Notice of Violation from Insp on 801202-05
ML18017B367
Person / Time
Site: Harris  Duke Energy icon.png
Issue date: 02/17/1981
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML18017B363 List:
References
50-400-80-27, 50-401-80-25, 50-402-80-25, 50-403-80-25, NUDOCS 8104220038
Download: ML18017B367 (1)


Text

APPENDIX A NOTICE OF VIOLATION Carolina Power and Light Company Harris 1, 2, 3 and 4 Docket Nos. 50-400, 401,. 402 and 403 Iicense Nos.

CPPR-158,

159, 160 and 161 As a result of the inspection conducted on December 2-5,
1980, and in accordance.

with the Interim Enforcement, Policy, 45 FR 66754 (October-7, 1980), the following violations were identified.

A.

10 CFR 50, Appendix B, Criterion XVI as implemented by CPSL PSAR, Section 1.8.5.16 requires that "Measures shall be established to assure that conditions adverse to quality such. as... deficiencies... are promptly... corrected".

Contrary to the above, measures to assure that conditions adverse to quality such as deficiencies are promptly corrected were not adequately established in. that NRC infraction,400/80-15-02; 401, 402, 403/80-13-02 reported corrected on August 4, 1980, by CPSI letter dated August 19,

1980, was uncorrected on-December 3,--1980.

~

This is a Severity Ievel V Violation (Supplement II.E).

10 CFR 50,, Appendix, B, Criterion V as implemented by CPSL PSAR Section 1.8.5.5'equires that "Activities. affecting quality shall be prescribed by.

documented instructions,, procedures

, Contrary to the above,. activities affecting quality were not prescribed by documented instructions or procedures on December 4, 1980, in that:

(1)

CPK. had no documented. procedural requirement for welder qualification bend test thickness tolerance which resulted in bend test specimens being made significantly-undersize;;

and. (2) CPK had no documented procedural require-ment. for marking'welder qualification bend test specimens which resulted in a loss of control of specimen identity.

This is a,Severity Level VI Violation (Supplement II.F).

Pursuant to'he provisions of 10 CFR 2.201, Carolina Power and Light Company is hereby required to= submit to this office within twenty-five days of the date of this, Notice a written statement or explanation in reply, including:

(1) admission or denial of the-alleged violations; (2) the reasons for the violations if admitted; (3) the corrective steps which have'been taken and the results achieved; (4) corrective. steps which will be taken to avoid further violations; and (5) the date when full compliance will be achieved.

Under the authority of Section 182 of the-Atomic Energy Act of 1954, as-amended, this response shall be submitted under oath or affirmation.

Date, FEB981