CRAP Carolina Power & Light Company September,12, 1980 Mr. J. P. O'Reilly Region II U. S. Nuclear Regulatory Commission 101 Marietta Street',
N. W.
Atlanta, Georgia 30303 SHEARON HARRIS NUCLEAR POWER PLANT 1, 2, 3 AND 4 DOCKET NOS
0-401, 50-402, AND 50-403 IE BULLETIN 80-
Dear Mr. O'Reilly:
As requested in IE Bulletin 80-20, Carolina Power
& Light Company (CP&L) has reviewed the design of the Shearon Harris Nuclear Power Plant (SHNPP) with regard to the use of Westinghouse Type W-2 control switches with spring return to neutral.
CP&L has determined that the subject switches are not used in safety-related applications at the SHNPP.
If you have any questions on this subject, please contact our staff.
CP&L plans no further response to this bulletin.
Yours very truly, M. A. McDuffie Senior Vice President Engineering
& Construction JJS/MAM/dk
'c:
Director, Division of Reactor Operations Inspection Office of Inspection and Enforcement United States Nuclear Regulatory Commission Washington, D. C.
20555 GPPlCIAL COI'V'~>09aoog'E(
411 Fayetteville Street
~ P. O. Box 1551
~ Raleigh, N. C. 27602