead time has been increased from ten to twelve months. The purchase order for this system has been delayed also, however, it should be issued within the next two weeks. Every effort will be made to expedite the delivery and installation date to meet the January 1, 1982 requirement. If delivery nu1280-0029a-43111 Rev 1 2/25/81

112 cannot be expedited, March 31, 1982 would be more realistic for full operation.

REFERENCES

1. NUREG-0578, Recommendation 2.1.8.b
2. American National Standard ANSI Nl3.1-1969, February 1969
3. Letter From D G Eisenhut, NRG, to All Operating Nuclear Power Plants, Dated September 13, 1979
4. Letter From H R Denton, NRG, to All Operating Nuclear Power Plants, Dated October 30, 1979
5. Letter From D G Eisenhut, NRG, to All Licenses of Operating Plants and Applicants for Operating Licenses and Holders of Construction Permits, Dated September 5, 1980
6. Letter From DP Hoffman, GP Co, to D L Ziemann, NRG, Dated October 17, 1979
7. Letter From DP Hoffman, GP Co, to D L Ziemann, NRG, Dated December 27, 1979
8. Letter From D P Hoffman, GP Co, to D L Ziemann, NRG, Dated March 4, 1980
9. Letter From D L Ziemann, NRG, to D P Hoffman, GP Co, Dated April 6, 1980 nu1280-0029a-43112 Rev 1 2/25/81

229 III.A.1.2 UPGRADE EMERGENCY SUPPORT FACILITIES NRG POSITION Additional clarification will be provided in the near future.

LICENSEE ACTION The upgrading of the Emergency Support Facilities will be addressed in NUREG-0696, "Functional Criteria for Emergency Response Facilities," when it is published in its final form. All decisions on future upgrading actions to our facilities await final issuance of NUREG-0696.

All implementation dates and licensee submittal dates are yet to be determined per Enclosure 1 of your October 31, 1980 letter (NUREG-0737).

Safety Parameter Display System The response to this item was addressed in NUREG-0737,Section I.D.2.

Technical Support Center The on-site Technical Support Center (TSC) is located in the present Shift Supervisor's office and control room viewing areas just outside of the control room. This total area is 1,000 ft 2 including the Shift Supervisor's office.

One half of the center is habitable to the same degree (shielding and air supply) as the control room for postulated accidents. The other half will not have radiation levels above those required for continuous occupancy and it has a different air supply. Designs are presently being formulated to make the entire Technical Support Center habitable. Key TSC personnel will be provided with a means for gaining entry to the control room.

Dedicated communications between the TSC, the control room, Emergency Opera-tions Center, the NRG and the EOF are provided.

Radiation monitoring is provided for both direct radiation and airborne radiation contaminants in the TSC and provides warning if the radiation levels in the support center are reaching potentially dangerous levels. Action levels are designated to define when protective measures should be taken.

To ensure access to technical data, Palisades TSC is provided with a card reader and.aperture cards, system descriptions, containment photographs and plant drawings which are necessary for assessment of an accident in the TSC.

These drawings are controlled and kept up to date by the Plant Document Control Section. The plans and procedures for engineering/management support and staffing of the TSC are part of the Palisades Emergency Plan.

Emergency Operations Facility The Emergency Operations Facility has been established at Consumers Power Company's South Haven Conference Center.

nu1280-0031a-43 Rev 1 2/25/81