ML18018B841

From kanterella
Jump to navigation Jump to search
Forwards Const Appraisal Team Insp Rept 50-400/84-41 on 841022-1102 & List of Potential Enforcement Actions Re Hardware Deficiencies Noted
ML18018B841
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 12/24/1984
From: Deyoung R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE)
To: Utley E
CAROLINA POWER & LIGHT CO.
Shared Package
ML18018B842 List:
References
NUDOCS 8501080559
Download: ML18018B841 (10)


See also: IR 05000400/1984041

Text

e

~8 ~<oII

c~

0

Cy

- ~i

C

~

Cl

.4-

4

Cy

~O

ky*y4

UNITEDSTATES

NUCLEAR REGULATORY COMMISSION

WASHINGTON. O. C 20555

December, 24,

1984

Oocket

No. 50-400

Carolina

Power and Light Company

ATTN:

Mr. E.

E. Utley

Executive Vice President

Power Supply .and Engineering

and Construction

P.O.

Box 1551

Raleigh, North Carolina

27602'entlemen:

SUBJECT:

Construction Appraisal

Team Inspection 50-400/84-41

Enclosed is the report of the Construction Appraisal

Team

(CAT) inspection

conducted

by the Office of Inspection

and Enforcement (IE) on October 1-12

and October

22 - November 2, 1984, at the Shearon Harris Unit 1 site.

The

Construction Appraisal

Team was

composed of members of IE,

NRC Region II,

and

a number of consultants.

The inspection

covered construction activities

authorized

by

NRC Construction Permit CPPR-158..

This inspection is the ninth of a planned series of construction appraisal

inspections

by the Office of Inspection

and Enforcement.

The results of these

inspections

are being used to evaluate

the management

control of construction

activities and the quality of construction at nuclear plants.

The enclosed report identifies the areas

examined during the inspection.

Mithin the areas,

the effort consisted primarily of detailed inspection of

selected

hardware

subsequent

to guality Control inspections,

a review of .

selected

portions of your guality Assurance

Program,

examination of procedures

and records,. observation of work activities,

and

an examination of your project

'management.

Appendix A to this letter is an Executive

Summary of the resu1ts

of this

inspection

and of conclusions

reached

by this'office.

Hardware

and

documentation for the construction

areas

reviewed were generally

found to be

in accordance

with requirements

and commitments.

However,

hardware deficien-

cies were noted by the

NRC CAT in several

areas that will require additional

management

attention.

These

areas

include examples

of lack of required design

input for maintaining electrical separation,

non-seismic installations

in

proximity to seismic Category I hardware,

and incorrect placement of concrete

reinforcing steel.

December

24

1984

~

~

c3

Carolina

Power and Light Company

\\

e

Of concern to the

NRC CAT inspectors

were several

areas 'in which CP8L failed to

'address

significant problems in a timely manner.

Examples of areas

where this

'as

evident included the determination of the adequacy of non-seismic instal-

lations ovey..Seismic

Category I items

and pipe-to-pipe clearances.

The

NRC CAT

notes that heavy dependence

on walkdowns or engineering

evaluations

to iden-

tify and resolve problems late in construction

has not been successful

at other

facilities and should not be relied upon at Shearon Harris.

The

NRC team observed that there

was evidence of good project management

and

construction practices at the Shearon

Harris site.

. These

good practices

include

a capable project management

organization

.the fact that site engineer

ing and inspection activities are primarily located

and controlled on-site

and

the extensive

use of field engineers

for problem resolution.

e

Appendix

B to this 'letter contains a'list of potential

enforcement

actions

based

on the 'NRC CAT inspection observations.

These are being reviewed by the

Office of Inspection

and Enforcement

and the

NRC Region II Office for appro-

priate action.

In addition,

Region IE will be following your corrective action

for deficiencies identified during this inspection.

In accordance

with 10 CFR 2.790(a) a copy of this letter and the enclosures

are being placed in the, Public Gocument

Room.

No reply to this letter is

required at this time.

However, you will be required to respond

to these

findings, including your plan and schedule for corrective actions, after a

decision is made regarding appropriate

enforcement action.

. Should you have any questions

concerning this inspection,

please

contact

us or

the Region II Office.

Sincer ely,

Richard C./be oung,

0

c or

Office of Qn pection and Enforcement

Encl osures:

1.

Appendix

A - Executive

Summary

2.

Appendix

B - Potential

Enforcement Actions

3.

Inspection

Report

cc w/enclosures;

See next page

December

24

1984

Carolina Power and Light Company

3

'

cc w/enclosures:

p

~

R.

A. Watson,

Vice President

Harris Nuclear Project

Carolina Power and Light Company

P.O.

Box 165

New Hill, NC

27562

R.

M. Parsons,

Completion Assurance

Manager

Carolina Power and Light Company

P.O.

Box

1.01

New Hill, NC

27562

'

t

J

h

ro

~

~

n

APPENDIX A

EXECUTIVE SUMMARY

An announced

Construction Appraisal

Team

(CAT) inspection

was conducted at the

Shearon Harris site during the period October 1-12 and October

22 - November

2, 1984.

Overall Conclusions

Hardware

and documentation for piping, pipe supports/restraints,

HVAC,

structural

steel

(including welding and nondestructive

examination in these

areas)

and

dams

and dikes were generally found to be in accordance

with

requirements

and commitments.

However, the team did identify the following

construction

program weaknesses

that require management

attention:

~

~

1. 'onflicts were identified between

design inputs

and

FSAR commitments

with regard to electrical cable

and raceway separation

which resulted

in separation

deficiencies.

2.

Hardware discrepancies

were found in non-seismic

items installed over

Seismic Category I items.

Failure of these discrepant

non-seismic

.items could adversely affect Class

1E electrical

components.

3.

Deficiencies identified in the area of interdisciplinary and pipe to

pipe clearances

indicated that the"-identification and resolution of

these

interferences

were not being effectively addressed.

The

NRC CAT team considered

the direct involvement and control

by CP8L in

design engineering

and the extensive

use of field engineers

to identify and

resolve problems to be positive aspects

of the Shearon

Harris const uction

program.

Electrical

and Instrumentation

The majority of the electrical

and instrumentation

samples

examined

met the

appropriate

design

and construction

requirements.

The applicant

s program for

inspection of construction activities and maintenance

of Class

1E electrical

equipment appears

to be effective.

Construction

and design deficiencies

were

identified in several

areas

including some items which will require additional

NRC review..

Some design

documents,

which specify separation

c~-teria for electrical

raceway installation, deviate

from FSAR commitments.

As a result,

numerous

installations'xist

where the required separation

between

Non-Class

1E and

Class

1E raceway

components

have not been maintained.

Because of numerous identified hardware deficiencies

in non-seismic

raceway

supports, their. possible failure.may adversely affect the ability of nearby

Class lE electrical components'o'erform

intended safety functions.

The corrective actions

being taken

by the applicant concerning

problems associ-

ated with instrumentation

appear to be adquate

although final actions

and

approvals

were not completed-at--the--time-of

the

NRC CAT i'nspection.

Mechanical

Construction

Piping, pipe supports/restraints,

concrete

expansion

anchors

and

HYAC supports/

restraints

were generally

found to be in accordance

with applicable

drawings

and

requirements.

Oiscrepancies

were identified with mechanical

equipment founda-

tion fasteners

and sliding end installations.

Noted deficiencies of undersized

wall thickness

in field purchased

piping indicates that the inspection

and

surveillance effort in this area requires

increased

management

attention.

Programmatic

concerns

were noted in two areas:

(1) lack of verification of

piping and pipe support/restraint

location to original design requirements

and,

(2) lack of an ongoing program to effectively identify and resolve

hardware

clearance

problems early in the construction process.

Both of these

concerns

involve practices that could result. in extensive

inspection,

analyses

and

rework efforts very late in the construction

schedule.

Weldin

and Nondestructive

Examination

Melding and nondestructive

examination activities were generally found to be

conducted in accordance

with the .governing codes

and specifications.

Few

deficiencies

were identified by the

NRC CAT inspectors

in this area.

However,

a number- of examples

were identified where vendor supplied tanks did not meet

the design requirements

for nozzle to shell weld reinforcement,

and

some of

the. tanks support welds were undersized.

In the area of NOE, several

irregular-

ities involving film quality were identified

However, the finished welds were

found to be acceptable.

Civil and Structural Construction

Construction quality and concrete material certification were in general

found

'to be acceptable.

However, three areas

were identified where the reinforcing

steel

had not been placed in accordance

with the design drawings.

.An area of improper concrete consolidation

was identified in one of the

beams

in the Reactor Auxiliary Building.

After chipping out the concrete in this

area,

a void was identified above the

embedded plate

and

one layer of the

bottom reinforcement

lapped at this location was placed to one side of the

beam

instead of being distributed across

the bottom of the

beam.

A number of non-seismic electrical

system

components

located 'over seismically

qualified

systems'

-w ich are supported

by unmarked concrete

expansion bolts were

identified.

Subsequent

ultrasonic testing indicated that the anchor bolt

embedment

lengths

were 'as low as

1< inches.

Also, tension

and shear tests

performed by CPEL personnel

indicate that the factors of safety are approxi-

mately 50K of recommended

values.

A-2

Material Traceabil it

and Controls

In general,

the project. material traceability and control program was found to.-

be acceptable.

Problems

were identified regarding traceabil ity of fastener

materials,

including large anchor bolts and equipment mounting bolts

and nuts.

It was noted that both the applicant

and the

NRC Region II had previously

identified such deficiencies

and corrective actions

were in progress

by the

applicant.

Desi

n Chan

e Control

Design change control, including control of changes

to design

documents,

was

determined to be generally in conformance with applicable

requirements.

A

number of minor, non-generic

discrepancies

were identified,

none of which are

considered significant.

In the area of document

change control, the most

significant finding was the numerous

unincorporated

changes

affecting many

documents.

The most significant finding in the area of design

change control

is that

some analyses

and other backup documentation for field changes

.have not

been designated

as quality .assurance

records.

Corrective Action 5 stems

In general

the applicant's

corrective action program

was found to be accept-

able.

However, it was evident that the scope

and quality of audit activities

regarding nondestructive

examination of welding were deficient and should

be improved.

The applicant stated that improvements

were. planned in this .

area.

Pro ect Mana ement

Project Management

personnel

and organization

'appear to be adequate

to assure

that. construction

and startup activities will meet quality requirements.

A-3

f

~

r

I

t

a

0

~

1

'

APPENDIX B

'OTENTIAL ENFORCEMENT ACTIONS.

As a result of the

NRC CAT inspe0tion of October 1-12 and October 22-November

2, 1984, the following items

have

been referred to

NRC Region II as Potential

Enforcement Actions-(section-references- are-tahe -detailed portion of the

inspection report):

1.

Contrary to 10 CFR 50, Appendix B, Criterion III and the

CP8L

SHNPP

FSAR,

Design Control

has not been maintained in ghat the applicant

has failed to

assure that applicable regulatory requirements

for separation

of Class

1E

and Non-Class

lE electrical

raceway

components

are correctly translated

into specifications,

drawings,

procedures

and instructions

(Sections

II.B.1 and II.B.2).

2.

Contrary to 10. CFR 50, appendix

B, Criterion V, the applicanthas

failed

to install reinforcing steel

to the tolerances

shown on the. design

drawing and specifications

in that:

a)

The top reinforcing steel

in beam 55-L-KZ in the Fuel Handling

Building was installed

1~< inch lower than

shown

on the rebar place-

ment. drawing and was not identified during the inspection of the

reinforcing stee'i

placement

(Section V.B.1).

b)

The bottom stee'i

on beam

38 between

column line FZ and the exterior

wall in the Reactor Auxiliary Building was placed

on one side of the

beam instead of being distributed across

the bottom of the

beam

(Section V.B.1).

3.

Contrary to 10 CFR 50, Appendix B, Criterion VII and the Shearon Harris

Plant

FSAR, Chapter 17, the program. for the control of purchased

materials affecting quality was not effectively implemented to assure

that. purchased

piping was in conformance with specified acceptance

criteria and requirements

for pipe wall thickness

(Section III.B.1).

Contrary to 10 CFR 50, Appendix B, Criterion

X and the Shearon Harris

Plant

FSAR, Chapter 17, the program for inspection of activities

affecting quality was not effectively implemented in that inspection

programs did not assure that equipment foundation connections

were

installed in accordance

with specified acceptance

criteria and

requirements

(Section III.B.5).

Cj

~

I.