ML18019A296

From kanterella
Jump to navigation Jump to search
Insp Rept 50-400/85-24 on 850520-0620.Violation Noted: Failure to Conduct Preoperational Tests in Accordance W/ Procedural Requirements
ML18019A296
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 06/27/1985
From: Burris S, Fredrickson P, Maxwell G, Prevatte R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML18019A294 List:
References
50-400-85-24, NUDOCS 8508080086
Download: ML18019A296 (21)


See also: IR 05000400/1985024

Text

~

~R RK0y

P0

Cy

I

ClO

I

0

I

/p ++**+

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTASTREET, N.W.

ATLANTA,GEORGIA 30323

Report No.:

50-400/85-24

Licensee:

Ca'rolina

Power and Light Company

P. 0.

Box 1551

Raleigh,

NC

27602

Docket No.:

50-400

Facility Name:

Harris Unit

1

Inspection

Conducted:

May 20

June

20,

1985

License No.:

CPPR-158

Inspectors:

G.

. Maxwell

Date Signed

R.

. Prevatte

Date Signed

S.

P. Burris

Approved by:

P. Fredrickson,

Sectio

ief

Division of Reactor Projects

Date Signed

Date Signed

SUMMARY

lr

Scope:

This routine,

announced

inspection

involved 344 (resident)

inspector-

hours

on site

in the

areas

of licensee

action

on previous

enforcement

items;

inspector

followup items;

licensee

identified

items;

pipe

hangers;

heating,

ventilation

and

air conditioning;

electrical;

nonconformance

control; fire

prevention/protection;

storage;

instrumentation

and control; preoperational

test

program implementation verification and independent

inspection.

Results:

Of the

12 areas

inspected,

no violations or deviations

were identified

in 11 areas;

one violation was found in one area (violation "Failure to conduct

preoperational

tests

in accordance

with procedural

requirements",

identified in

the details Section

13.2 of the report).

No apparent

deviations

were found.

8808080086

850628

PDR

- ADOCN, 05000400

8

PDR

II

1

I

I

I

REPORT DETAILS

Persons

Contacted

Licensee

Employees

"R. A. Watson,

Vice President,

Harris Nuclear Project

G. A. Myer, General

Manager,

Milestone Completion

C.

C. Wagoner,

Project General

Manager,

Construction

"J.

L. Willis, Plant General

Manager,

Operations

"E. J.

Wagner,

Manager,

Engineering

J.

L. Harness,

Assistant Plant General

Manager,

Op'erations

"L. I. Loflin, Manager, Harris Plant Engineering

Support

M. Thompson, Jr.,

Manager,

Engineering

Management

B.

Van Metre, Manager, Harris Plant Maintenance

  • N. J. Chiangi,

Manager,

QA/QC Harris Plant

"C.

S. Hinnant,

Manager, Start-up

J.

M. Collins, Manager,

Operations

"A. H. Rager,

Manager,

Construction

Inspection

G.

L. Forehand,

Director,

QA/QC

C.

S.

Bohanan,

Director, Regulatory

Compliance

  • M. D. Vernon, Superintendent,

QC

  • D. A. McGaw, Superintendent,

QA

Other

licensee

employees

contacted

included

22 construction

craftsmen,

11 technicians,

28 operators,

eight mechanics,

11 security

force

members,

and ten engineering

personnel.

  • Attended exit interview

Exit Interview

The inspection

scope

and findings were

summarized

on June

21,

1985, with

those

persons

indicated

in paragraph

1

above.

No written material

was

provided to the

licensee

by the resident .inspectors

during this reporting

period.

The licensee

did not identify as proprietary

any of the materials

provided to or reviewed

by the resident

inspectors

during this inspection.

The violation identified in this report

has

been

discussed

in detail with

the licensee.

The licensee

provided

no dissenting

information at the exit

meeting.

Licensee Action on Previous

Enforcement

Items

(92702)

(Closed)

Violation 400/83-37-01

"Failure to Control Electrical

Cable

Installation".

The inspector

evaluated

CP&L's responses

to Region II

dated

March 16,

1984, August 24,

1984,

and April 12,

1985.

CP&L issued

design criteria to remove previously installed adhesive

backed

supports

t

I

I

l

and

prevent their

use

in future installations.

Additional training

was held for craft

and inspection

personnel

to, prevent

use

on other

equipment

in

further

applications.

Follow-up

inspections

by

the

resident

inspector indicate that this problem

has

been corrected.

This

item will be routinely evaluated

as

a part of the

ongoing inspection

program.

This item is closed.

b.

(Closed)

Violation 400/83-22-01

"Failure to

Comply with Procurement

Requirements".

The inspector

evaluated

the

program outlined in

CPRL

letter to

Region II dated

September

2,

1983

and

CP&L information

letters

providing directions

to

those

required

to

take

corrective

steps.

During the weeks of May 13 and

May 20,

1985,

CPhL

QA conducted

an

in-depth

evaluation

of the

special

Inservice

Inspection

Program

(ISI) which has

been

established

to

assure

that

the

inspection

and

rework,

as

applicable,

of the

estimated

3000

weld joints

has

been

completed.

QA personnel

documented

the results of their evaluation

in

Surveillance

Report

numbered

QASC 85-907.

The inspector

observed

the

in-process

activities

of the

QA in-depth

evaluation

and

reviewed

Surveillance

Report

QASC

85-907 .

The inspector

determined

that the

special

ISI program

has

been

implemented

and

has identified those weld

joints which require special

inspections

and repairs.

The program

has

been

completed

on approximately

90 percent of the estimated

3000 joints

which require inspection,

with reasonable

assurance

that the remaining

welds will be

inspected

and

repaired

satisfactorily.

This

item is

closed.

4

Inspector

Followup Item (92701)

(Closed)

Inspector

Follow-up

Item 400/84-49-04

"ITE Gould

Motor Control

Center

Mechanical

Interlock Deficiencies".

This item was also reported

by

CPRL

as

a

10CFR 50.55(e)

item

400/CDR85-204

"Motor Starter-Mechanical

Vertical Interlock Binding".

The

closure

of this

item is discussed

in

paragraph

S.e.

This item is closed.

5.

Licensee Identified Items

(92700)

Prior to this inspection

period,

the licensee

had identified the following

items under

10CFR 50.55(e):

a.

(Closed)

400/CDR82-106

"480V Switchgear

Design

Deficiency of the

Secondary

Di sconnects".

On

November

12,

1982,

the

licensee

notified

Region II of

a

10CFR 50.55(e)

item concerning

possible

binding which

could result in breakage

of finger contacts

on the

secondary

discon-

nects for Brown-Bouveri class

1E 480V switchgear.

This defect

had been

identified in older designs

that were manufactured

with rectangular

tabs that hold the contact strips in place

and contain

a

small cutout

in the

contact strip.

When

the

breaker

is

racked

out the finger

contacts

could get caught

behind

the rectangular

tabs

and result in

breaking off of the contacts.

This would result in loss of control

circuitry.

The final report to Region II was

submitted

on April 29,

1983.

3

b.

c

~

The reports

have

been

reviewed

and

determined

to

be

acceptable

by

Region II.

The resident

inspector

has

reviewed all reports

and

the

"closed"

Deficiency

and

Disposition

Report

(DDR)

on this

item.

A

Brown-Bouveri

representative

changed

all

these

components

onsite

on

April

21

and

22,

1983.

CPS L provided

engineering

assistance

and

quality control coverage of these activities.

The inspector

completed

a

sample

audit

on six of the

51 components

replaced.

No deficiencies

were identified during thi s audit.

This item is closed.

(Closed)

400/CDR84-168

"6.9KV

Switchgear

Circuit

Breakers".

On

March 26,

1984,

the licensee

notified Region II of

a

10 CFR 50.55(e)

item

concerning

incorrect

functioning

of the trip circuitry for

Siemans-Allis

switchgear circuit breakers.

This deficiency resulted

from the

interface

of

EBASCO wiring

standards

with Siemans-Allis

wiring.

The

EBASCO standard

practice is to monitor the trip coil with

the circuit breaker

in both the

open

and closed position.

Monitoring

the trip coil with the breaker in the open position allowed sufficient

current flow through the indicator lights to keep the trip coil in

an

energized

state.

This .current flow would prevent

breaker

operation.

Corrective action required

the rewiring of the control circuitry to

eliminate

the current

path

through

the trip coil

when the breaker is

open.

The final report

on this item was

submitted to Region II on

November

8,

1984.

The reports

have

been

reviewed

and determined to be

acceptable

by Region II.

The inspector

reviewed applicable

supporting

documentation

and

observed

a representative

sample

of the

work to

verify that corrective

actions

identified in the

report

have

been

completed.

This item is closed.

(Closed)

400/CDR84-176 "Electric Cables-Hi-Pot Test Failure".

On March

25,

1984 the

licensee

notified Region II of

a

10 CFR 50.55(e)

item

concerning Hi-Pot test failure of two cables that

had previously passed

the site required

megger test.

This Hi-Pot test

was

not required

by

site

procedures.

Corrective

action

required

replacement

of both

cables.

The licensee additionally performed

a Hi-Pot test

on all

500

MCM power

cables

previously installed

and other selected

safety

and

nonsafety

600V power cables.

Applicable procedural

changes

have

been

implemented

to prevent

total

reliance

on

megger

readings

for cable

acceptability.

The final report

on this item was

submitted

to Region

II on

December

12,

1984.

The report

has

been

reviewed

and determined

to

be acceptable

by Region II.

The

inspector

held discussions

with

responsible

licensee

representatives,

reviewed supporting documentation

and

observed

representative

samples

of work to verify that

the

corrective actions identified in the report

had

been

completed.

This

item is closed.

d.

(Closed)

400/CDR84-186

"Siemans-Allis 6.9KV Cubicle with Bent Terminal

Lugs

and Chaffed Wire".

On September

7,

1984,

the licensee

notified

Region II of a

10 CFR 50.55(e)

item concerning chaffed wiring and bent

terminal

lugs in the Siemans-Allis

6.9KV switchgear.

This problem was

a result of inadequate

clearances

between

the

sides

of the circuit

breakers

and the

switchgear

cubicles.

Corrective action resulted

in

reworking of the internal wiring and

replacement

of the affected

lugs

by

a

vendor

representative.

This work was monitored

by

CPKL QA/QC

personnel.

The final report

on this item was

submitted

to Region II

on

February

14,

1985.

The report

has

been

reviewed

and

determined

acceptable

by

Region II.

The resident

inspector

has

reviewed

all

supporting

documentation,

held discussions

with responsible

licensee

personnel,

and observed

representative

samples

of work to verify that

the corrective

actions identified in the report

have

been

completed.

This item is closed.

(Closed)

400/CDR85-204

"Motor Starter-Mechanical

Vertical Interlock

Binding".

On January

22,

1985,

the licensee

notified Region II of

a

10 CFR 50.55(e)

item

concerning

motor starter

mechanical

vertical

interlock binding for

two special

starters

supplied

by Gould,

Inc.

This defect

was

found in eight containment

fan cooler starters

which

could

have

prevented

the required transfer

between

high and low speed

operation.

Corrective

action

resulted

in rework of these

starters

to

an

improved design

developed

by Gould,

Inc.

The rework

has

been

performed

by

a vendor representative

in accordance

with Field

Change

Request

(FCR)

E-3883.

This

work was monitored

by

CP&L Construction

Inspection (CI) personnel.

The final report

on this item was submitted

to

Region II on April 12,

1985.

The report

has

been

reviewed

and

determined

acceptable

by

Region II.

The

resident

inspector

has

reviewed all

supporting

documentation,

held discussions

with respon-

sible licensee

personnel

and

observed

a representative

sample

of the

work to verify that the corrective action identified in the report

has

been

completed.

This item is closed.

Pipe Hangers

(50090C

and 92706B)

The

inspector,

assisted

by

CI

and

QC welding

inspection

personnel,

conducted

an inspection

on eight pipe hangers,

identified as:

1AF-H-

329,

1AF-H-353,

1AF-H-383,

1AF-H-229,

1AF-H-337,

1AF-H-23,

1AF-H-241,

and

1AF-H-2.

The

wor k, inspection

and documentation

review

had

been

completed

on these

hangers

and the packages

had

been

placed

in the

QA

vault.

The inspection

included the following:

(1)

Location and elevation;

(2)

Material identification;

(3)

Catalog parts;

(4)

Strut/snubber

assembly installation;

(5)

Orientation,

geometry

and clearance

requirements;

(6)

Installation

and torquing of fasteners;

(7)

Attachments;

(8)

Physical integrity of hanger;

(9)

Welding identification and location were

as specified;

(10)

Welding

procedure

specifications

adhered

to the requirements

of

ASME Section

IX and

AWS D. 1. 1 for hangers;

'

(11)

Adherence to drawings

and inspection

procedures;

(12)

gualification of inspection

personnel;

and

(13)

Documentation of nonconforming. conditions.

No violations or deviations

were identified in the areas

inspected.

7.

Heating, Ventilation

and Air Conditioning Systems

(HVAC)

(50100)

The

inspector,

as

a part of the

inspection

of ongoing

work activities

associated

with the installation of HVAC systems,

observed

the leak testing

being

performed

on

HVAC

package

HVAC-T-15C-1 for

RFT

8210-004.

The

inspector

observed

that

leaks

were

being repaired

at duct flanges

using

TREMCO

440

tape

to

seal

between

the

flanges.

Discussions

with

the

applicable Harris Plant Engineering Staff (HPES) indicate that this material

is

specified

in

EBASCO specification

B-E04A.

The

resident

inspector

requested

that the

environmental

qualification report for this material

be

provided for review.

HPES provided preliminary data

and

stated

that

the

final qualification for this material

had not been

received

by

EBASCO or

HPES.

Pending

review of the final qualification of this material for its

suitability for

use

under

elevated

temperature,

moisture

and

radiation

environmental

conditions, this item will be identified as

an Unresolved

Item

"Environmental gualification of

TREMCO 440

Tape"

400/85-24-02.

No viola-

tions or deviations

were identified.

8.

Electrical

(51053C,

51063C,

927068)

a.

The

inspector

accompanied

construction

inspection

personnel

on

an

inspection

of completed

electrical

conduit

15436G-SB

in the reactor

containment building.

The inspection

covered

the following:

(1)

Conduit location, routing, size

and identification;

(2)

Torquing of fasteners;

(3)

Bending radius;

(4)

Couplings, fittings and grounding;

(5)

Interferences;

(6)

Supports;

(7)

Separation

requirements;

I

(8)

Adherence

to drawings,

specifications

and procedures;

(9)

gualification of inspection

personnel;

(10) Documentation of inspection results

and nonconforming

conditions.

b.

The

inspectors

observed

the installation activities

associated

with

Class

1E cables

with the following numbers:

12964G-SA

and

12967G-SA.

These observations

related to cable pulling and termination

and various

switchgear

and

cabinets.

The following were evaluated

during these

observations:

(1)

The latest termination cards

were in use;

(2)

The size

and type cable

was correct;

(3)

The

cable

identification

(cable

number

and

color

code)

was

correct;

(4)

The correct bending radius

was applied;

(5)

The cable routing was correct;

(6)

The cables

were protected

from damage;

(7)

gualified electrical

inspection

personnel

were monitoring the

installation activities;

(8)

Approved drawings

and specifications

were being used;

(9)

Approved materials

were being used;

(10) Cleanl iness;

(11) Calibration of tools and instruments;

(12) Approved work and inspection

procedures

were being used;

(13) Documentation of inspections

and nonconformances.

No violations or deviations

were identified in the areas

inspected.

9.

Nonconformance

Control

(92706B)

The inspector

reviewed

the

nonconformance

control

log and

reviewed

closed

nonconformances:

85-1320,

85-0851,

85-1085,

85-0852,

85-1249

and 85-0516.

This

sample

of six closed

nonconformances

was

reviewed to determine

the

following:

a.

Adequacy of identification of nonconformances;

b.

Proper review and evaluations;

c.

Correct disposition

and details;

d.

Verification, acceptance

and review of disposition;

e.

Performance

of reinspections;

f.

Adequacy of corrective action

and prevention

measures, if required;

g.

Proper final review and closeout.

No violations or deviations

were noted in the areas

inspected.

10.

Fire Prevention/Protection

(42051C,

92706B)

a.

The inspectors

observed

the fire prevention

and protection activities

related to containing combustible materials

where the ignition of these

materials

could damage

safety-related

structures.

The inspectors

also

observed

the ongoing site training activities for the construction fire

brigade.

b.

Some

of the specific

areas

observed

by the

inspectors

during this

period were:

(1)

Nonflammable protective

coverings

were

observed

over

such equip-

ment as the electrical control cabinets

at elevation 286'f the

reactor

auxiliary building and over various safety-related

pumps

and components

located throughout the plant.

(2)

The inspectors

observed

during the various tour s of the reactor

auxiliary building and the containment building that the accumula-

tion of combustible materials

in these

areas

was being minimized.

(3)

Flammable

materials

were

stored to prevent

or reduce

the likeli-

hood of combustion.

(4)

Melding activities were observed

in at least

15 separate

locations

throughout

the site

and

in each

instance it was

observed

that

appropriate

fire extinguishing

equipment

was

available

within

close

proximity of the

welding activities.

It was

also

noted

that

the

portable fire extingui shers

contained

sufficient fire

extinguishing

medium,

as

evidenced

by displaying current

inspec-

tion stickers and'aving

unbroken

seals.

(5)

The inspectors

observed that at the various elevations

throughout

the reactor auxiliary building and the containment building, fire

suppression

devices

are strategically

located

and readily avai 1-

able for use.

c.

A review of the fire brigade drill and training records

showed that

drills

and training

are

conducted

on

a regular

basis

for the fire

brigade

members.

During the

above

observations,

the following were referenced

for requi re-

ments:

FSAR Section

1.8

and 9.5;

Regulatory

Guide 1.39,

NFPA Standard

241

and AP-VII-03 (Exhibits 2,

3 and 4).

No violations or deviations

were noted in the areas

inspected.

ll.

Storage

(50073C,

92706B)

The inspector

toured

warehouses

1,

2

and

3,

the operations

warehouse,

and

various

plant

equipment

storage

areas.

During

the tours,

the

storage

conditions of the equipment

were evaluated

to determine

whether requirements

are being met as follows:

a.

Piping and equipment,

in general,

were stored off the ground or floors

to prevent entry of dirt into them, or contamination

from environmental

conditions.

b.

The storage

areas

were identified sufficiently to provide identity and

locations

as

required

by those

who

may

be

seeking

the

locations

of

parts

or equipment.

c.

Access

was adequate

for placement

or removal of parts

and equipment.

d.

Warehouse

equipment

was stored in the correct position.

e.

The

temperature

and

humidity

controls

were

being

maintained

as

required.

f.

Access to plant storage

areas

was being maintained.

g.

Equipment installed heaters

were energized

as required.

h.

Protective

covers

were in place.

During the

observations,

the

following were referenced

for requirements:

PSAR Section 1.8,

and construction

procedures

AP-XIII-07 and

PGD-002.

No violations or deviations

were identified in the areas

inspected.

12.

Instrumentation

and Control

(52053C)

The

inspector

accompanied

Construction

Inspection

(CI) personnel

on

an

inspection

of the installation

of flow transmitter

FT-01RC-0425IIW;

the

associated

instrument

impulse lines;

tube track

and supports

W-S-l, W-S-2,

W-S-3,

F-5-4,

F-5-5,

W-S-6,

W-S-7,

and

W-S-8 in the

reactor

containment

building.

The inspection

included the following:

a.

Instrument location, identification and mounting;

b.

Use of correct materials;

c.

Torquing of fasteners;

d.

Tubing installation;

e.

Physical integrity;

f.

Adherence

to drawings, specifications

and procedures;

g.

gualification of inspection

personnel;

h.

Documentation of inspection results

and nonconforming conditions;

i.

Clearances,

as specified;

j.

Apparent

damage.

During the

above

observations,

the following were referenced

for require-

ments:

FSAR Section

1.8;

construction

work procedures

WP-300,

WP-302,

WP-304,

WP-305;

construction

inspection

procedures

TP-54,

TP-67;

and

construction

drawings

and specifications

CAR-2166-8-431

and CAR-SH-IN.

No violations or deviations

were noted in the areas

inspected.

13.

Preoperational

Test Program Implementation Verification (71302)

a.

During

the

week

of

May 20,

1985,

CP&L conducted

portions

of the

preoperational

performance

and flow balance

testing for the high-head

safety injection

pumps.

The test

procedure

is

numbered

1-2080-P01.

10

The high-head

safety injection

system utilizes the charging

pumps

as

the driving force during an anticipated

accident condition.

Steps

6.4,

6.6,

6.7, 6.8,

6.9,

6.10

and

6.11 of procedure

1-2080-P01

require

repositioning

the

manual

suction

and discharge

valves to each

of the charging

pumps

~

On

May 25,

1985, after completion of tests

on charging

pump

1A (step

6. 12

in

the

procedure),

the

start-up

test

engineer

directed

the

auxiliary operator to 'close the manually-operated

suction

and discharge

valves for pump

1A.

Closing

these

valves

was

not in accordance

with

the requirements

of the procedure.

To deviate

from the preoperational

test procedure,

the start-up engineer is required to obtain

an approved

temporary

change

notice in accordance

with the Start-up Manual, section

7.6.2.

The start-up

engineer

had not obtained prior approval to close

the charging

pump

manual

isolation

valves.

Subsequent

operation

of

charging

pump

1A, with the

manually-operated

suction

and

discharge

valves

closed,

resulted

in

pump failure.

CP&L start-up

personnel

documented

the failure of the charging

pump

on

a Nonconformance

Report

numbered

NCR-85-1471.

The inspectors

were informed by responsible

CP&L

management

personnel

that

other conditions

contributed

to

the

pump

failure:

(1)

The

start-up

engineer

should

have

obtained

proper authorization

prior to implementing test changes.

(2)

The closing of the manually-operated

valves

was not communicated

to the control

room.

(3)

Test

personnel

failed

to follow the

general

requirements

of

procedure

OP-107,

which requires verification of

pump flow path

prior to starting

a

charging

pump.

Also,

involved

personnel

failed to follow the

requirements

of

a

caution

tag

which

was

attached

to the

pump's control

switch.

The caution

tag

reempha-

sized

the

need

to verify pump flow path prior to starting

the

pump.

The

inspectors

informed

CP&L management

that failure to follow the

requirements

of test procedure

1-2080-P01

and the

CP&L Start-up Manual,

section

7.6.2,

is contrary to

10CFR50,

Appendix

B, Criterion

V;

PSAR

Section

1.8.5.5;

and

CP&L Corporate

QA Program,

section

6.

This is

a

violation "Failure to Conduct Preoperational

Tests

in Accordance

with

Procedural

Requirements"

400/85-24-01.

During the weeks of May 27 and June

3,

1985,

the inspectors

evaluated

the

in-process

preoperational

test

for the

residual

heat

removal

(RHR) system.

This test is identified as 1-2085-P-03,

Low Head

Safety

Injection.

The

inspectors

reviewed this controlled

start-up

11

test procedure

to verify:

that

an approved

procedure

was available

and

in use; test

equipment

being

used

was properly calibrated;

changes

to

the procedure

were

documented

in accordance

with the administrative

procedures,

and personnel

were stationed

and in direct communication

as

required

by the procedure.

The inspectors

witnessed

section

6.5 "Interlock and Operating Differen-

tial Pressure

Check of Containment

Sump to

RHR and

RMST to

RHR Valves",

steps

6.5.9

through

6.5.27,

which verified

motor-operated

valve

operations,

computer

address

points,

pressure

regulated

valve adjust-

ments

and visual verification of these

evolutions.

The

inspectors

verified that test data

were recorded

on the appropriate

data

sheets.

During this inspection,

the inspectors

noted that the test

personnel~

involved with this test

conducted

themselves

in

a professional

manner

and took immediate corrective actions for any identified problems.

The fill and venting of the reactor

coolant

system

(RCS) started

on

June

16,

1985

and concluded

June

20,

1985, in accordance

with procedure

1-2005-0-01.

The

inspectors

reviewed

portions

of thi s procedure

to

ensure that the procedure

had been

approved

and selected

valve lineups

had been verified as to proper valve position requirements.

During the initial fill and venting

sequence,

the licensee identified

that

the

reactor

coolant

pump

seal

areas

for

loops

A and

B were

leaking.

After an inspection

by the licensee,

the

leaks

were

found

to

be located

at the flange

between

the motor

assembly

and

the

pump

casing;

this area

ia sealed

by use of

an installed 0-ring

and

then

torqued to approximately

1000 foot pounds.

The licensee

stopped

the fill and venting of the

RCS,

and depressurized

and drained

the

system

to inspect

these

mating surfaces.

Disassembly

inspection

of the

three

pumps

revealed

that

the 0-rings

were

not

installed.

Therefore,

the only boundary

was from the torque applied by

the flange bolts.

The inspectors will follow-up on this item during

future

inspections

to

determine

the

root

cause

and

review

CP&L's

corrective actions.

This item is identified as

an Inspector

Follow-up

Item 400/85-24-04

"Missing 0-Ring for Reactor

Coolant Pumps".

The

inspectors

conducted

tours

of

the

various

plant

areas.

The

following items were observed

and assessed

during the tours to assure

compliance with requirements:

(1)

The general

condition of the plant's

housekeeping

and the overall

condition of equipment

were observed.

(2)

The plant

was

found to

be free of any major fire hazards.

Fire

extinguishing

equipment

was

readily

available,

and

flammable

materials

were

being

protected

from ignition sources

and

were

being

controlled

in

accordance

with

site

administrative

procedures.

c

12

(3)

The

inspectors

observed

electrical

personnel

placing

cables

in

their respective

cable trays

and conduits.

Sufficient care

was

being taken to prevent

damage

to the cables

being

placed

and to

cables

which had already

been installed.

(4)

The

inspectors

looked for uncontrolled

openings

in previously

cleaned

or flushed

systems

or components.

Where

system

openings

were

identified,

cleanliness

controls

were

established

duri ng

flushing.

I

(5)

The inspectors

observed

one instance

in which electrical

personnel

were working on electrical

equipment which had already

been turned

over to the start-up

group.

The work was being accomplished

under

the

proper

admi ni strati ve

contr ol s

pr ovided

i n

the

Start-up

Manual .

~ e.

The

inspectors

observed

operations

personnel

deenergizing

electrical

components

as required

by the clearance

program

when equipment is being

placed out of commission for repairs,

tests

or rework.

f.

The

inspectors

observed

the

status

of the

plant

being

correctly

identified in the control

room

by operations

personnel.

The roving

operators

were making frequent tours of the various buildings and were

maintaining adequate

control of plant systems

and equipment.

g.

The

inspectors

reviewed

log

books

maintained

by the test

group

to

identify problems

or plant activities that

may

be

appropriate

for

additional follow-up.

Except

as

noted,

no violations or deviations

were identified in the areas

inspected.

14.

.Independent

Inspection - Operations

(92706

and 42400B)

e

During the

weeks of June

3 and June

10,

1985,

the inspectors

reviewed

the licensee's

action with respect

to IE Information Notice No. 85-16,

"Time/Current Trip Curve

Discrepancy

of ITE/Siemens-Allis

Molded

Case

Circuit

Breaker".

This

IEN

described

a

potentially

significant

discrepancy

pertaining to HE-3-M040 breakers.

The inspectors

reviewed

documents

which indicated

that

a

CP5L on-site

nuclear

safety

review

group

study

had

indicated

that

ITE/Siemens-Allis

type

HE3 circuit

breakers

were not used at the Harris Plant.

The inspectors

toured the

diesel

generator building and observed that the class

1E motor control

centers

(MCCs) for the

emergency

diesel

generators

contain

the

ITE

type

HE3 circuit breakers.

The inspectors

evaluated

the

procurement

documents

and

the

documentation

provided

by

the

supplier

of the

emergency

diesel

generator

MCCs.

The

responsible

maintenance

and

start-up

personnel

were

interviewed

and

asked if CP&L planned

to

conduct

any tests

to determine if the type

HE3 circuit breakers

have

been adjusted

to trip at the prescribed

setpoints

~

l

13

The inspectors

were

informed by

CP&L procurement

personnel

that there

were

no test results

supplied

by the

MCC manufacturer

to verify proper

overload trip tests

for these

type

HE3 circuit breakers.

Interviews

with start-up

and maintenance

personnel

revealed

that there

have

been

no provisions

made to require testing the overload settings

on the site

electrical

systems

which contain

the

HE3 circuit breakers,

other

than

those required

by the proposed site technical

specifications.

CP&L is

currently

reviewing

the

extent

of

use

and

the

need

for

additional

testing of 'HE3 circuit breakers

at Harris.

The inspector

informed

CP&L management

that this

apparent

failure to identify

a

condition

adverse

to quality is

an

unresolved

item

pending

NRC

evaluation of the licensee's

review and is identified as "Overload Trip

Setpoints for ITE Type

HE3-M040 Molded

Case Circuit Breakers"

400/85-

24-03.

b.

During this

inspection

period,

the

inspectors

toured

the

emergency

diesel

generator

buildings

to

observe

ongoing activities to

ensure

compliance

with

NRC requirements

and

FSAR commitments.

Housekeeping

activities

were

adequate

for all

areas

inspected

and

sensitive

components

were

covered

as

necessary

to

prevent

contamination

by

airborne dust.

The inspectors

obtained

selected

diesel

generator

test

procedures

for review prior to the

licensee's

conducting

of these

specific tests,

which were scheduled

to commence during this inspection

period.

c.

During the

week of June

10,

1985, the inspectors

observed

the lifting

and installation of the reactor vessel

head.

The following attributes

were evaluated

while observing work activities:

(1)

The vessel

head "0" ring grooves

were verified for cleanness;

(2)

The overhead lifting hook was cleaned,

tested

and inspected;

(3)

The responsible

craft

and inspection

personnel

were cognizant of

the applicable

procedural

requirements.

No violations or deviations

were identified in the areas

inspected.