ML18033B737

From kanterella
Jump to navigation Jump to search
Insp Repts 50-259/91-17,50-260/91-17 & 50-296/91-17 on 910429-0510.Violations Noted.Major Areas Inspected:Review of Operational Interface Control,Personnel Access Control, Design & Mods,Secondary Containment & Fire Protection
ML18033B737
Person / Time
Site: Browns Ferry  Tennessee Valley Authority icon.png
Issue date: 06/10/1991
From: Kellogg P, Patterson C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML18033B734 List:
References
50-259-91-17, 50-260-91-17, 50-296-91-17, NUDOCS 9106270078
Download: ML18033B737 (17)


See also: IR 05000259/1991017

Text

~ps RE0(l~~P

F

0

Cy

~i

4V

O

Iill

O

+n +**++

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTASTREET, N.W.

ATLANTA,GEORGIA 30323

Report Nos.:

50-259/91-17,

50-260/91-17,

and 50-296/91-17

Licensee:

Tennessee

Valley Authority

6N 3&A Lookout Place

1101 Market Street

Chattanooga,

TN

37402-2801

Docket Nos.:

50-259,

50-260,

and 50-296

License Nos.:

DPR-33,

DPR-52,

and

DPR-6&

Facility Name:

Browns Ferry Units 1, 2,

and

3

Inspection at Browns Ferry Site near Decatur,

Alabama

Inspection

Cond cted; April 29, - May 10,

/'

FF

Inspector:

C.

Patterson,

Sensor

Res>dent

Inspector

E. Christnot,

Resident

Inspector

T.

Cooper,

Resident Inspector

Date Signed

Approved by:

Pau

I

TVA eet-'ms,

Projects

ivision

SUMMARY

a

e

signed

Scope:

This special

announced

inspection of the unit separation

program was conducted

to verify that Unit

2 startup

and operation

would not

be

impacted

by the

planned

modifications for Unit 3.

This included

a review of the operational

interface

control,

personnel

access

control,

design

and

modifications,

secondary

containment,

fire

protection,

training,

and

division

of

responsibilities.

Results:

0

The unit separ ati on program

has

been adequately

implemented to suppor t Unit 2

restart. 'he operational

inter face controls

and personnel

access

control

have

been

established.

Mechanical,

and electrical

systems

in Units 1 and

3 needed

to support Unit 2

have

been

uniquely identified.

Boundary isolation valves

910b270078

910b11

PDR

ADOCK 05000259

Q

PDR

have

been chained

and locked closed.

Plant personnel

have received training on

the

separation

program with additional

training for plait operators.

The

delineation

of responsibilities

and

lines

of

commu'nication

between

the

operating unit and construction unit have been established.

One violation was identified for failure to follow the hold order procedure,

paragraph

3.

The separation

hold or'der tags

were being

hung without first

establishing

the clearance

boundary

and independently verify'ing the boundary.

This is in the reverse

order of the procedure

requirements.

Implementation of

hold orders

is

a

weakness

in the

operations

area.

There is

a lack of

understanding

of the purpose

of a clearance

boundary.

Personnel

sign onto a

hold order without reviewing the specifics of the boundary against the work to

be performed.

In this case

the boundary

was not ever established.

During the inspection, it was identified that sealing of conduit and junction

box in Units

1 and

3 around equipment

needed for Unit 2 operation

had not been

considered,

paragraph

3.

This was

a problem in Unit 2 when spurious actuation

of open

head fire spray nozzles

wet equipment in the reactor building.

Most of

the

open

head

nozzles

were replaced in Unit 2 and components

sealed

because

of

this

concern

or the

environmental

qualification of equipment

program.

The

licensee

sealed

an additional

216

items

in Units 1 and

3 to resolve this

concern.

REPORT DETAILS

Persons

Contacted

Licensee

Employees:

  • J.

Bynum', Vice President,

Nuclear Operations

0. Zeringue,

Vice President,

Browns Ferry Operations

  • L. Myers, Plant Manager

"M. Herrell, Operations

Manager.

J.

Rupert, Project Engineer

"M. Bajestani,

Technical

Support

Manager

R. Jones,

Operations

Superintendent

A. Sorrell, Maintenance

Manage~

G. Turner, Site Quality- Assurance

Manager

"P. Carier, Site Licensing Manaoer

"P. Salas,

Compliance Supervisor

"J. Corey, Site Radiological Control Manager

R. Tuttle, Site Security Manager

Other

licensee

employees

or contractors

contacted

included

licensed

reactor

operators,

auxiliary

operators,

craftsmen,

technicians,

public

safety officers, quality assurance,

design,

and engineering

personnel.

NRC Personnel

"C. Patterson,

Senior Resident

Inspector

E. Chri stnot,

Resident

Inspector

"W. Bearden,

Resident

Inspector

  • K. Ivey, Resident

Inspector

"G. Humphrey,

Resident

Inspector

"Attended exit interview

Acronyms

and Initialisms used

throughout this report

are listed in the

last paragraph.

Program Description

Browns Ferry Unit 2 is being returned to service after

a six year

shutdown

following extensive modification work.

Similar modifications

ar'e

planned

for Unit 3

and eventually Unit 1.

Since all three units are physically

adjacent

and operationally interdependent,

the licensee

established

a Unit

Separation

Program.

This program established

the controls

necessary

to

operate Unit 2 while working

on Unit 3 with Unit

1 in layup.

The program

is

defined

in

procedure

SSP-12.50,

Unit

Separation

for

Recovery

Activities.

This

procedure

contains

the

personnel

access

control

and

system

operation

interface control.

The personnel

access

control consist

of physical

and administrative

measures

to restrict Unit

2 operating

spaces

from Unit 3 recovery personnel.

This 'consists

of barriers,

unique

badging

and posting of signs.

The

System

Operational

Interface

Control

consists

of color coded interface drawings,

colored tape,

signs

and tags,

and hold orders.

3.

Operation Interface Control

a

~

Boundary Establishment

The inspector

reviewed the system interface boundaries

to verify the

boundaries

were adequately

established.

The

licensee

established

the

separation

boundary

by using

as the

bases

the

Unit

2

safe

shutdown

analysi s

boundary

surrounded

by

additional operational

boundaries.

The safe

shutdown

boundary review

was

performed with Bechtel

assistance

and included

a review of the

essential

calculation

for those

applicable

systems.

Some of thi s

review

was

previously

addressed

in

IR

91-06.

Additional

items

reviewed

were

FSAR Chapter

14,

Appendix

R

Shutdown

Analysis

and

Unit 2 Dependency Matrix.

No additional

items were identified by the

FSAR Chapter

14 or Dependency Matrix.

The Appendix

R review revealed

that the Unit 3

DGs were needed for safe

shutdown if a fire occurred

in the Unit

1

and

2

DG building.

However,

the Unit

3

DGs

are

required

by TS to support

common equipment.

The inspector

cross-referenced

the list of safe

shutdown

systems to

the list of systems

needed

to support Unit 2 operation listed in'SP-

12.50.

The Fire Protection

system

was not listed in SSP-12.50.

The

licensee

stated this

system is already

red color coded

and required

by existing

TS.

The inspector

agreed

there

was

ample justification

for removing this

from the list'.

The inspector

questioned if the

electrical

components

in Units

1

and

3 were adequately

sealed

from

spurious

actuation

of

the fire protection

system.

A previous

violation for, this concern,

87-33-01,

was identified.'nit

2 fire

protection

systems

were

upgraded

and

most

open

head

spray

nozzles

replaced or removed.

The

same

upgrades

were not performed in Units

1

and 3.

The licensee

reviewed the separation

drawings

and issued

FDCN

to

DCN H0397

on

May 10,

1991, to seal

an additional

216 items.

This

sealing

would be completed before restart of Unit 2.

The inspector

noted that

FSAR Appendix

F, "Interfacing Systems"

had

not been reviewed.

The licensee

reviewed the Appendix and identified

no additional

items that were not previously addressed.

The

inspector

concluded

the boundaries

were adequately

established

'nd

concerns

resolved.

0

Clearance

Boundary

The inspector

reviewed the following hold orders for separation:

3-91-95

Unit 2/Unit 3 Electrical Interface Separation

1352 Tags

3-91-96

Unit 2/Unit 3 Mechanical

Interface Separation - 714 Tags

1-91-66

Unit 1/Unit 2 Mechanical

Interface Separation

-444 Tags

1-91-67

Unit 1/Unit 2 Electrical Interface Separation - 1223 Tags

The hold orders

were denoted

as

90 to

95% complete

on the plan of the

day.

The

inspector

questioned

why the

hold orders

were

not

1005

completed'he

clearance

sheet,

form SDSP-216,

was reviewed

and the

signatures

for

clearance

boundary

established

and

independent

verification were not signed.

The personnel

preparing

the hold order

were questioned.

There

was

some confusion whether the hold order had

been

issued

or

released.

However,

the. hold order tags

were

being

,placed

on equipment in the plant.

This is

a violation

TS Section 6.8. 1 concerning

procedures.

SDSP-

14.9,

Equipment

Clearances,

Section

6.3,

requires

a

clearance

boundary

be established

and independently verified before the hanging

of hold order

tags.

This violation is identified

as

VIO 259,260,

296/91-17-01,

Failure to Follow Hold Order

Procedure.

The licensee

issued

PRD to correct this problem.

Additionally the inspector

reviewed

hold order 0-91-160.

This

was

for Unit

1 loads

not required for Unit 2 Cycle

5 operation.

A hold

order

0-91-161

was

in place

because

of

ampacity

and

separation

concerns

related

to other

plant equipment.

The concerns

would

be

resolved

by modification

once

the respective

unit

was

returned

to

service.

The

common accident

signal

was disabled

by a

DCN.

This would prevent

Unit

1 or Unit 3

LOCA signals

from actuating Unit 2 equipment.

This

was previously reviewed in IR 90-23.

The inspector

questioned

the operational

scheme for tagging boundary

breakers

and valves.

For valves the boundary valves

had both

a hold

order tag

and orange

and black tag.

The valves were tagged

closed to

prevent

fluid flow.

Electrical

breakers

remain

closed

allowing

current flow but,

were

labeled with an

orange

and black tag.

The

licensee

stated

this

method

was

explained

in

the

separation

procedure.

The

inspector

concluded

although this

w'as inconsistent

the procedure

explanation

was adequate.

Tapes

and Labeling

During the drawing walkdowns,

the

use of the orange colored tape

and

labeling of electrical

panels

was inspected.

In general,

the

use of

tape

or labels

was

found to adequately

denote

systems

required for

Unit 2 operation

which were not physically located

in Unit 2.

The

following minor items were identified:

1.

Tape

was

found

on

the Unit

3

DG exhaust

lines

which

was

a

possible fire hazard.

The licensee

removed

=-the tape

on May 1,

1991.

2.

Tape

was

found

on

a Unit 3 control

bay chiller but the chiller

was

abandoned

equipment.

The

licensee

removed

the

tape

on

May 1,

1991.

3.

In Unit

2

on the

4160

shutdown

board

C, there were labels for

the

breaker

control

power

on

the

boards.

The

inspector

questioned

why the labeling was in Unit 2.

The licensee

removed

the labels

on May 1,

1991.

CARR

BFP

910129

was

issued prior to the beginning of the inspection

stating

that

the

tape

used

for marking

the

interfaces

was

not

procured

under

required specifications.

Per

the specifications

.he

allowed halogens is 1000

ppm for use

on corrosion resistant

metals,

while the tape

used

contains

about

85,000

ppm.

The specifications

requires

that all

tape

be

removed

before

returning

a

system

to

operation,

contrary

to

the

intended

purpose

of the

tape.

The

licensee

is

removing

the

tape

from the

stainless

steel

piping,

cleaning

and testing

the piping,

and

then will sleeve

the pipe and

retape

the sleeve.

This will resolve

the

problems with the

halog'en

content of the tape

and the removal

requirements,

since the tape will

be

on the sleeve,

not on the piping itself.

d.

Separation

Drawings

The inspector

reviewed

and walked down the following drawings:

45E614-11

10-45E614-5

120V AC/250Y

DC Valves and Misc.

Wiring Diagram

120V AC/250V DC Valves and

Misc.

1-45E1647-1

Wiring Diagram Unit Control Board Panel 9-9,

Cabinet

1,

1-45E614-9

1;45E701-3

0"15E500-2.

3-15E500-3

Wiring Diagram

Misc.

Wiring Diagram

120V AC/250V DC Valves and

BDl RPS

PWR Single Line

Key'iagram of Standby

Systems

Key Diagram of Normal

and Standby Auxiliary

Power System

.

5

0-45E710"4

Key Diagram Instrumentation

and Controls,

DC

and

AC Power System

3-45E3647-1

Wiring Diagram, Unit Control Board,

Panel 9-9, Cabinet

1

1-47E814-1

3-45E779-20

2-45E779-18

Flow Diagram Core Spray System

Wiring Diagram 480V Shutdown Auxiliary Power

Schematic

Diagram

Wiring Diagram 480V Shutdown Auxiliary Power

Schematic

diagram

1-47E1847-1

Mechanical

I&C Flow Diagram Control Air

System

3-47E861-1

Flow 5 Control

Diagram Diesel Starting Air

System Diesel

Generator

3A

1-47E813" 1

2-47E811-1

1-47E858-1

3-47E850-1

Flow Diagram Reactor

Core Insolation Cooling

System

Flow Diagram Residual

Heat

Removal

System

Flow Diagram

RHR Service Water System

Flow Diagram Fire Protection

and

Raw Service

Water

3-47E858-1

3-47E844-3

Flow Diagram

RHR Service

Water

System

Flow Diagram

Raw Cooling Water

The

inspector

walked

selected

systems

down to assure

the

proper

isolation

of

boundary

valves

on

interfacing

systems.

Valves

identified on drawings

as

boundary isolation valves

were

inspected.

All of the identified valves

had

a hold tag

hung

on them, they'had

been

chained

in the required position,

and

they

had

the

required

orange

and black sign

hung

on the valve,

per procedure

SSP

12.50,

identifying

the

valve

as

necessary

for Unit

2

operation.

The

boundary

system

piping

was

properly

marked with orange

tape,

as

required

by the procedure.

The inspector

reviewed

SSP

12.50

and the list of designated

drawing

locations did not contain the centralized

EOF or CECC.

The licensee

placed

a set of critical drawings in CECC.

An inspector verified the

drawings were in place

on May 10,

1991.

4.

Per sonnel

Access Control

a

~

Physical Barriers

.The inspector

examined the physical barrier program being implemented

to

separate

Unit

3 activities

from Unit 2.

At the

time of the

inspection,

the

barriers

had

been

fabricated,

and

were

being

installed.

Hard hats

were being issued to Unit 3 workers that are .dissimilar to

any other

hardhats

in

use

at

the site.

A light blue

hard . hat

signifies that the worker is assigned

to Unit

3

and is not 'exempt

from the Unit 2 ac'cess

control restrictions.

The licensee

procedure,

SSP 12.50,

requires that

a list of exempt

personnel

who are

allowed

to freely travel

between Unit 3 and Unit 2 be developed.

Non-exempt

personnel will be required to obtain

an orange

and black

access

badge prior to entering

Unit 2

from Unit 3.

Before

these

badges

can

be issued,

the person

must be qualified through experience

or training to perform the required

work on Unit 2.

The licensee

procedure

requires

that Unit

3 work control

and the job supervisor

are responsible

for assuring

that

each

individual requi red to enter

Unit 2 is qualified.

Access

to the Unit

3 reactor

building will be

through

the

same

airlock being

used for access

to the Unit 2 reactor building, until

the secondary

containment isolation separation

is completed.

At that

time barriers will be placed to prevent

access

to unit

3 through the

airlock.

The equipment airlock will be used for Unit 3 access after

the separation.

Access Control

The inspector interviewed security

management

concerning

the measures

being

taken to implement .the

access

control

program for Unit

3 and

Unit 2.

The security force has

been

prepared for the

implementation

of the

separation

program.

They

have

received

the

same

general

employee

training

as

the

plant

personnel

and

are

familiar with

requirements

for the unit separ'ation.

0

Unit

3

recovery

personnel

must

meet

the

vital

area

access

requirements

before

being

issued

a badge,

but their badges will be

distinctively marked,

with either

a blue dot or

a blue stripe,

to

differentiate

them from the unit 2 work force.

For Unit 3 personnel

found in Unit 2 without the proper authorization,

security plans to

consider

the 'incident

as

a security violation, to

be dealt with as

such.

The inspector

reviewed

and observed

the licensee's

design

and modification

activities involved with the unit separation

program.

This consisted of a

review of drawings,

DCN, associated

FDCNs,

and the Support to Frontline

Dependency Matrix.

The observations

consisted of completed work and work

activities in the field.

Dependency Matrix

'he

inspector

reviewed the

dependency

matrix in relationship to the

scope

of the electrical

system

separation

boundary.

The inspector

noted

the matrix did not list any Unit 3

RMOV Board 480V AC or 250V

OC; listed Unit

RMOV 480V AC Boards

1A, B,

C, and

E; listed all

4

KV

shutdown boards; listed all, except

3D,

4KV Unit Boards;'did

not list

the

Unit 3,

4KV Tie

Board;

and listed

various

other electrical

boards.

The

inspector

observed

the

electrical

system

boundary

identification tags

on various electrical

boards

such

as

41'60 volt

unit,

common,

bus tie

and

shutdown

boards,

480 volt

common

and

shutdown boards,

480 volt and

250 volt

DC

RMOV Boards,

and

120/208

volt I and

C panels.

The inspector

concluded

from the review,

walkdown,

and followup of

the dependency

matrix versus

the electrical unit separation

boundary

that

no electrical

board

listed

on

the

matrix is

outside

the

electrical unit separation

boundary.

b.

The inspector

noted that the dependency

matrix was

an operator aid in

the control

room.

The matrix references

numerous

notes but the notes

were

not available

to the operator s.

The licensee

made

the

notes

available to the control

room operators

on May 1,

1991.

Design

and Modifications

The

inspector

reviewed,

observed,

and

followed

up

the

licensee

activities

involving modifications for Unit Separation.

The

DCNs

reviewed

were

W16408,

Physical Modificati'on to penetrations,

W16441,

Seal

Unit

3 Stairwells to Refuel

Floor,

W15432,

Emergency

Lighting

for Unit 3 Equipment Airlock; W16576,

Add a Card Reader to Door 25A,

Airlock from Turbine Building to Unit 3 Reactor Building, and W16567,

Install

New Emergency Stairwell.

The inspector

reviewed the various

DCAs associated

with the

OCNs. The'nspector

noted that

OCN W16440,

Masonry

Block Walls

and

Other

Components

of the Unit

3 'Elevator

Shaft,

and

DCN W16532,

Seismic Qualification of Unit 3 Refuel

Flow

Exhaust Ducts,

were not issued at the close of the inspection.

The inspector

observed

in progress field activities included in DCNs

W16567 and

W16576.

These activities involved

WPs 2069-91,

0074-91,

and 0076-91.

The inspector

reviewed the field work completed for DCN

W16567 which involved

WP 2069-91.

The inspector

concluded

from the reviews

and the observations

of the

work activities

that

the

modifications

were

being

installed

in

accordance

with the

DCAs and WPs.

c.

Temporary Alterations

The inspector

reviewed

two TAs.

One TA, involving the connections

to

the

SBGT

system

from the

Unit

3 containment,

containment

purging

system

and the

HPCI system,

had not

been

approved for installation.

The other TA, designated

TACF 3-91-002-040,

involved the installation

of an expandable

plug between

the Unit 2 and Unit 3 turbine building

station

drain

sumps.

The

inspector

observed

that this

TA was

installed

and adequately identified.

The inspector

concluded that the

BFN separation

program

as it applied to

the

areas

reviewed

was

being

conducted

in

a

controlled

manner

in

accordance

with procedures.

6.

Secondary

Containment

The

inspector

reviewed

the

separation

plans

associated

with secondary

containment.

Presently four zones,

the three reactor

buildings

and refuel

floor, are treated

as

a

common

secondary

containment.

This will remain in

place

when Unit'

is started.

Several

months after restart Unit 3 reactor

zone will be separated

from the other three

zones.

Several

modifications

are

being

prepared

to

permit

isolation

of

Unit

3.

Some

of

the

modifications necessary

are

as follows:

Rubber boots

on piping penetrations

Reinforce concrete

blocks

on top of elevator shaft

Seal

up elevator cables

and ventilation

Modification to reactor cavity HVAC

A TS change is also required for Unit 3.

TS 3.7.c.2.6.

requires

shu'tting

down all three units if reactor

zone

containment

is lost in any reactor

zone.

These activities wi 11

be followed during

the routine

inspection

program after Unit 2 restart.

7.

Fire Protection

The

inspector

reviewed

the Fire Plotection pre-fire plans

and verified

that the interfaces

between Units

2

and

3

had

been

accounted

for in the

latest revision.

All interfacing

access

areas

between the two units had

been

accounted

for in the revision.

The

access

areas

from Unit

3 into

Unit

2

Reactor

Building

were still listed

as

alternate

access/egress

points, with a note stating that Security would be required to unlock the

doors

between

the two units.

The interfacing doors were only listed as

an

alternative, if the others

could not be used.

e

8.

Training

The inspector

observed

the training for unit separation

for the general

employees

and

the

licensed

operators.

The

general

employee

training

consisted

of

a video tape

which stressed

the procedure

requirements

of

licensee

procedure

SSP 12.50, Unit Separation

for Recovery Activities.

Licensed

personnel

received live training *at the beginning of a shift.

The inspector

observed

the training of one'f the operating shifts.

The

training consisted of watching the general

employee training tape

and then

having the instructor discuss

the procedure

SSP

12.50 with the personnel.

The training of the operating

personnel

did not include

any information

not provided in the procedure,

such

as the areas

where barriers

would be

erected,

an explanation of the, systems

and

components

chosen

as

boundary

components,

or any basis for the decisions'he

operators

were told that

the Unit 3 recovery

personnel

would be wearing

"unique"

badges,

but the

badges

themselves

were not described

to the personnel.

(}uestions to the

instruct or

were

usually

requesting

more

detail,

such

as

access

requirements

to the Unit 3

and Unit 2 reactor buildings and whether the

orange

tape being

used to mark the

boundary

system piping was acceptable

due to chloride leaching.

4

The operators

were required to successfully

complete

a test following the

training session.

The test consisted of 10 multiple choice questions

and

two short informational questions.

The operators

were allowed to use the

procedure

while taking the test.

Of the four shifts that

had

completed

the

training,

one

person

had failed the test.

This

person will be

required to repeat

the training.

The

inspector

concluded

that

the training

was

adequate

to explain the

separation

program.

The inspector

commented to operations

management

that

operations

personnel

may need

more detail in their training.

9

Oivision of Responsibilities

On

April

18,

1991,

the

licensee

i ssued

a

memor andum'o

delineate

responsibilities

and

lines

of

communications

between

BFN

Operations

(Unit 2)

and

BFN Restart

Organizations

(Unit 3).

BFN

Operations

is

responsible

for all

operations

and

programs

at

BFN which affect

the

licensing, operations,

and maintenance

of the units.

BFN Restart

provides

service

to

BFN Operations

for implementing modifications to

BFN Units I

and

3 based

on

NRC commitments

and established

criteria using

acceptable

BFN procedures.

The -inspector

concluded that the memorandum,

which would

be placed in a separation

procedure,

clearly defined responsibilities

and

communication

channels.

The

inspector

noted

one

comment

during

the

review of the

hold order

violation discussed

in this report.

Initially the Unit 2 operations staff

stated

that the hold order work was being performed

by Unit 3 people

who

j

e

10.

10

felt the

method

was acceptable.

The inspector

emphasized

that according

to the

memorandum that Unit 2 operations

was clearly responsible.

Exit Interview (30703)

The inspection

scope

and findings were

summarized

on

May 10,

1991 with

those

persons

indicated in paragraph

1 above.

The inspectors

described

the areas

inspected

and discussed

in detail the inspection findings listed

below.

The licensee

did not identify, as proprietary

any of the material

provided to or reviewed

by the inspectors

during this inspection.

There

were

no dissenting

comments

by the licensee.

Item Number

Descri tion and Reference

259,

260,

296/91-17-01

VIO, Failure to Follow Hold Order Procedure,

paragraph

3.

Acronyms and Initial i sms

0

AC

BFN

BFP

CAQR

CECC

CFR

DCA

DC

DCN

DG

EOF

FDCN

FSAR

HPCI

HVAC

IC

IR

KV

LOCA

NRC

PPM

PRD

RMOV

RPS

SBGT

SDSP

SSP

TA

TACF

TS

VIO

wp

Alternating Current

Browns Ferry Nuclear Plant

Browns Ferry Plant

Condition Adverse to Quality Report

Centralized

Emergency

Control Center

Code of Federal

Regulations

Design

Change Authorization

Direct Current

Design

Change

Notice

Diesel Generator

Emergency Operating Facility

Field Design

Change

Notice

Fi na 1

Sa fety Ana 1 ys i s

High Pressure

Coolant Injection

Heating, Ventilation,

and Air Conditioning.

Instrument

and Control

Inspection

Report

Ki 1 ovolt

Loss of Coolant Accident

Nuclear Regulatory

Commission

Parts

Per Million

Problem Reporting

Document

Reactor Motor Operated

Valve

Reactor Protection

System

Standby

Gas Trea'tment

Site Directors Standard

Practice

Site Standard

Practice

Temporary Alteration

Temporary Alteration Control

Form

Technical Specification

Violation

Work Plan