Discusses Establishment of Safety Review Sched Re Oper Lic. Based on Resource Eval,Estimates That SER Could Be Pub on 800324 W/Prospective Decision Date by 801219.Encloses Summary of Milestones Re Target Sched
ML18031A043
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 12/07/1978
From: Boyd R
Office of Nuclear Reactor Regulation
To: Curtis N
PENNSYLVANIA POWER & LIGHT CO.
References
NUDOCS 7812150179
Download: ML18031A043 (4)


Text

g.C Ol $70 Docket Nos.

50-P a

,50-388 l

ter.

Norman W. Curtis Vice President

- Engineering and Construction Pennsylvania Power and Light Company 2 North Ninth Street Allentown, Pennsylvania 18101

Dear Mr. Curtis:

Distribution Docket File NRC PDR Local PDR LWR ¹3 File D. Vassallo F. Williams

0. Parr S. Miner H. Rushbrook ELD

. IE (3)

R.

Boyd D. Crutchfield A. Abell K. Singer, SS J. Panzarella, SE H. Berkow

'CC:

NSIC TIC ACRS (16)

SUBJECT:

,SCHEDULE FOR THE RADIOLOGICAL SAFETY REVIEW OF THE SUS(UEHANNA STEAM ELECTRIC 'STATION, UNITS 1

AND 2 This letter discusses the establishment of a schedule for the safety review of your application for operating licenses for the Susquehanna Steam Electric

Station, Units 1 and 2 docketed on July 31, 1978.

The environmental review schedule has already'been sent to you.

- We have evaluated our workload, and estimate that our Safety Evaluation 1980, with a subsequent Prospective summary of the important milestones your information.

based on this resource evaluation we Report could be published by March 24, Decision Date by December 19, 1980.

A of that target schedule is enclosed for We appreciate, as discussed in our November 28 meeting, your views that

'completi'on of construction of Unit 1 could occur as early as March 1980.

In that light, we agreed to reevaluate the schedule this coming February when completion of first round questions should be accomplished.

With your assessment of when the responses can be provided, and an updated construction review by the Caseload Forecast Panel in March or April, we will reevaluate the staff review schedule to try to find a way to assure that the licensing and construction schedules are compatible.

To this end, I believe iQ would be useful if the results of the first'rehearing conference were available by this time to assist us in estimating the hearing contribution to the overall schedule.

It will be equally important in trying to accelerate this review that any matters of disagreement or areas of uncertainty uhich might arise should be discussed promptly with the project manager.,

If he cannot resolve them 7f'/ ~/goy 7 orrscc~

CUNNAsec~

oAT43m NRC PORN 318 (9 76) NRCM 0240

  • Il.s.oovcllNIIONT'rmlNTINoortlccl I ~ se lee

'I~ e

fir. Norman!I. Curtis DEc 07 19'5

himself, he will arrange for a meeting with appropriate management to discuss them.

This will avoid unnecessary schedule delays.

Beyond that, it will be especially important to keep in close touch with the project manager over the next several months to make sure that all of these interim activities stay on schedule so that it will be possible to make a meaningful reassessment by the flarch/April time period.

Mr. Sydney Miner 3 the project manager, can be reached at (301) 492-7896.

Enclosure:

As stated Sincerely,,

Uriginal signed by:

Roger S. Boyd Roger S. Boyd, Director Division of Project Management Office of Nuclear Reactor Regulation cc w/enclosure:

See next page orr3cc>

C URN Att CW RADII:LPM 12/ 5 /78 LWfg3~. BC OParr 12/ ~ /78 LW:A(P.....

DVassallo

'l 2/ ~/78 OPS:.0:

RBoy.g..

12/ ~

J7g II NRC PORM 318. (9-76) NRCM 0240

  • V,B,OOVCIINMCNTCNINIINO OrrICCI It 1 ~

t4 ~

t<t

Hr.

Norman W. Curtis cc:

Hr. Earle H. Head Project Manager Pennsylvania Power

& Light Company 2 North Ninth Street Allentown, Pennsylvania 18101 Jay Silberg, Esq.

Shaw, Pittman, Potts Trowbridge 1800 M Street, N.

W.

Washington, D. C.

20036 Hr. William E. Barberich, Nuclear Licensing Group Supervisor Pennsylvania Power

& Light Company 2 North Ninth Street Allentown, Pennsylvania 18101 Edward H. Nagel, Esquire General Counsel and Secretary Pennsylvania Power

& Light Company 2 North Ninth Street Allentown, Pennsylvania 18101 Bryan Snapp, Esq.

Pennsylvania Power

& Light Company 901 Hamilton Street Allentown, Pennsylvania 18101 Robert H. Gallo Resident Inspector P. 0.

Box 52 Shickshinny, Pennsylvania 18655

ENCLOSURE SUS UEHANNA STEAM ELECTRIC STATION, UNITS 1

5 2:

OL STAGE RADIOLOGICAL SAFETY REVIEW TARGET MILESTONES Milestone FSAR Docketed Date 7/31/78 Applicant's response to acceptance review questions received 8/11/78 through 1/22/79 First round questions issued to applicant Applicant's response to first round questions received Staff positions issued to applicant Applicant's response to staff positions received 12/08/78 through 2/16/79 3/02/79 through 5/11/79 6/22/79 through ll/09/79 9/21/79 through 11/09/79 Safety Evaluation Report Issued 3/24/80 ACRS Subcommittee Meeting ACRS Fullcommittee Meeting ACRS letter received Safety Evaluation Report Supplement issued Earliest start of RAD/SAFETY hearing (if required)

Prospective Decision Date (if hearing is required) 4/15/80 5/09/80 5/16/80 7/25/80 8/26/80 12/19/80