Confirms 850130 Telcon W/Ja Coffey Re 850207 Enforcement Conference at Region II Ofc to Review Apparent Violations Involving Operability of Safety Equipment & Status of Maint Improvement Program
ML18029A407
Person / Time
Site: Browns Ferry  
Issue date: 02/01/1985
From: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Parris H
TENNESSEE VALLEY AUTHORITY
Shared Package
ML18029A408 List:
References
NUDOCS 8503070052
Download: ML18029A407 (4)


Text

Tennessee Valley Authority ATTN:

Mr. H.

G. Parris Manager of Power and Engineering 500A Chestnut Street Tower II Chattanooga, TN 37401 Gentlemen:

'j

SUBJECT:

CONFIRMATION OF MEETING -

BROWNS

FERRY, DOCKET NOS. 50-259, 50-260 AND 50-296 This confirms the telephone conversation between Mr. J.

A. Coffey of your staff and Mr.

R.

D. Walker of my staff on January 30,

1985, concerning an enforce-ment conference to; be conducted at the Region II Office on February 7,
1985, at 10:00 a.m.,

EST.

Me requested this meeting to review apparent violations involving operabil:ity of safety equipment, the status of your Maintenance Improvement Program and to review TVA's evaluation of activities discussed in your letter from Mr. J.

P.

Darling to Mr.

James P. O'ei lly dated November 15, 1984.

A proposed meeting agenda is enclosed.

Should you have any questions regarding these arrangements, we will be pleased to discuss

'them.

Sincerely, James P. O'Reilly Regional Administrator

Enclosure:

Proposed Meeting Agenda cc w/encl:

J.

A. Coffey, Browns Ferry Nuclear Plant Site Director G. T. Jones, Plant Manager J.

W. Anderson, Manager Office of guality Assurance K.

W. Whi.tt, Chief,. Nuclear Safety.~

Staff D. L. Williams, Jr.,

Supervisor Licensing Section R.

E. Rogers, Project Engineer 8503070052 85020l PDR ADOCK 05000259 9

PDR

p~g I G'~:l

FEB 1 )9)5 2'cc w/encl:

NRC Resident Inspector Document Control Desk R. J. Clark, Licensing Project Manager, NRR State of Alabama RII MRuland;.jc 01/0(/85 RII FCa trell 01/g//85 RISHI DVerrelli 01/Pi/85 RII RII PB m

Jpuckett J lshinski 1/P/85 '/ t /85 1/Pi/85

FEB 1 1985 ENCLOSURE PROPOSED MEETING AGENDA Tennessee Valley Authority February 7,

1985, at 10:00 a.m.

EST I.

Opening Remarks II.

Enforcement Concerns III.

Discussions of Enforcement Issues J.

Nelson Grace'.

S. Cantrell TVA Representatives Failure of HPCI Outboard Isolation Valve due to reversed pinion gear (November 22, 1984).

Unusual Event associated with open equalizing valves and the core spray system (January 21, 1985).

Inoperability of HPCI due to inability to open in less than 25 seconds (December 9,

1984 to January 11, 1985).

Other maintenance related problems.

IV.

Discussion of Maintenance Improvement Program Status V.

Discussion of TVA's Evaluation of Activities Mentioned in November 15, 1984 Letter TVA Representatives TVA Representatives VI.

Closing Comments J.

Nelson Grace