OPERATING DATA REPORT OPERA TING ST A TUS I. Unit Name:
Palisades
- 2. Reporting Period:
800701 - 800731
- 3. Licensed Thermal Power (MWt):
2530 811. 7
- 4. Nameplate Rating (Gross MWe):
- 5. Design Electrical Rating (Net MWe):
805
- 6. Maximum Dependable Capacity (Gross MWe): __
- _6_7_5 ___ _
- 7. Maximum Dependable Capacity (Net MW~):
--*--=-6-=3'-"'5 ___ _
Notes DOCKET NO.
DATE COMPLETED BY TELEPHONE 50-255 8/11/80 PJBodtke.
616-764-8913
- 8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report, Give Reasons:
Q.. Power Level To Which Restricted, If Any (Net MWe):
- 10. Reasons For Restrictions, If Any:
- 11. Hours In Reporting Period
- 12. Number Of Hours Reactor Was CritiCal
- 13. Reactor Reserve Shutdown Hours.
- 14. Hours Generator On-Line --=
, ;..,=
- 15. Unit Reserve Shutdow~ Hours This Month
. 744 557.4 539.5
- 16. Gross Thermal Energy Generated (MWH) 1, 18 2, 912
- 17. Gross Electrical Energy Generated (MWH) 361, 130
- 18. Net Electrical Energy Generated (MWH) 339, 436
- 19. Unit Service Factor 7 2. 5
- 20. Unit Av.ailability Factor
- 72. 5
- 21. Unit Capacity Factor (Using MDC Net)
- 71. 8
- 22. Unit Capacity Factor (Using DER Net)
- 56. 7
- 23. Unit Forced Outage Rate 2 7. 5 Yr.-to-Date 5111 1458 1362.1 2,944.296 910' 600 856,063
- 26. 7.
26.7 26.4 20.8 13.1
- 24. Shutdowns Scheduled Over Next 6 Months (Type. Date. and Duration of Each):
- 25. If Shut Down At End Of Report Period, Estimated Date of Startup:
- 26. Units In Test Status (Prior to Commercial Operation):
INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION
- Based on Condenser Backpressure Forecast Cumulative
'75,.542.
41,022.8 38,788.4 74,455,776 22,942,830 21,526,838
- 51. 3
- 51. 3 44.9 35.4 35.7 Achieved (Q/77)
- i.
~ ;
l -
e A VERA GE DAILY. UNIT POWER LEVEL DOCKET NO.
50-255 UNIT Palisades DATE 8/11/80 COMPLETED BY PJBodtke TELEPHONE 616-764-8913 MONTH July 1980 DAY AVERAGE DAILY POWER LEVEL DAY A VERA GE DAILY POWER LEVEL (MWe-Net)
(MWe-Net) 707 17 612 2
511 18 591 3
19 616 4
20 592 5
21 589 6
22 609 7
23 646 8
24 640 9
25 626 IO 26 635 11 299 27 649.
12 649 28 673 13 677 29 663 14 639 30 673*
15 608 31 633 16 605 INSTRUCTIONS On this format, list the average daily unit power level in MWe-Net for each day in the reporting month. Compute to the nearest whole megawatt.
(9/77)
No:
Date 16 800702 F: Forced S: Scheduled (lJ/77)
UNIT SHUTDOWNS AND POWER REDUCTIONS REPORT MONTH July 1980
~.
3 0
- eo.....
'J
"'O *='"'
- 11)
- =::;
0
- 0.
~ -
- 11)
~
..c :; ~
I-.
~ :C
'lJ -.....
o-
~
~~.~
6 F
204.5 A
2 Reason:
A-Equipment Failure (Explain)
B-Maintenance oi Test C'-Refueling D-Regulatory RestriCtion
- Licensee Event
- Report*#
NA E-Operator Training & License Examination F-Administrative G-Operational Error (Explain)
H-Othcr (Explain) 3 r::
Ev IUV"I r::
- 11)
- 11)
- 11)
- . ~ -g 0 "O
.o. 0 Eu r/l u 0 u Method:
I-Manual 2-Manual Scram.
3-Automatic Scram.
- 4-0ther (Explain)
Oil leak system.
DOCKET NO. 50-255 UNIT NAME DATE COMPLETED BY TELEPHONE Palisades 8/11/80 PJBodtke 616-764-8913 on 4
5 Cause & Corrective Action to Prevent Recurrence generator seal oil Exhibit G - fostructions for Preparation of Data Entry Sheets for Licensee Event Report (LER) File (NUREG-0161)
Exhibit I - Same Source
SUMMARY
OF OPERATING EXPERIENCE FOR THE MONTH OF JULY 1980 Plant was manually tripped on 7/2 due to a filter housing rupture on the turbine seal oil system.
Subsequently, plant went to cold shutdown to repair CRDM seal housings.
Reactor went critical on 7/9 and tripped shortly after criticality on high start-up rate.
Reactor again taken critical on 7/10 and the plant operated the rest of the month at approximately 87% power.