ML18038B592

From kanterella
Jump to navigation Jump to search
Insp Repts 50-259/95-57,50-260/95-57 & 50-296/95-57 on 951002-1117.Violations Noted.Major Areas Inspected:Small Bore Pipe Supports,Instrument Tubing & Supports,Seismic Ii/I Issues & Unit 3 Startup Issues
ML18038B592
Person / Time
Site: Browns Ferry  
Issue date: 12/15/1995
From: Casto C, Lenahan J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML18038B590 List:
References
50-259-95-57, 50-260-95-57, 50-296-95-57, NUDOCS 9512270144
Download: ML18038B592 (26)


See also: IR 05000259/1995057

Text

~P,g REMI

(4

P0

Cy

A

O

v,

++*++

UNITED STATES

NUCLEAR REGULATORY'COMMISSION

REGION II

101 MARIETTASTREET, N.W., SUITE 2900

ATLANTA,GEORGIA 303234199

Report Nos.:

50-259/95-57,

50-260/95-57,

and 50-296/95-57

Licensee:

Tennessee

Valley Authority

6N 38A Lookout Place

1101 Market Street

Chattanooga,

TN

37402-2801

Docket Nos.:

50-259,

50-260

and 50-296

License Nos.:

DPR-33,

DPR-52,

and

DPR-68

Facility Name:

Browns Ferry Nuclear

Power Station Units 1,, 2,

and

3

Inspection

Conducted:

October 2-6, October 17-20,

November 1-3,

November 6,

and

November 13-17,

1995

Inspector:

J. J.

Lenahan

Accompanying Personnel:

C.

Chou

(Hove

Approved by:

C. A.

asto,

Chief

Engineering

Branch

Division of Reactor Safety

/z rs/PW

Date Signed

1-3,

and November 6,

1995)

l5

5'

Date Signed

SUMMARY

Scope:

This routine,

announced

inspection

was conducted

in the areas of small

bore

pipe supports,

instrument tubing and supports,

seismic II/I issues,

Unit 3

.

startup

issues,

and licensee

action

on previous inspection findings.

On

November 6,

1995,

a meeting

was held in

NRC Headquarters,

Rockville, Maryland,

between

NRC and the l.icensee to discuss

design details regarding structural

steel

beams

and coverplates.

Results:

In the areas

inspected,

deviations

were not identified.

A violation was identified for failure to implemen't installation of small

bore

piping, and instrument supports,

and structural

steel

in accordance

with design

drawing requirements,

paragraphs

2.1-, 2.4,

and 4.4.

A weakness

was identified

for failure to perform

a generic review how an issue identified on Unit 3

affected'he

Unit 2 operating plant - paragraph

3.0.,

Enclosure

2

9512270144

951215

PDR

ADOCK 05000259

8

PDR

0

4l

<Qi

REPORT DETAIL

1.0

Persons

Contacted

Licensee

Employees

¹J.

  • R.

J.

¹*D.

  • G

¹*L.

  • G
  • p

"H.

  • S

¹*J.

Corey,

Manager,

Radiological

Control

and Chemistry

Gilbert, Operations

Support Supervisor

Glass,

Supervisory Civil Engineer,

Nuclear Engineering

(NE)

Housley, Site Licensee

Engineer

Little, Operations

Superintendent

Madison, Unit 3 Civil Engineering Supervisor

Preston,

Plant Manager

Salas,

Licensing Manager

Williams, Engineering

and Materials Manager,

NE

Wetzel, Acting Compliance

Manager

Valante, Unit 3 Lead Civil Engineer,

NE

2.0

2.1

Other licensee

employees

contacted

during this inspection

included

craftsmen,

engineers,

technicians,

and administrative personnel.

Other Organizations

P. Koski, Structural

Engineer,

Bechtel

V. Kapoor,

Browns Ferry Civil Design Unit Manager,

Bechtel

NRC Resident

Inspectors

¹L. Wert, Senior Resident

Inspector

R. Husser,

Resident

Inspector

  • J. Hunday,

Resident

Inspector

  • Attended October 20,

1995 exit interview

¹Attended

November

16,

1995 exit interview

Followup on Unit 3 Restart

Issues

Cable Tray and Conduit Support

guestions

were raised

by

NRC and through the employee

concerns

program

regarding

seismic qualification of cable tray and conduit supports.

The

resolution of this issue

can

be subdivided into two categories:

new

conduit

and cable tray supports,

and evaluation of existing cable tray

supports.

New supports

are those installed since

1986.

These

supports

are designed

in accordance

with the licensee's

revised seismic design

criteria and were installed under the licensee's

current quality

assurance

program requirements.

Existing supports

were those installed

prior to 1986, primarily during original plant construction.

Inspection

and acceptance

of existing conduit

and cable tray supports

was performed

under the Generic

Implementing Procedures

(GIP) for Seismic Verification

Enclosure

2

i%I

,<Qi

of Nuclear Plant Equipment.

The GIP was issued

by the Seismic

Qualification Utility Group

(SQUG) in response

to

NRC Unresolved Safety

Issue

A-46 (USI A-46), Seismic

Adequacy of Mechanical

and Electrical

Equipment in Operating Plants.

During the inspections

documented

in NRC Inspection

Report

numbers

50-

259,260,296/95-15

and 95-52, the inspector

examined

new conduit

and

cable tray supports,

and the implementation of the A-46 program for

evaluation of existing supports.

These

programs

were found to be

acceptable

in all areas,

except the drywell, where the licensee's

A-46

walkdown program

was still in progress.

The licensee

recently completed

the A-46 program for conduit

and cable tray supports

in the drywell.

During the current inspection,

the inspector

performed

a walkdown

inspection in the Unit 3 drywell to assess

the effectiveness

of the

licensee's

A-46 cable tray and conduit inspection

program.

The

inspector

examined existing conduit

and cable tray supports

on drywell

elevations

563,

584,

604

and 616.

With the exception of a missing

conduit clamp,

no deficiencies

were identified regarding the cable tray

and conduit supports.

Work was in progress

on dressing

cables

and

installing cable tray covers

on cable trays in the electrical

penetration

area

between elevation

575 and 584.

During the walkdown the

following deficiency was identified by the inspector:

A pipe clamp was

found to be missing

on

a

J inch diameter control air pipe support at

elevation

605, Azimuth 195 degrees,

in the Unit 3 drywell.

Drawing

number 3-478600-2033,

Revision I, specifies installation of a clamp

on

this support,

designated

support

sequence

number Ol, to ensure that

a

three directional restraint of the pipe was provided.

The failure to

install the clamp in accordance

with the design drawing requirements

was

identified to the licensee

as Violation item 296/95-57-01,

Failure to

Install Modifications in Accordance with Design Drawing Requirements.

During the walkdown inspection,

the inspector also identified other

minor items

such

as

a missing clamp

on

a non-safety related

pipe

support,

loose grating

on

a platform under the reactor vessel,

an

apparent

leak on

CRD module 50-23,

and

some

housekeeping

items.

The

loose. grating is discussed

in paragraph

3.0,

below.

The inspector

reviewed the results of the vessel

hydrostatic test

and verified that

the leak from the

CRD module met the hydrostatic test

acceptance

criteria.

The leak from CRD Module 50-23 .was observed

to be

3 drops per

minute .(dpm) during the hydrostatic test,

which is well within the 30

dpm hydrostatic test acceptance

criteria.

The remaining

items were

addressed

by the licensee

on work requests.

The inspector

concluded that the licensee's

A-46 cable tray and conduit

walkdown inspection

and evaluation

program meets

NRC requirements

and is

acceptable

for Unit 3 restart.

Enclosure

2

ik

]pi

2.2

Seismic Class II/I - Water Spray

This issue

involved the effects of water spray from potential failure of

non-safety related piping on safety related

equipment.

The Unit 3

program

implemented to evaluate this issue

was similar to the

one

implemented for Unit 2 prior to Unit 2 restart.

The inspector

reviewed

EgE Report

No. 51001.23-R-001,

Revision 0, dated

September

30,

1993,

Evaluation of Seismic

Induced II/I Spray Hazards at Browns Ferry Unit 3.

This report described

the program which included inplant screening to

identify potential

hazards,

evaluation of outliers,

recommended

plant

modifications,

and configuration control guidelines.

The screening

resulted

in identification of ill potential outliers.

The inspector

reviewed Calculation

number CD-(3999-931257,

Evaluation of Seismic-

Induced II/I Spray Hazards,

which was completed to evaluate

the

outliers.

Ninety-five of the outliers were resolved

by evaluation,

while the remaining

16 required modification.

The modifications were

implemented

under

DCN Number

W 22556A.

The inspector reviewed the

design drawings in the

DCN package

and verified that the

16 outliers

which required modifications were covered

under the

DCN.

The inspector

examined

support

number 3-47B491-3000

which was installed

under the

DCN

to correct

one of the outliners.

The remaining modifications were

inaccessible.

2.3

2.4

The inspector concluded that the licensee's

program complied with their

commentments

and

was acceptable

for Unit 3 restart.

Instrument Tubing

This issue

concerned

seismic re-analysis

of instrument tubing.

The

reanalysis

resulted

in modifications to a large number of instrument

tubing supports.

The licensee

combined the instrument tubing program

with the small

bore piping program.

Inspection of instrument tubing is

covered

under paragraph

2.4,

below.

Small

Bore Piping

This issue

concerned

the seismic qualification of existing class

1 small

bore piping and instrument tubing and resolution of deficiencies

identified in the small

bore piping/instrument tubing.

The small

bore

piping in this program included all Class

I piping systems

less

than two

inches in diameter which had not been rigorously analyzed.

The

licensee's

commitments for resolution of this issue

are specified in a

letter to NRC, dated

February

27,

1991, Subject:

Brown Ferry Nuclear

Plant - Action Plan to Disposition Concerns

Related to Units

1

and

3

Small

Bore Piping.

The program included performance of walkdown inspections

to determine

as-built conditions for small

bore piping/tubing; performance of

rigorous analysis;

preparation of design

changes

to repair identified

Enclosure

2

deficiencies

and install

new supports;

installation of the design

changes;

and performance of a confirmatory analysis

on ten percent of

the small

bore piping/instrument tubing

and associated

supports.

The inspector

reviewed Engineering Attribute Walkdown Instruction

BC-

012,

Walkdown Instructions for Seismic Class

I Small

Bore Piping, Tubing

and Associated

Supports.

This instruction established

the requirements

and criteria for performance of walkdown inspections of small

bore

piping/tubing in order to identify discrepancies

and obtain as-built

data for the rigorous analysis

program.

The inspector

performed

a walkdown inspection

and examined

randomly

selected

supports

on various

systems

to determine if modifications

identified from the rigorous analysis

program were completed in

accordance

with design requirements.

Acceptance criteria utilized by

the inspector

were critical specific in Hodification and Addition

Instruction HAI-4.2A, Piping/Tubing Supports,

Revision

19.

The

following small

bore piping and instrumentation

tubing supports

were

inspected:

RHR System,

support

numbers

3-47B452-3022,

3069 through 3074,

3076,

3078,

3138 through 3142,

3178,

3180,

and 3181.

Core spray system,

support

numbers

3-47B458 -731,

-735, -740,-

741,

-745 through -749,

-757 through -764,

and -768.-

Control air system,

support

numbers

3-47B600 - 1433 through

1436,

-1439 through

1442, support

sequence

numbers

01 through

12 on

drawing numbers

3-47B600 -1432,

and

sequence

numbers

Ol through

05

and

15 -

17 on drawing number 3-47B600 -1438,

Reactor Mater Cleanup

(RWCU) system,

support

number 3-47B456 -258

RCIC system,

support

number 3-47B456

-258

Reactor water recirculation system,

support

numbers

3-47B465 -587,

-589,

2004 through

2006,

2014,

and 2015.

CAD system,

support

numbers

3-47B461

-772 through

774

Containment inerting system,

support

numbers

3-47B650

-25 and -26.

The following discrepancies

were identified during the walkdown

inspection:

Enclosure

2

0

<5

<Qi

An oversized

hole was not repaired in the control air system

support,

designated

as support

sequence

03

on drawing number 3-

478600

-1432, Revision

1.

Note

12 on the drawing required that

the oversized

hole

be repaired.

A quarter inch thick plate with no gap

was observed to have

been

installed

between

the clamp halves

on the anchor/support

for

control air system support

number 3-478600-1435.

Note

2 on

drawing number B-47B600-1435,

Revision 0, requires

the clamp

halves to be installed with a gap greater

than zero inches.

In addition the resident

inspector identified the following discrepancy

while inspecting the reactor vessel

level backfill modification on

instrument

panel

number 3-LPNL-925-674 and -675.

Note

4 on drawing

number 3-47B600-2512-2,

Revision 01, requires that tubing clamps

be

installed to ensure that the maximum unsupported

tubing span with

concentrated

weights (i.e.,

unsupported

valves

and flow elements)

does

not exceed

24 inches.

Detail

B on drawing number 3-47B600-2512-1,

Revision 0, requires that

a structural

support

be provided

on the panel

for instrument tubing and flow elements

in accordance

with Detail J,

drawing 3-47E600-808.

Contrary to this requirement,

tubing clamps were

not installed to secure

the tubing/flow element to the Detail J support.

The unsupported

tubing span

exceeded

24 inches.

These three discrepancies

were identified to the licensee

as additional

examples of violation item 296/95

57 01.

The licensee

issued

problem evaluations

reports to document

and

disposition the above problems.

Prior to the end of the current

inspection,

the inspector verified that the above

items

had

been

repaired prior to restart of Unit 3.

The inspector also identified several

other minor discrepancies

which

were not considered significant enough to identify as additional

violation examples.

These

included minor drafting errors

on two

drawings which were documented

on

PER number

BFPER951556,

and

a minor

error in welding as

RHR support which was documented

on

PER number

BRPER951541.

The drawings

were corrected.

In addition,

RHR instrument

tubing attached

to support

numbers

3-47B452-3140,

3141,

and 3142 were

found to be out of tolerance.

This problem was documented

on

PER number

BFPER951426.

The pipe clamps

were adjusted

on the supports

under work

order C294977.

The inspector reinspected

these

supports

and verified

that the clamps

had

been adjusted

so instrument tubing was installed in

accordance

with design drawing requirements.

The licensee's

Unit 3 small

bore piping/instrument tubing program

had

also

been previously inspected

during inspections

documented

in

NRC

Inspection

Report

numbers

50-259,260,296/92-19

and 95-03.

Based

on the

Enclosure

2

0

~$

3.0

results of the current inspection,

the inspector

concluded that the

licensee's

Unit 3 small

bore piping/instrument tubing program

was

implemented

in accordance

with their commitments to

NRC and is

acceptable

for restart of Unit 3.

Within the areas

inspected,

violations or deviations

were not

identified.

Walkdown of Structural

Steel

Platforms

The inspector walked

down structural

steel

platforms

and examined the

attachment of grating to the platform structural

steel

members.

The

inspector also

examined

methods

used to anchor equipment to the platform

steel

and/or grating.

During the walkdown inspection,

the inspector

determined that the grating

had not been attached

to the platform steel

in accordance

with the details specified

on the design drawings.

As

discussed

in paragraph

2.1 above,

the inspector identified loose grating

on

a platform located

under the Unit 3 reactor vessel.

Since the

drywell closure

was not completed,

and the licensee

had

an open work

order,

number 95-17260-00,

to complete this work, this problem was not

identified as

a violation.

The inspector

re-examined this area prior to

the

end of the inspection

and verified that the grating was properly

attached

to the structural

steel prior to drywell closeout.

The

inspector also identified areas

in the Unit 3 corner

rooms where the

grating

had not been positively attached

to the structural

steel

as

required

by paragraph

4.2.5. 1A of TVA General Specification

G-89,

Structural Steel,

Revision 3,

and

TVA drawing number 0-48E915,

Revision

2, Hiscellaneous

Steel

Floor Grating

and Railing.

Since work in this

area

had not yet been

completed, this problem also

was not identified as

a violation.

The licensee

issued

work request

C294942 to complete this

work.

The inspector re-examined

the areas prior to Unit 3 startup

and

verified that the grating was properly attached

to the structural steel.

During the walkdowns the inspector

noted

some miscellaneous

equipment

and small structural

steel

platforms were anchored to the platform

grating.

The licensee

performed

a design evaluation of the worst case

small steel

platform and checked for stability against overturning

and

sliding.

The inspector

reviewed the design calculations

which showed

the anchorage

of the platform was adequate.

The inspector also

determined that the equipment (electrical

conduits

and junction boxes,

and small

bore piping) was adequately

anchored to meet design loading

conditions.

Approximately two weeks after the inspector

had identified the issues

regarding

loose grating in Unit 3, the resident

inspector identified

a

similar problem in Unit 2.

The licensee

issued

Problem Evaluation

Report

BFPER951655 to document

and disposition this problem.

The

licensee

performed

an operability review and determined that the loose

sections of grating would not affect operability of any safety-related

Enclosure

2

IN

iO

<Qi

equipment.

However, the inspector questioned

why licensee

personnel

had

not identified the problem

on Unit 2 after the problem in Unit 3 had

been previously identified.

Since

a

PER had not been

issued for the

Unit 3 problem,

the extent of condition review for affect on other Units

had not been performed.

The inspector identified the failure to perform

a generic review of the Unit 3 loose grating issue

and its possible

affect on Unit 2 as

a weakness

to licensee

management.

Within the areas

inspected,

violations or deviations

were not

identified.

4.0

4.1

Action on Previous

Inspection

Findings

(Closed) Violation Item 296/95-15-01,

Failure to Complete Modifications

in Accordance with Work Plan

and Drawing Requirements

The licensee

responded

to this violation in a letter dated

June

20,

1995, Subject:

NRC Inspection

Report 50-259,260,296/95-15

- Reply to

Notice of Violation.

The licensee attributed the cause of the two

examples

in the violation to personnel

error during installation of the

modifications.

Example

1 involved failure to upgrade

a weld on

a beam

as required

by the design drawings.

Problem Evaluation Report

(PER)

number

BFPER 950293

was issued to documented

and disposition this

problem.

Example

2 involved failure of quality control personnel

to

inspect

a conduit support.

PER number

BFPER 950273

was issued to

document

and disposition this problem.

The licensee

issued

a work order

and upgraded

the welds

on the

beam in

example

1 to the size specified

on the design drawings.

The inspector

examined

the modified welds

and verified that they complied with the

design requirements.

Additional corrective action included counseling

of civil/structural site engineering

personnel

regarding this problem,

and the necessity

to provide adequate

and specific location information

on design drawings.

The licensee

issued

another work order to document

installation

and inspection of the support in example

2 in accordance.

with their procedural

requirements.

The support did not require

any

additional modification.

The inspector

reviewed the completed

inspection records

and verified that the inspections

had

been

completed

in accordance

with the licensee's

procedures.

Additional corrective

actions

include counseling

and training of all field engineers

to

emphasize

the importance of proper closeout of work plans,

and

a

statistical

sample to review documentation for conduit support

installations.

Enclosure

2

0

il

<Qi

8

(Closed)

Unresolved

Item 260/95-52-01,

SDV System Inspection

Following

Reactor

Scram

4.3

This unresolved

item concerned

implementation of the licensee's

commitment to inspect the scram discharge

volume system after the first

scram from rated temperature

and pressure

following a refueling outage.

The commitment

was

made in response

to Generic Safety Issue

(GSI) 40-

Safety Concerns

Associated with Pipe Breaks in

BWR Scram System.

Review

of operations

data (control

room logs

and computer printouts)

showed

that the

SDV system

was walked down and inspected within 30 minutes

on

August 9,

1991, following the first scram which occurred

from full

temperature

and pressure

following the refueling outage (first cycle

following Unit 2 restart).

The data

was not available for review for

June 3,

1993 scram

(second

cycle following Unit 2 restart).

For the

December

2,

1994 scram (third cycle following Unit 2 restart),

the

control

room logs indicate that the

SDV system walkdown was not

completed within the 30 minutes time period

as per the licensee's

commitment.

However, further review disclosed that the

SDV system

was

subjected

to

a hydrostatic test prior to startup after the last Unit 2

refueling outage.

The hydrostatic test satisfies that licensee's

commitments for SDV system

walkdown inspection.

The licensee

revised

their commitment for the periodic walkdown inspection of the

SDV system

in a letter to

NRC dated

November 21,

1995, Subject:

Browns Ferry

Nuclear Plant - Revisions to Commitments

Concerning the Utilization of

Security Personnel

for Notification of Irradiated Fuel'amage,

Replacement

of the Process

Computer,

and Periodic Walkdown of the Scram

Discharge

Volume Piping System.

The revised

commitment requires

a

SDV

system leakage

inspection

once per refueling outage during the reactor

vessel

hydrostatic test.

(Closed) Violation Item 296/95-52-02,

Failure to Construct

Cable Tray

Support in Accordance with Design Requirements

The licensee

responded

to this violation in a letter dated

November 9,

1995, Subject:

NRC Inspection

Report 50-259,260,296/95-52

- Reply to

Notice of Violation.

The licensee attributed the cause of the violation

to be personnel

error due to a poorly coordinated field design

change.

The licensee

issued

PER Number

BF

PER 95 1125 to document

and

disposition this problem.

A work order was issued to complete the two

missing flare bevel welds.

The inspector re-inspected

the support

and

verified the welds were completed

in accordance

with design

requirements.

The inspector also reviewed the quality control

inspection records

which documented

inspection of the welds.

The

licensee

issued

a memorandum to field engineering

personnel

which

summarized

the problem and reminded personnel

of their responsibility to

properly coordinate

design

changes.

A statistical

sample of other

new

cable tray supports

installed in Unit 3 were walked down to verify that

all welds were completed

as required

by design

documents.

No additional

problems (i.e., missing welds) were identified.

One other issue

was

Enclosure

2

<

lgi

identified, which had also

been included

on

BF PER 95 1125,

concerned

errors

made

when tagging cable tray supports with identification

numbers.

A large

number of errors in cable tray tag numbers

were

identified.

However,

these errors

had

no safety significance.

The

licensee

issued

work orders to correct the tag numbers.

4.4

(Closed)

Inspector

Followup Item (IFI) 260,296/95-41-02,

Platform Steel

gualification

This IFI was identified due to questions

regarding calculations

used to

qualify reinforcement

elements

on the Unit 3 drywell platform structural

steel

beams.

The problems

involved effective areas,

cut-off points,

critical load cases,

and selection of the critical sections to be

checked.

Problems identified were

as follows:

In Calculation CD-(3303-920114,

Revision 6, the interaction ratio

was not checked for the applied stress

against

the allowable

stress for Operating

Base

Earthquake

(OBE) case for Member

5

(8WF17) from 0.7L to 0.9L to qualify the member.

The section

modulus

used for this member in Revision

6 of the calculation

was

calculated

using conservative

assumptions.

The section

modulus

for the member

was recalculated

using the actual

beam properties

which were used to check the applied stresses

in the member.

The

revised calculations

showed the applied stresses

were less

than

allowable stress

values.

Calculation CD-(3303-930573,

Revision 6, qualified composite

section

k2-k2 on Drawings 3-48E453-2;

Revision

1

(DCA W17767-003,

Revision 0).

This composite section

was

a wide flange

10WF21

beam

reinforced

by a T-section

(WT Bx15.5) attached

(welded) to the web

in the horizontal direction.

The problem concerned

the licensee's

failure to check this composite section

using the full effective

area to reduce the allowable stress for the ineffective

beam

elements,

or to reduce the ineffective area to develop the full

allowable stress

per AISC Code requirements.

The licensee

revised

the calculation to check the unstiffened lengths

using all the

elements

in the composite section to meet the code requirements.

All the elements

were acceptable

and could

be used for the fully

effective areas.

Therefore, this problem was resolved.

Calculation CD-(3303-920114,

Revision 6, qualified

a composite

beam which consists of a wide flange

10WF27 with a ~/i inch thick

side plate welded

between

the

beam flanges

on one side of the

10WF27,

and .a Bx6xj inch tube steel

section

welded to the side

plate using stitch welds.

During review of this calculation,

the

Enclosure

2

jgi

10

inspectors

noted that the licensee

had not evaluated

the effect of

transfer of stresses

from the tube steel

into the plate

and

ques i

uestioned

the licensee

regarding behavior of the composite

section for integration of stresses.

The licensee

fabricated

and tested

a test

beam which was similar

to the composite

beam.

The test

beam was fabricated

from a

W12x27, % inch thick plate

and Sx8xj inch tube steel

section.

The

purpose of the test

was to demonstrate

that

beam theory was

applicable for the composite

member.

The test

beam

was clamped in

test frames at its two ends

(simple supported)

and loaded using

a

hydraulic jack.

The load was applied to the flange of 'the W12x27,

to duplicate field conditions.

When the test load reached

60,900

pounds,

the anchorage for the test

frame failed, ending the test.

The test

beam was examined

by licensee

engineers

during and after

the test.

There were

no indications of weld cracks,

or damage to

or distortation of the

beam.

The maximum stress

at the extreme

edge of the

WF beam under the test load was 30,600 psi which was

below the allowable value of 32,400 psi.

The inspectors

examined

the. test

beam

and verified that it was

constructed

to be representative

of the actual as-built composite

member existing in the drywell. The inspectors verified the member

sizes

used in the test

beam were

as stated

by the licensee

and

that the method

used

(4 inch stitch welds at

12 inch centers)

to

fabricate the composite section duplicated field conditions.

The

inspectors

also verified that the test

beam

had not been

damaged

during the test.

There were

no indications of distortation or

weld cracking.

The inspectors

concurred with the licensee's

conclusions that the test demonstrated

that

beam theory was

applicable for the composite

member.

The licensee

revised the design calculations to incorporate

shear

flow theory to calculate

combined

bending

and shear stresses

acting at various points in the composite

cross section.

The

calculated

stresses

were less than allowable stress

values.

The

licensee's

design methodology were also discussed

during the

meeting with the Office of Nuclear Reactor Regulation

(NRR)

discussed

in paragraph

5.0,

below.

During the November

6 meeting,

NRR personnel

requested

that the

licensee verify that the composite

member

was constructed

accordance

with design drawing requirements.

When licensee

engineers

performed

a walkdown inspection of the

member

on

November 8,

1995, they discovered that the welds connecting the ~/i

inch thick plate to the

12

WF27 beam flanges

were not the

221 inch

continuous

length at each

end of the

member

as specified

on the

design drawings.

The actual

welds were only approximately

12

inches long.

The licensee

documented this problem on

PER number

Enclosure

2

.4

il

<p

<Ql

5.0

BF PER 951704.

A work order

was initiated to correct the welds.

The inspectors

examined the member

and verified it had

been

repaired

{welded) in accordance

with the details

on the design

drawing,

DCA WI7538-086, Revision 5.

The licensee

revised the

drawing and issued

Revision

6 to clarify the details for

fabrication of the composite

member.

The inspectors

discussed

the

extent of Condition evaluation of this

PER with licensee

engineers.

In evaluating the extent of condition, the licensee

inspected

the

6 other subframes

which had

been modified and

reviewed the

DCAs issued for structural

steel platform steel

modifications.

No other weld problems

were identified.

The

licensee

also reviewed the design drawings for the similar

subframe in Unit 2.

The review disclosed that different design

details

were

used to reinforce the member.

Failure to fabricate

the member in accordance

with design requirements

was identified

to the licensee

as another

example of Violation item 296/95-57-01.

This example is not considered

licensee identified since the

licensee

discovered

the incorrect welds

as

a result of questions

raised

by

NRC personnel.

Meeting

Summary

On November 6,

1995,

a meeting

was held in the

NRC Headquarters

Office in Rockville, Maryland to discuss

the design methodology

used in design of cover plates

on

beam sections.

The attendees

at

the meeting were

as follows:

G. Bagchi, Chief, Office of Nuclear Reactor Regulation, Civil

Engineering

and Geosciences

Branch

(NRR/ECGB)

D. Jeng,

Section Chief,

NRR/ECGB

J. Williams, Project Manager,

NRR

R.

Chou,

Reactor

Inspector,

Region II

J.

Lenahan,

Civil Engineer,

Region II

P. Salas,

Browns Ferry Licensing Manager,

TVA

J. Valante,

Browns Ferry Lead Civil Engineer,

TVA

G. Thomas,

Senior Structural

Engineer,

Bechtel

Corporate Offices

P. Koski, Structural

Engineer,

Browns Ferry Project,

Bechtel

Topics covered

in the meeting included discussions

of methods

used

to calculate stress

in beam composite sections,

weld design,

and

selection of critical sections for analysis.

The licensee

also

discussed

the results of a load test they performed

on

a mock up

model of a composite section to demonstrate

that the composite

section

behaved

as

a beam.

The test results

were acceptable.

NRR

personnel

requested

that the inspectors

perform an inspection to

confirm that the test

beam was fabricated to duplicate field

conditions,

and that the as-built

beam

was fabricated in

accordance

with design drawing requirements.

The results of the

inspection

are discussed

in paragraph

4.4,

above.

Enclosure

2

il

~

i

12

6.0

.Exit Interview

The inspection

scope

and results

were summarized

on October 20,

1995

and

November

16,

1995, with those

persons

indicated in paragraph

1.

The

inspector described

the areas

inspected,and

discussed

in detail the

inspection results listed below.

Proprietary information is not

contained

in this report.

D'issenting

comments

were not received

from

the licensee.

Violation Item 296/95-57-01,

Failure to Install Modifications in

Accordance with Design Drawing Requirements

Enclosure

2

'1

0

<Qi