OPERA TING DAT A REPORT OPERATING STATUS
- 1. Unit Name:
PALISADES 8ll. 7
. 2. Reporting Period:
- 3. Licensed Thermal Power (MWt):
- 4. Nameplate Rating (Gross MWe ):
- 5. Design Electrical Rating (Net MWe):
- __
8_0_5_* ------
- 6. Maximum Dependable Capacity (Gross MWe): __
- ._6.;..7_5_* ___ _
- 7. Maximum Dependable Capacity (Net MWe):
_. _*_6_3_5 ___ _
800301 -
800331 2530 Notes DOCKET NO. 50-255 DATE 4/ 1/80 COMPLETED BY PJBodtke.
TELEPHONE 616-7 64-8 913
- 8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report, Give Reasons:
- 9. Power Level To Which.Restricted, If Any (Net MWe):
- 10. ~easons For Restrictions, If Any:
This Month
- 11. Hours In Reporting Period i2. Number Of Hours Reactor Was Critkal 744 0
- 13. Reactor Reserve Shutdown Hours
- 14. Hours Generator On-Line 0
- 15. Unit Reserve Shutdown Hours
- 16. Gross Thermal Energy Generated (MWH)
- 17. Gross Electrical Energy Generated (MWH) 0 0
- 18. Net Electrical Energy Generated (MWH) 0
- 19. Unit Service Factor 0
- 20. Unit Availability Factor 0
- 21. Unit Capacity Factor (Using MDC Net) 0
- 22. Unit Capacity Factor (Using DER Net)
- 23. Unit Forced Outage Rate 0
0 Yr.-to-Date 2184 0
0 O*
0 0
0 0
0 0
0 Cumulative n,615 39,564.8
. 37,426:3 71,511,480 22,032,230 20,610;775 52.0 52.0 44.8 35.4.
36.3
- 24. Shutdowns Scheduled Over Next 6 Months (Type, Date, and Duration of Each):
~*:.
- 25. If Shut Down At End Of Report Period, Estimated Date of Startup:
- 26. Units In Test Status (Prior to Commercial Operation):
INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION
- Based on Condenser Backpressure April 28*, 1980 Forecast Achieved
AVERAGE DAILY UNIT POWER LEVEL DOCKET NO.
50-255 UNIT Palisades DATE 4/1/80 COMPLETED BY PJBodtke TELEPHONE 616-764-8913 MONTH March 1980 DAY AVERAGE DAILY POWER LEVEL DAY A VERA GE DAILY POWER LEVEL (MWe-Net)
(MWe-Net) 0 17 o*
2 0
18 0
3 0
19 0
4 0
20 0
5 0
21 0
6 0
22 0
7 0
23 0
8 0
24 0
9 0
25 0
10 0
26 0
11 0
27
- 0.
12 0
28 0
13 0
29 0
14 0
30 0
15 0
31 0
16 0
INSTRUCTIONS On this format, list the average daily unit power level in MWe-Net for each day in the reporting mLJnth. Compute to the nearest whole megawatt.
(9/77)
Nu:
13 (Contd F: Forced Date 800301 S: Scheduled (9/77) 2 UNIT SHUTDOWNS AND POWER REDUCTIONS REPORT MONTH March 1980
-Q)
- 0.
I-.
s Reason:
744 H
A-Equipment Failure (Explain)
B-Maintenance or Test
(-Refueling D-Regulatory Rest riCtion Licensee Event Report#
E-Operator Training & License Examination F-Administrative G-Operational Errur (Explain)
H-Other (Explain) 3 Method:
I-Manual c
Q)Vl c
Q) 0 "O
.0. =>
Eu 0 u 2-Manual Scram.
3-Automatic Scram.
4-0ther (Explain)
DOCKET NO. _5_0_-_2_55 ___ _
UNIT NAME Palisades DATE 4/1/80 COMPLETED BY PJBodtke TELEPHONE 616-764-8913 Cause & Corrective Action to Prevent Recurrence TMI Modifications and anchor bolt inspections/repairs according to IE Bulletin 79-02.
- 4 5
Exhibit G - Inst ructions for Preparation of Data Entry Sheets for Licensee Event Report (LER) File (NUREG-0161)
Exhibit I - Same Source
GENERAL
SUMMARY
OF OPERATING EXPERIENCE FOR MARCH 1980 Work continues on the seismic pipe hanger/anchor bolts inspections and repairs, and TMI modifications.