Forwards IE Insp Repts 50-259/79-20,50-260/79-20 & 50-296/79-20 on 790802-03.No Noncompliance Noted
ML18024B033
Person / Time
Site: Browns Ferry  Tennessee Valley Authority icon.png
Issue date: 08/20/1979
From: Murphy C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Parris H
TENNESSEE VALLEY AUTHORITY
Shared Package
ML18024B034 List:
References
NUDOCS 7910010155
Download: ML18024B033 (4)


See also: IR 05000259/1979020

Text

I

~p,S REcy

(4

jf

0

gati.

++**+

In Reply Refer To:

RII:RJH

50-259/79-20

50-260/79-20

50-296/79-20

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTAST., N.W., SUITE 3100

ATLANTA,GEORGIA 30303

AUG2 0 1979

Tennessee

Valley Authority

Attn:

H.

G. Parris

Manager of Power

500A Chestnut Street

Tower II

Chattanooga,

Tennessee

37401

Gentlemen:

This refers to the inspection

conducted

by R. J. Hardwick of this office

on August 2-3,

1979 of activities authorized

by NRC License Nos.

DPR-33,

DPR-52

and DPR-68 for the Browns Ferry facility, Unit Nos.

1,

2 and 3,

and to the discussion of our findings held with J. L. Harness

at the

conclusion of the inspection.

Areas

examined during the inspection

and our findings are discussed

in

the enclosed

inspection report.

Within these

areas,

the inspection

consisted of selective

examinations of procedures

and representative

records,

interviews with personnel,

and observations

by the inspector.

Within the scope of this inspection,

no items of noncompliance

were

disclosed.

Two new unresolved

items resulted

from this inspection

and are discussed

in the enclosed report.

These

items will be examined during subsequent

inspections.

In accordance

with Section 2.790 of the NRC's "Rules of Practice",

Part 2, Title 10,

Code of Federal Regulations,

a copy of this letter and

the enclosed

inspection report will be placed in the NRC's Public

Document

Room. If this report contains

any information that you (or

your contractor) believe to be proprietary, it is necessary

that you

make

a written application within 20 days to this office to withhold

such information from public disclosure.

Any such application must

include

a full statement

of the reasons

on the basis of which it is

claimed that the information is proprietary,

and

shou%'d

be prepared

so

that proprietary information identified in the application is contained

V 9 x 0 0 z 6 t'ZS

AUG 2

0 1979

Tennessee

Valley Authority

in a separate

part of the document.

If we do not hear from you in this

regard within the specified period, the report will be placed in the

Public Document

Room.

Should you have any questions

concerning this letter,

we will be glad to

discuss

them with you.

Sincerely,

C. E. Murphy, Chi

Reactor

Construe ion and

Engineering

Support Branch

Enclosures:

Inspection Report Nos. 50-259/79-20,

50-260/79-20

and 50-296/79-20

cc w/enclosures:

J.

G. Dewease

Plant Superintendent

Post Office Box 2000

Decatur,

Alabama

35602

D. E. McCloud, Project Engineer

400 Chestnut Street

Tower II

Chattanooga,

Tennessee

37401