Forwards IE Insp Repts 50-259/79-09,50-260/79-09 & 50-296/79-09 on 790312-15 & Notice of Violation
ML18024A913
Person / Time
Site: Browns Ferry  
Issue date: 03/29/1979
From: Robert Lewis
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Parris H
TENNESSEE VALLEY AUTHORITY
Shared Package
ML18024A915 List:
References
NUDOCS 7907310155
Download: ML18024A913 (4)


See also: IR 05000259/1979009

Text

~g IIE0y,fp0

C

I

ClO

c Q

g

++*++

UNITEDSTATES

NUCLEAR REGULATORYCOMMISSION

REGION II

10'I MARIETTASTREET, N.W.

ATLANTA.GEORGIA 30303

MAR 2

9 1979

In Reply Refer To:

RII:DSP

50-259/79-9

50-260/79-9

50-296/79-9

Tennessee

Valley Authority

ATTN:

H.

G. Parris

Manager of,'ower

500A Chestnut Street

Tower II

Chattanooga,

TN

37401

Gentlemen:

This refers to the inspection

conducted

by D. S. Price of this office on

March 12-15,

1979, of activities authorized

by NRC Operating License Nos.

DPR-33,

DPR-52 and DPR-68 for the Browns Ferry Nuclear Plant Units 1,

2 and

3

facilities, and to the discussion of our findings held with H. L. Abercrombie

at the conclusion of the inspection.

Areas

examined during the inspection

and our findings are discussed

in the

enclosed

inspection report.

Within these

areas,

the inspection consisted of

selective

examinations

of procedures

and representative

records,

interviews

with personnel,

and observations

by the inspector.

One new unresolved

item resulted

from this inspection

and is discussed

in the

enclosed

report.

This item will be examined during subsequent

inspections.

'

5

P

f

During the inspection, it was found that certain activities under your

license

appear to be in noncompliance with NRC requirements.

This item and

references

to pertinent requirements

are listed in the Notice of Violation

enclosed

herewith as Appendix A.

This notice is sent to you pursuant

to the

provisions of Section 2.201 of the NRC's""Rules of Practice," Part 2, Title 10,

Code of Federal Regulations.

Section 2.201 requires

you to submit to this

office, within 20 days of your receipt of this notice,

a written statement

or

explanation in reply including:

(1) corrective steps

which have

been taken

by you 'and the results

achieved;

(2) corrective steps

which will be taken to

avoid further noncompliance;

and (3) the date

when full compliance will be

achieved.

In accordance

with Section 2.790 of the NRC's "Rules of Practice," Part 2,

Title 10,

Code of Federal Regulations,

a copy of this letter and the enclosed

inspection report will be placed in the NRC's Public Document

Room. If this

report contains

any information that you (or your contractor) believe to be

proprietary, it is necessary

that you make

a written application within 20

days to this office to withhold such information from public disclosure.

Any

such application must include

a full stategept

of the reasons

on the basis of

V90731ois~

lr',

Tennessee

Valley Authority

MAR

'r- 8 879

which it is claimed that the information is proprietary,

and should be prepared

so that proprietary information identified in the application is contained in

a separate

part of the document.

If we do not hear from you in this regard

within the specified period,

the report will be placed in the Public Document

Room.

Should you have any questions

concerning this letter,

we will be glad to

discuss

them with you.

'Sincerely,

g. c.

R.

C.

ewis, Acting Chief

Reactor Operations

and Nuclear

Support Branch

Enclosures:

1.

Appendix A, Notice of Violation

2.

Inspection Report Nos. 50-259/79"9,

50-260/79-9

and 50-296/79-9

cc w/encl:

cc w/encl:

J.

G. Dewease

Plant Superintendent

P. 0.

Box 2000

Decatur,

AL

35602

D. E. McCloud, Project Engineer

400 Chestnut Street

Tower II

Chattanooga,

TN

37401

.