Text

Northwest Medical Isotopes Construction Permit Application Review

  • Mandatory Hearing (Safety Panel 1)
  • January 23, 2018 NRC-011 United States Nuclear Regulatory Commission Official Hearing Exhibit In the Matter of:

NORTHWEST MEDICAL ISOTOPES, LLC (Medical Radioisotope Production Facility)

Commission Mandatory Hearing Docket #: 05000609 Exhibit #:

Identified:

Admitted:

Withdrawn:

Rejected:

Stricken:

Other:

NRC-011-MA-CM01 1/23/2018 1/23/2018

Panelists

- Chief, Research and Test Reactors Licensing Branch, NRR

-Project Manager, NRR

-Senior Project Manager, NMSS

-Project Manager, NRR 2

Licensing Process

  • Licensing process for NWMI production facility similar to that for other non-power Part 50 facilities
  • Unique licensing considerations 3

Advisory Committee on Reactor Safeguards Review

  • Staff presented at subcommittee and full committee meetings
  • Staff performed additional independent analysis
  • ACRS recommended issuance of construction permit
  • Staff documented the NWMI commitments in Safety Evaluation Report 4

Production Facility Licensing

- Special nuclear material batches contain greater than 100 grams of uranium-235

-Processes similar to those at existing fuel cycle facilities

Unique Licensing Considerations

  • Two processes described within a single facility

-Production facility licensed under 10 CFR Part 50

-Target fabrication licensed under 10 CFR Part 70

  • Understanding the interface between the two processes 6

Relationship Between Production Facility and Target Fabrication

  • Both processes described in construction permit application
  • Review focused on interface, shared systems, and impact
  • Permit would authorize construction of 10 CFR Part 50 production facility 7

Proposed Permit Conditions

  • Construction permit does not constitute approval of the safety of any design feature or specification
  • Permit conditions

-Criticality Safety

-Quality Assurance

-Site Characteristics 8

Criticality Safety Conditions

  • Criticality accident alarm system
  • Subcritical limit
  • Conditions are confirmatory
  • Termination of conditions 9

Quality Assurance Condition Similar to requirements of 10 CFR 50.55(f),

condition would support

-Adequate implementation of commitments in design, procurement, and construction

-Maintenance of documentation

-Approval of certain QAPP changes

-Correction of deficiencies 1

0

Geotechnical Condition

  • NWMI committed to performing site-specific geotechnical investigation
  • Since results could impact design bases, Staff recommends NWMI

-Identify sinkhole potential, soil characteristics, and liquefaction potential

-Submit design changes based on findings

  • Results inform construction inspection 1

1

Acronyms

  • CFR

- Code of Federal Regulations

- Office of Nuclear Reactor Regulation

  • NMSS - Office of Material Safety and Safeguards
  • NWMI - Northwest Medical Isotopes
  • QAPP - Quality Assurance Program Plan 1

2