Responds to NRC Re Violations Noted in Insp Rept 50-400/85-24.Corrective Actions:Review Criteria for Preoperational Procedures to Prevent Equipment Damage Established & Implemented & Personnel Briefed
ML18019A309
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 07/26/1985
From: Joseph Willis
CAROLINA POWER & LIGHT CO.
To: Grace J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
HO-850198-(O), NUDOCS 8508120483
Download: ML18019A309 (8)


Text

@ME JULY g ~

Carolina Power & Light Company p

~

gg )pi 31 SHEARON HARRIS NUCLEAR PROJECT P.O.

Box 101 New Hill, North Carolina 27562 Pile Number'SHP/10-13510 Letter Number:

HO-850198 (0)

Dr. J. Nelson Grace United States Nuclear Regulatory Commission Region II 101 Marietta Street, Northwest (Suite -2900)

Atlanta, Georgia 30323

Dear Dr. Grace:

In reference to=.your letter of June 28, 1985 and Inspection Report 50-400/85-24, the attached is Carolina Power and Light Company's reply to the violation identified in the inspection report.

It. is considered that the corrective action taken is satisfactory for resolution of the item.

Thank you -for your consideration in this matter.

Yours very truly, J. L. Willis Plant General Manager Shearon Harris Nuclear Power Plant DLT:sbc Attachment cc'Messrs.

G. Maxwell/R. Prevatte (NRC-SHNPP)

Mr. B. C. Buckley (NRC)

NBI-Osl

'508120483 850726 PDR ADOCfC 05000400 G

PDR I ~Go/

~ f

~

~

S v

Dr. J. Nelson Grace bcc'. Mr. H. R. Banks Mr. T. A. Baxter (Shaw, Pittma Mr. C. S.

Bohanan Mr. H.

W. Bowles Mr. C. Carmichael (2)

Mr. N. J. Chiangi Mr. A. B. Cutter Dr. T. S. Elleman Ms. S. F. Flynn Mr. G. L. Forehand Mr. J.

F. Garibaldi (Ebasco)

Mr. J. L. Harness Mr. P.

C. Hopkins Dr. J.

D. E. Jeffries Mr. I. A. Johnson Mr. L. I. Loflin Mr. R.

E.

Lumsden Mr. R. L. Mayton, Jr.

Mr. S.

McManus Mr. G. A. Meyer Mr. C. H. Moseley, Jr.

Mr. D. L. Nordstrom (LIS)

Mr. G. A. Sinders Mr. M. Shannon (Westinghouse)

Mr. Sheldon D. Smith Mr. M. F.

Thompson Mr. A. C. Tollison Mr. E. J.

Wagner Mr. R. A. Watson Mr. J. L. Willis File: HI/A-2D File.'H-X-0544 Day File Document Services n, Potts 6 Trowbridge)

Attachment 1

CP&L Response to Violation 400/85-24-01 Re orted Violation:

10 CFR 50.55(f)(1) requires CP&L to implement the quality assurance program described or referenced in the Preliminary Safety Analysis Report.

Section 1.8.5.5 of the CP&L Quality Assurance Program requires that measures be established to ensure that inspections are conducted in accordance with documented instructions, procedures, and approved drawings.

Contrary to the above, on May 25,

1985, a site start-up engineer, while conducting a preoperational test by procedure 1-2080-P-01, directed an auxiliary operator to close the manually-operated suction and discharge valves for charging pump 1A.

The procedure did not allow or require the valves to be closed.

The subsequent test steps required running the pump.

The pump was started, with both valves closed, causing an overheated condition and ultimately a

pump failure.

Denial or Admission and Reason for the Violation'.

The violation is correct as stated.

The cause of the event was the failure of the responsible Start-up Engineer to follow pre-op procedure 2080-P-01 "HHSI Pumps Performance and Flow Balance Test".

As*stated in the violation, the Start-up Engineer directed that the manual suction and discharge valves be closed.

This occurred during the completion of testing Charging Pump 1A in procedure section 6.12 (determination of the time required for each CHG/SI Pump to reach full flow after initiation of

'S'ignal).

The pump was subsequently restarted on the next shift to perform procedure section 6.13 (MOV Dynamic Valve Operation and

Response

Time Testing).

The failure occurred after Charging Pump 1A was started.

While the action of closing the suction and discharge valves is required when a

pump is secured in earlier procedure sections, it was not required in procedure section 6.12.

In addition to the procedural error, we have concluded that two other elements were significant contributors to the failure.

The first was a deficiency in procedure 2080-P-Ol.

The procedure contained specific valve lineups referenced as procedure steps.

Valve lineup 12.5 referenced in procedure step 6.13.1 did not include specific entries for lineup of manual isolation valves.

The testing required by section 6.13 allowed the Start-up Engineer to select any Charging Pump, yet the procedure did not contain steps to verify that the manual suction and isolation valves were open for the selected pump.

The second element is the failure to effectively communicate the status of Charging Pump 1A to other personnel.

Neither the Auxiliary Operator nor the Start-up Engineer communicated this status to the Main Control Room at the time or to the respective relief personnel at the shift turnover prior to the failure.

The combined effect of these two items was that personnel responsible for directing and implementing the subsequent restart of the pump were not aware of the need to

Attachment 1 (Cont'd) realign the flow path for Charging Pump lA and were not required by 2080-P-01 to verify-the flow path.

Corrective Ste s Taken to Avoid Further Noncom liance:

The following steps have been taken to prevent recurrence'.

Operations and Start-Up Personnel have been briefed on verbatim procedure compliance and the requirement to keep the control room informed of any changes to system lineup status.

Each Start-Up Engineer and Shift Foreman have received and sig'ned a memorandum indicating their understanding of CP&L policy of verbatim procedure compliance and the possible disciplinary consequences of failure to follow procedure.

2 ~

CP&L has established and implemented review criteria for pre-op procedures to prevent equipment damage due to inadequate procedures.

Specifically the review criteria serve to verify proper valve lineup in all main flow paths.

The: review criteriaare.listed.in. Attachment 2 and are implemented as follows'.

a ~

For pre-.op procedures approved prior to June 1,

1985 a

special review was conducted and documented.

The procedures subject to this review were (1),pre-op procedures where the testing was not completed as of July 10, 1985 and (2) pre-op procedures which deal with fluid systems.

Electrical and HVAC pre-op procedures were excluded from this review.

Each of the subject procedures was reviewed by a Start-up Engineer and a

member of the Operations Unit.

The review by the Start-up and Operations Units is documented by a signed form.

This review was completed on July 10, 1985.

b.

For procedures approved after June 1, 1985, the guidance listed in Attachment 2 is to be followed in preparation and review process of all pre-op procedures.

Ho~ever, the completion of the signed form noted above in item a.

is not used for these procedures.

3 ~

In order to strengthen the lines of communication between the Start-up Engineers performing testing and the Operations personnel on shift, a Shift Test Engineer (STE) is assigned to each shift when significant pre-op testing is being conducted on safety-related equipment as determined by the Manager Startup.

The STE is stationed in the Main Control Room.

The specific duties and responsibilities of the STE are defined in written guidelines developed and approved by the Manager-Operations and the Manager-Startup.

Date. When Full Com liance Was Achieved:

Full compliance was achieved on July 10, 1985.

(

eL p gx a ~ r

",ed

Attachment 2

Preoperational Test Procedure Review Criteria 1.

Procedure will accomplish stated test objectives.

2.

Valve line up is correct; all manual and remotely operated valves are included.

3.

Proper valve line up or verification is provided in the event that procedure steps may be performed out of order.

4.

The flow or flow path through rotating or other critical machinery 1'.

established as specified by valid technical references prior to operation b.

confirmed by verifying manual valve alignment prior to operation c..

verified immediately after placing in service 5.

In the event that valves are manipulated after equipment is secured all subsequent system operations account for the changed positions.