ML18017B253

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-400/80-18,50-401/80-16,50-402/80-16 & 50-403/80-16 on 800707-11.Noncompliance Noted:Failure to Follow Procedures Re Housekeeping & Document Control & Weld Matl Control
ML18017B253
Person / Time
Site: Harris  Duke Energy icon.png
Issue date: 08/12/1980
From: Economos N, Herdt A
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML18017B248 List:
References
50-400-80-18, 50-401-80-16, 50-402-80-16, 50-403-80-16, NUDOCS 8010140156
Download: ML18017B253 (10)


See also: IR 05000400/1980018

Text

~S RE'0II

(4

+

0

ly

A.0O

Cy

+~

~O

++*++

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTAST., N.W., SUITE 3100

ATLANTA,GEORGIA 30303

AUG 2 6580

Report Nos. 50-400/79-18,

50-401/79-16,

50-402/79-17

and 50-403/79-16

Licensee:

Carolina Power and I,ight Company

411 Fayetteville Street

Raleigh,

NC

27602

Facility Name:

Shearon Harris Nuclear Plant

Docket Nos. 50-400,

50-401,

50-402

and 50-403

License Nos.

CPPR-158,

CPPR-159,

CPPR-160

and

CPPR-161

Inspection at Shearon

arri

near Raleigh, North Carolina

Inspected

by:

N. Eco

Approved by:

A. R. Herdt, Section Chief,

RC&ES Branch

SUNHARY

Inspection

on July 7-11,

1980

Areas Inspected

Da

Si ned

. 8'la g

Date

igned

This routine

unannounced

inspection

involved

41 inspector-hours

on site in the

areas of steel structures

and supports,

observation of welding activities inside,

and outside containment;

weld material control; pressurizer lift; storage;

main

dam construction activity; other safety-related

piping visual examination of

welds; housekeeping.

Results

Of the eight areas

inspected,

no items of noncompliance

were identified in five

areas;

three items of noncompliance

were identified in three areas (Infraction-

Failure to follow procedures

- housekeeping

storage

and document control, Para-

graph 5.a.; Infraction - weld material control, Paragraph

7; Deficiency - welder

qualification test records,

Paragraph

8.)

8 0 10140/5&'

DETAILS

Persons

Contacted

I,icensee

Employees

-N.

%R

d E

'G

-"V.

D.

>R.

D.

G.

W.

J. Chiangi,

Manager Engineering

6 Construction,

QA

M. Parsons,

Site Manager

E. Willett, Principal Engineer',

Mechanical

L. Forehand,

Principal

QA Specialist

M. Safarian,

QA Welding Specialist

C. Whitehead, Sr.,

QA Specialist Material Control

Hanford, Principal Engineer,

Met./Welding

Sugg, Civil QA

Milner, Civil QA

Mercer, Welding QA

Other licensee

employees

contacted

included construction craftsmen,

and

office personnel.

Other Organizations

Chicago Bridge 8 Iron Company

(CBI)

R. Lerch, Project Superintendent

F.

P. Hazelip, Welding and

QA Superintendent

2.

Daniel Construction

Company (Daniel)

="W. D. Goodman,

Project Manager

+Attended exit interview.

Exit Interview

The inspection

scope

and findings were

summarized

on July ll, 1980, with

those persons

indicated in Paragraph

1 above.

The inspector identified the

areas

inspected

which included steel structures

and supports - observation

of welding activities, welding material control, record review; pressurizer

lift. Three items of noncompliance

were discussed

in detail.

The licensee

concurred with the inspection findings.

'icensee

Action on Previous Inspection Findings

Not inspected.

Unresolved Items

Unresolved items were not identified during this inspection.

,

Independent Inspection Effort

"2"

a

~

Plant Tour

The inspector performed

a general inspection of various work areas

to

observe pipe handling, storage, installation and welding activities in

progress

and to inspect the general state of housekeeping,

cleanliness,

including control of unused

weld electrodes

and

equipment

near

the

working areas.

Within these areas,

the inspector

made the following observations:

(1)

Housekeeping

- On July

7 and 8, 1980, construction debris,

accumu-

lation of water, dirt and trash including soft drink cans,

rags,

empty cups, etc., in excess

amounts

were noted inside

the fuel

handling building, various other areas

of the auxiliary building

and reactor

containment building.

This observation

was discussed

with the licensee

representative

and

immediate action was taken

to correct the situation.

The condition described

above

was contrary to requirements

of

Procedure

AP-VII-06,

Rev.

2,

Appendix A which

requires

that

garbage

trash,

scrap

and other

excess

material ... shall not be

allowed to accumulate

and create

conditions

which may adversely

affect quality.

(2)

Pipe Protection

and Storage - On July 8 and 9, 1980, the inspector

noted

several

instances

where stainless

steel pipe spools

were

improperly stored,

e.g.,

behind

the

fab

shop

and

inside

the

reactor auxiliary building, fabricated

spools

were either resting

in water,

on the

ground

and in one instance,

several fabricated

short spools were covered with a thin coat of grout material.

Also, in these

same

areas

a number of fabricated stainless

steel

spools were left with openings, e.g., nipples, pipe ends unprotected

(uncapped).

In all instances

there

was

no evidence

of welding

activity in the area.

This observation

was discussed

with the

licensee

representative

who

agreed

that corrective

action

was

required.

The condition described

above

was contrary to requirements

of

Procedure

WP-113, Paragraph

3.7 which requires

component

ends to

be

plugged

or sealed

against

entry of contaminants

during the

times when the ends are not being worked on.

(3)

Document

Control -

On July 9,

1980, while observing fuel pools

liner welding activities discussed

in Paragraph

7 of this report,

the inspector noted that the weld procedure specification for the

automatic

gas tungsten arc process

(GTAW) WPS-.8BU7 used

on hori-

zontal

and vertical liner welds

was

an out-dated

Revision 2,

issue.

This had been

superseded

by Revision 3, issued

on June

18,

1980.

In discussing

this matter

the

licensee

representative

stated that failure to issue the new revision in a timely manner

was an isolated

case related to a personnel

problem which now has

been alleviated.

However,

the inspector

stated

that failure to

place the new revision into the field three

weeks after issuance

could not

be justified

on that basis.

Failure to issue

the

revised

WPS

and to recall

the

one

superseded

was contrary to

requirements of Procedure

CQA-2, Rev. 2, Paragraph 9.1, "... Proce-

dures

or portions

thereof that have

been

superseded

or voided

will be recalled or destroyed."

These

findings represent

three

(3) examples of failure to follow

procedural requirements.

Failure to accomplish activities affecting

quality in accordance with approved procedures is in noncompliance

with Criterion V of Appendix

B,

10 CFR 50

as

implemented

by

Carolina Power and Light PSAR, Section 1.8.5.5.

This noncompliance

was categorized

as

an infraction and

was identified as item 400/

80-18-01

"Failure to follow procedures

- housekeeping,

storage

and document control.

b.

Main Dam Construction Activity

The inspector

reviewed

Procedures

CQC-13,

Rev. 4,

Concrete

Control,

QCI-13.3,

Rev.

1, Concrete Field Tests

and observed

concrete

placement

on the wall lining of the spillway.

The inspector

witnessed

slump,

weight, air and temperature

checks

made by QA/QC personnel

and reviewed

related

QC/QA at the work station.

Within these

areas

the inspector

noted that the counter of truck No.

95 was inoperative.

At the time

of this discovery the first bucket of concrete

had been

drawn and was

being hoisted

to the point of placement

while the

second

bucket

was

made

ready to be filled.

Upon being notified that the counter

was

inoperative,

personnel

scrapped

the entire

load.

Discussions

with

licensee

QA representatives

disclosed

the counter

was repaired but

could not provide objective evidence for verification.

Within the

areas

inspected,

no items of noncompliance

or deviations

were identified.

c ~

NSSS Material Storage Yard (Units 1-4)

Material and components

stored in this area

were inspected in order to

ascertain

whether

storage

conditions

were consistent

with applicable

specifications

and

standards.

Components

observed

included reactor

vessels,

pressurizer

steam

generator,

coolant

pumps

and

main loop

piping.

Within the areas inspected

no items of noncompliance

were identified.

d.

Pressurizer

- Iiftand Placement (Unit 1)

On July 9,

1980, pressurizer

S/N

1641

was transported

from the

NSSS

storage

12, to the designated

area at the power block in preparation

for subsequent

placement into the pressurizer

cavity.

The transport

and lifting operation

was performed by Rigging International

(RI) with

procedures

reviewed

and

approved

by the licensee.

The licensee's

QA/QC organizations

handled all activities within the areas of their

responsibility,

e.g.,

surveillance,

inspections,

documentation

and

approval,

etc.

The inspector

observed

the transportation

and lift/

placement of the pressurizer - the latter

was performed

on July 10,

1980.

Related

records

reviewed included

QA records/reports

R-661-3,

checklists, lift, rigging, hoisting,

NDE (MT) and transporting reports

and,

NSSS checklist records.

The transfer

from storage

to the point

of liftwas performed with RI's Crawler Transporter while the lift was

performed with the Carolina Giant Crane.

Within the

areas

inspected

no items of noncompliance

or deviations

were identified.

6.

Steel Structures

and Supports Visual Examination of Welds

The containment liner is being fabricated by CBI under

CPM, contract

number

84031 in accordance

with provisions of the

ASME Code Section III, Div. 2,

Subsection

CC (74W75).

At the time of this inspection,

work had progressed

to the 15th ring.

Field welds are being fabricated thru the use of manual

shielded

metal arc

(SMAW) and semiautomatic

subarc

(SA) processes.

CBI's

Nuclear

QA Manual for ASME Section III products is the controlling document

for all site activity including weld material control,

process

control

welding and NDE.

Completed welds between ring B17 and course

Cl of the roof and those polar

crane

girder vertical support

bracket

gusset

plates

Nos.

178-128

RSL,

-113L, -112RM, -97R and -64RSL were inspected/observed

for weld finish and

appearance,

transition between plates

of differing wall thickness,

height

of reinforcement,

presence/absence

of arc strikes

and weld spatter,

exces-

sive grinding and surface defects

as applicable.

For these welds the inspector also reviewed welder performance qualification

records,

radiographs

and

MT reports

as applicable,

shop release for shipment

checklists

for the 'gusset

plates

and job site receiving inspection

and

refurbishing checklists for plates

13-C1, 14-Cl and 15-C1.

Within these

areas

the inspector noted that the toe of the transition weld

between

ring B17 and

course

Cl of the roof was rather

abrupt,.

In many

locations this condition resulted in a rather sharp notch between the toe

of the weld metal

and the chamfered plate material of the Cl course.

The

roof plate

was chamfered to accommodate

the change in plate thickness,

3/8

ring B17 and 1/2" course Cl.

The inspector discussed this matter with CBI

and CPS'epresentatives

and

expressed

concerns

over the possible

adverse

conditions that can result from notch related stresses.

The CBI representa-

tive stated that his instructions

were that the weld was acceptable

provided

the included angle between the weld metal and the base material

was greater

than

90

.

The inspector

requested

that

CBI provide the basis for this

acceptance

criterion, that additional inspections

be performed to verify

asbuilt

conditions

meet

code

requirements

and

where

warranted,

to take

appropriate

steps

to provide for a more gradual transition at this point.

The licensee

agreed

to look further into this matter and to take whatever

action

was appropriate.

This matter

was identified as inspector followup

item 400/80-18-04,

"Containment liner weld geometry".

7.

Steel Structure

and Supports - Observation of Welding Activities Outside

Containment

Welding on the liner of the south fuel pool is controlled by Ebasco Specifi-

cation

CAR-SH-AS-17, Revision 4, "Pool Liners Seismic Class I Structures".

Site procedures

used to control welding related activities include MP-07,

Rev. 6,

"General

Welding Procedure

for Stainless

Steel

Welding", MP-05,

Rev. 9, "Stamping of Weldments'

MP Oly "Qualification of Weld Procedures",

MP-03,

Rev.

8,

"Welding Material".

Welding is being performed with weld

procedure

specifications

(WPS) qualified to the latest

addenda

of ASME

Section IX in force at the

time of the qualification.

Horizontal

and

vertical welds

except for the corners

and top seams

are fabricated by the

automatic

TIG process

using the Dimetrics equipment.

Corner and top seams

are fabricated with manual

SMAW and

GTAW processes.

In process,

horizontal

vertical, corner and top seams

between elevations

261 and 286 were observed

for compliance with code

and procedural

requirements.

Welders were inter-

viewed,

equipment

were inspected

and calibration stickers

checked

as applic-

able, field QA/QC records

were checked for accuracy,

weld material quality

records

and welder performance qualification test records

were reviewed for

compliance with applicable

codes

and standards.

Within these areas the inspector noted the following:

On July 9,

1980,

the welding material

used

on the fuel pool liner

welds as documented

on weld material issue slips were as follows:

SIZE

HTj//LOTj/

308

308

308

308

3/32 II

1/8"

3/32II

045

-602571

>65325H4BD

C3017

464176

A subsequent

review of quality records disclosed

that. the material issued

to the field as

308 stainless

steel material produced

from the heats

marked

with (-") was actually 308-L (low carbon) material.

An inspection of the

rod issue station

(No. 2) that issued

the material

showed that both heats

had been marked

on the log as

308 stainless

steel material even though the

manufacturer's

containers

correctly identified the material

as extra

low

carbon

(ELC).

This finding was

discussed

with CPRL site

management

who

took immediate corrective action on the matter.

The inspector stated that

failure to maintain control of materials

was contrary to Criterion VIII of

Appendix to

10 CFR 50,

implemented

by CP&L's

PSAR Section 1.8.5.8

which

requires that ... measures

shall be designed

to prevent the use of incorrect

material ....

This finding was categorized

as

an infraction and

was

identified as item 400/80-18-02 "Weld Material Control".

8.

Other Safety-Related Piping, Visual Examination of Welds (Unit 1)

The

main

steam

safety

release

valve header

to the main steam isolation

valve welds were fabricated in the fab shop

and were completed at the time

of this inspection.

The

welds

were fabricated in accordance

with ANSI

B31.1-73Property "ANSI code" (as page type) with input value "ANSI</br></br>B31.1-73" contains invalid characters or is incomplete and therefore can cause unexpected results during a query or annotation process. with weld procedures

and welders qualified in accordance

with ASME

Section IX.

The completed welds observed/inspected

were as follows:

WELD

DESCRIPTION

SIZE

FW"282

FW-287

FW-303

Pipe to Valve j/2MS-Vl-SAB-1

Pipe to Valve f/2MS-V2-SAB-1

Pipe to Valve

$j2MS-V3-SAB-1

1.052 x 32" f

1.052 x 32" f

1.052 x 32" g

For these welds,

the inspector observed/inspected

welder and joint identifi"

cation weld finish and workmanship, transition,

weld reinforcement,

spatter

and/or arc-strikes,

condition of base metal in the heat affected

zone area

for surface

imperfections.

Performance

qualification records

of welders

with these

welds were reviewed for compliance with applicable

code require-

ments.

Within these

areas

on July 10,

1980,

the inspector

noted that in certain

cases

where welders with stencils,

e.g.,

A51 and

B87 had qualified to

a

combination procedure involving two processes,

e.g.,

GTAW/SMAW, the record

did not

show the

amount of metal deposited

by each process

as required by

QW-351 of ASME Section IX.

The inspector discussed

this matter with cogni-

zant

CPRL personnel

who agreed

to review the records of welders qualified

in this manner and revise them to show this information as required.

The inspector stated that failure to maintain sufficient records to provide

objective evidence of activities affecting their quality was in noncompliance

w'ith Criterion XVII of Appendix B to

10 CFR 50,

as

implemented

by CPM.'s

PSAR Section 1.8.5.17.

This noncompliance

was categorized

as

a deficiency

and

was identified as

item 400/80-18-03

"Welder performance qualification

records".

~1

i

aq i

~.